Sample PMP Exam Questions Paper 94 Answers

Hi PMP aspirants, welcome to AKVTutorials. Looking for a comprehensive set of PMP Project Management Professional practice questions that address the evolving landscape of project management technology? Emphasize benefits realization management with our PMP practice questions, ensuring your readiness to achieve project objectives and outcomes. In this article, you will get Sample PMP Exam Questions Paper 94 Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

You have a firm fixed price contract with a clause stating that all changes in the scope of work must be written. One of your team members verbally instructed the seller to add a change that resulted in a 100% task overrun. Under this situation, what conflict management strategy should you use (as the project manager) with the team member?

Option A : Punishment

Option B : Problem solving

Option C : Negotiating

Option D : Withdrawal

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Problem solving

PMP Mock Test Question No 2

While creating the agenda for a status meeting with the team, a project manager receives input from one team member that an item should be added. Another team member says the team is not ready to resolve the item during the meeting. After much discussion, the project manager decides to put the item on the agenda as an initial discussion item only. Which conflict resolution technique is the project manager using?

Option A : Compromise

Option B : Smoothing

Option C : Forcing

Option D : Withdrawal

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Compromise

PMP Practice Exam Question No 3

A project has several teams. Team C has missed several deadlines in the past. This has caused team D to have to crash the critical path several times. As the project leader for team D, you should meet with the:

Option A : manager of team D.

Option B : project manager alone.

Option C : project manager and management.

Option D : project manager and the team C leader.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

project manager and the team C leader.

PMP Mock Exam Question No 4

A project manager must publish a project schedule. Activities, start/end times and resources are identified. What should the project manager do next?

Option A : Distribute the project schedule according to the communications plan

Option B : Confirm the availability of the resources

Option C : Refine the project plan to reflect more accurate costing information

Option D : Publish a Gantt chart illustrating the timeline

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Confirm the availability of the resources

Project Management Professional Question No 5

What leadership style should you employ during the first two weeks of project planning?

Option A : Coaching

Option B : Directing

Option C : Supporting

Option D : Facilitating

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Directing

PMP Certification Prep Question No 6

 The project team is working on an important and complex project that requires a lot of coordination. Under these circumstances, the BEST strategy is to:

Option A : have a war room.

Option B : hire a contractor.

Option C : hold more meetings to get the word out.

Option D : gain extra assistance from management.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

have a war room.

PMP Exam Question No 7

The engineering resource group, a matrixed organization of which a project manager’s project team is a part, has a policy of no bonus for project work. The project manager’s current project has an aggressive timeline and a difficult technical obstacle to overcome. A new product offering is dependent on this project’s success in the current timeline. The project manager has heard grumbling from his team about the fact that they cannot be rewarded for their effort. What is the FIRST thing the project manager should do?

Option A : The project manager should evaluate if other team members from another department can help with the project.

Option B : The project manager should talk to management about changing the bonus policy or allow this project to have its own bonus system to reduce risk on his project.

Option C : The project manager should negotiate a less aggressive schedule from the client.

Option D : The project manager should talk with the team about the importance of getting this done on time and explain the company policy

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

The project manager should talk to management about changing the bonus policy or allow this project to have its own bonus system to reduce risk on his project.

PMP Exam Sample Question No 8

You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally and you do not have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance?

Option A : Referent

Option B : Expert

Option C : Penalty

Option D : Formal

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Expert

PMP Exam Practice Question No 9

Your best programmer is an independent contractor. Recently, you learned that she is working on a project in the evening for one of your competitors. Your BEST course of action is to:

Option A : Replace her.

Option B : Get her to sign a nondisclosure agreement.

Option C : Inform her that you do not allow your contractors to work with your competition, and ask her to choose.

Option D : Limit her access to sensitive data.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Get her to sign a nondisclosure agreement

PMP Certification Exam Question No 10

What is the MOST correct statement about conflict?

Option A : The primary source of conflict is personalities.

Option B : Conflict can be beneficial.

Option C : Conflict is best resolved by smoothing.

Option D : The best way to prevent conflict in the procurement process is to make sure the project manager is not involved with negotiations.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Conflict can be beneficial.

PMP Mock Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply