Hi PMP aspirants, welcome to AKVTutorials. In need of practice questions that assess your knowledge of various project management methodologies, including agile, waterfall, and hybrid approaches? Uphold project governance and compliance standards with our PMP Project Management Professional practice questions, ensuring alignment with organizational policies. In this article, you will get Project Management Practice Questions CAPM PMP Certification Exams Paper 92. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
In which phase feasibility studies performed
Option A : Initiation
Option B : Planning
Option C : Executing
Option D : Closing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Initiation
PMP Mock Test Question No 2
You are asked to take over a project with lot of pending scope change requests. To assess the change impact, you should get hold of
Option A : Scope statement
Option B : WBS
Option C : Project Plan
Option D : Scope Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
WBS
PMP Practice Exam Question No 3
A matrix organization begins a new project. Project manager knows that the team is more responsive to their functional managers than to PM. To overcome this, PM decides to prepare
Option A : Project plan
Option B : Project charter
Option C : Scope statement
Option D : Human resource management plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Project charter
PMP Mock Exam Question No 4
Which of the following is a good objective?
Option A : Construct a building
Option B : Implement a new telecommunication system
Option C : Lay 200 bricks by tomorrow
Option D : Develop a program for proving network maintenance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Lay 200 bricks by tomorrow
Project Management Professional Question No 5
Scope changes on project are inevitable, however, scope changes can be minimized by:
Option A : Spending more time developing the scope baseline
Option B : Spending more time analyzing the estimates
Option C : Asking the sponsor to actively participate in the planning
Option D : A and B
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Asking the sponsor to actively participate in the planning
PMP Certification Prep Question No 6
A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
Option A : Change the scope baseline
Option B : Prepare a variance report
Option C : Call a meeting of the change control board
Option D : Change the project’s objectives
Option E : Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Call a meeting of the change control board
PMP Exam Question No 7
Which of the following is not a major process of Project Procurement Management?
Option A : Solicitation Planning
Option B : Source Selection
Option C : Contract Administration
Option D : Information Distribution
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Solicitation Planning
PMP Exam Sample Question No 8
The process of identifying which project needs can be best met by procuring products or services outside the project organization is called ________________
Option A : Needs Identification
Option B : Procurement Planning
Option C : Requirement Analysis
Option D : None of the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Procurement Planning
PMP Exam Practice Question No 9
The ‘Product Description’ is generally broader than a ‘Statement of Work’. This statement
Option A : Is True
Option B : Is False
Option C : Is Ambiguous
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Is True
PMP Certification Exam Question No 10
A contract that involves payment to the seller for its actual costs is called a
Option A : Fixed Price Contract
Option B : Cost Reimbursable Contract
Option C : Unit Price Contract
Option D : Partnership
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Cost Reimbursable Contract