Hi PMP aspirants, welcome to AKVTutorials. Seeking PMP practice questions that cover the intricacies of project governance and compliance with organizational policies and procedures? Embrace technological advancements in project management with our practice questions, staying ahead in the evolving landscape of project management technology. In this article, you will get Recent PMP Exam Questions Test Paper 93. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

 Which of the following is/are input(s) for Solicitation Planning

Option A : Procurement Management Plan

Option B : Statement(s) of Work

Option C : Standard Forms

Option D : Both A and B.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Both A and B.

PMP Mock Test Question No 2

Which of the following is not a Tool and Technique for Source Selection.

Option A : Contract Negotiation

Option B : Weighting System

Option C : Evaluation Criteria

Option D : Independent Estimates

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Evaluation Criteria

PMP Practice Exam Question No 3

Which of the following is not an input to Contract Administration.

Option A : Work Result

Option B : Change Requests

Option C : Seller Invoices

Option D : All of them are inputs to Contract Administration.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

All of them are inputs to Contract Administration.

PMP Mock Exam Question No 4

____________________ involves clarification and mutual agreement on the structure and
requirements of the contract prior to the signing of the contract.

Option A : Screening System

Option B : Evaluation Criteria

Option C : Contract Negotiation

Option D : Weighting System

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Contract Negotiation

Project Management Professional Question No 5

Make or Buy Analysis is a Tool and Technique for

Option A : Procurement Planning

Option B : Solicitation Planning

Option C : Solicitation

Option D : Source selection

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Procurement Planning

PMP Certification Prep Question No 6

The process of obtaining quotations, bids, offers or proposals as appropriate is called

Option A : Procurement Planning

Option B : Solicitation Planning

Option C : Solicitation

Option D : Source Selection

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Solicitation

PMP Exam Question No 7

On his first project assignment as the project manager, the project manager encounters disagreements among highly technical team members. How would the project manager BEST deal with the conflict?

Option A : He should listen to the differences of opinions, determine what is the best choice and implement that choice.

Option B : He should postpone further discussions, meet with each individual, and determine the best approach.

Option C : He should listen to the differences of opinions, encourage logical discussions, and facilitate an agreement.

Option D : He should help the team focus on agreeable aspects of their opinions and build unity by using relaxation techniques and common focus team building.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

He should listen to the differences of opinions, encourage logical discussions, and facilitate an agreement.

PMP Exam Sample Question No 8

Giving a team member a corner office is different than giving him health benefits because a corner office is a(n):

Option A : Perquisite

Option B : Fringe benefit

Option C : use of the expectancy theory.

Option D : example of formal power.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Perquisite

PMP Exam Practice Question No 9

 Team members are arguing about the location of specification limits on a control chart. The discussion is becoming heated when the project manager walks in and says, “It seems that the real problem here is that we do not have enough information about the customer’s specifications. Let’s, “this is an example of “

Option A : asserting the project manager’s authority

Option B : problem solving

Option C : compromising

Option D : withdrawal

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

problem solving

PMP Certification Exam Question No 10

During project planning in a matrix organization, the project manager determines that additional human resources are needed. From whom would he request these resources?

Option A : Project manager

Option B : Functional manager

Option C : Team

Option D : Project sponsor

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Functional manager

PMP Exam Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply