Project Management Practice Questions CAPM PMP Certification Exams Paper 92

Hi PMP aspirants, welcome to AKVTutorials. In need of practice questions that assess your knowledge of various project management methodologies, including agile, waterfall, and hybrid approaches? Uphold project governance and compliance standards with our PMP Project Management Professional practice questions, ensuring alignment with organizational policies. In this article, you will get Project Management Practice Questions CAPM PMP Certification Exams Paper 92. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

In which phase feasibility studies performed

Option A : Initiation

Option B : Planning

Option C : Executing

Option D : Closing

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Initiation

PMP Mock Test Question No 2

You are asked to take over a project with lot of pending scope change requests. To assess the change impact, you should get hold of

Option A : Scope statement

Option B : WBS

Option C : Project Plan

Option D : Scope Management Plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

WBS

PMP Practice Exam Question No 3

A matrix organization begins a new project. Project manager knows that the team is more responsive to their functional managers than to PM. To overcome this, PM decides to prepare

Option A : Project plan

Option B : Project charter

Option C : Scope statement

Option D : Human resource management plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Project charter

PMP Mock Exam Question No 4

 Which of the following is a good objective?

Option A : Construct a building

Option B : Implement a new telecommunication system

Option C : Lay 200 bricks by tomorrow

Option D : Develop a program for proving network maintenance

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Lay 200 bricks by tomorrow

Project Management Professional Question No 5

 Scope changes on project are inevitable, however, scope changes can be minimized by:

Option A : Spending more time developing the scope baseline

Option B : Spending more time analyzing the estimates

Option C : Asking the sponsor to actively participate in the planning

Option D : A and B

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Asking the sponsor to actively participate in the planning

PMP Certification Prep Question No 6

A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

Option A : Change the scope baseline

Option B : Prepare a variance report

Option C : Call a meeting of the change control board

Option D : Change the project’s objectives

Option E : Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Call a meeting of the change control board

PMP Exam Question No 7

Which of the following is not a major process of Project Procurement Management?

Option A : Solicitation Planning

Option B : Source Selection

Option C : Contract Administration

Option D : Information Distribution

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Solicitation Planning

PMP Exam Sample Question No 8

The process of identifying which project needs can be best met by procuring products or services outside the project organization is called ________________

Option A : Needs Identification

Option B : Procurement Planning

Option C : Requirement Analysis

Option D : None of the above 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Procurement Planning

PMP Exam Practice Question No 9

The ‘Product Description’ is generally broader than a ‘Statement of Work’. This statement

Option A : Is True

Option B : Is False

Option C : Is Ambiguous

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Is True

PMP Certification Exam Question No 10

A contract that involves payment to the seller for its actual costs is called a

Option A : Fixed Price Contract

Option B : Cost Reimbursable Contract

Option C : Unit Price Contract

Option D : Partnership

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Cost Reimbursable Contract

PMP Mock Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply