Hi PMP aspirants, welcome to AKVTutorials. Seeking PMP practice questions to fine-tune your Project Management Professional skills? Ignite your PMP aspirations with our Practice Questions—your gateway to mastering Project Management Professional principles. In this article, you will get Practice PMP Exam Questions Test 52 with Answer Explanation. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
A project manager is creating a procurement management plan for a project that involves implementing software that will be used to track and follow up on sales leads. Which of the following would not be included in that document?
Option A : The criteria that will be used when determining which vendor to select
Option B : The roles and responsibilities related to the procurement
Option C : An explanation of how vendor performance will be monitored and measured
Option D : A list of pre-qualified sellers, if any
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
The criteria that will be used when determining which vendor to select
PMP Mock Test Question No 2
Which of the following is true about scope management on agile projects?
Option A : Scope would only change when a change request is approved
Option B : Scope is defined at the beginning of the project
Option C : Project scope includes the features and functions of the project
Option D : Scope is approved at the start of each iteration
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project scope includes the features and functions of the project
PMP Practice Exam Question No 3
At this point on your project, you are in the process of reviewing and approving change requests and then communicating those decisions to your stakeholders. Which of the following are inputs of that process?
Option A : Project Management Plan, Work Performance Reports, Change Requests
Option B : Project Charter, Change Requests, Agreements
Option C : Work Performance Reports, Work Performance Information, Project Documents
Option D : Change Requests, Project Management Plan, Approved Changed Requests
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Change Requests, Project Management Plan, Approved Changed Requests
PMP Mock Exam Question No 4
All of the following are true about fixed price with economic price adjustment (FP-EPA) contracts except:
Option A : The price is set at the start of the contract.
Option B : There may be price adjustments over time based on changes to certain financial indices.
Option C : They are often used when a contract is several years in length.
Option D : The duration and scope can be left open-ended.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
The price is set at the start of the contract.
Project Management Professional Question No 5
A project manager is working with a team to automate several manufacturing steps at a tire production plant. At this point, she needs to understand what process should be used when the project team (or stakeholders) need to escalate concerns. Which document should be reviewed to find this information?
Option A : Risk Management Plan
Option B : Stakeholder Register
Option C : Communications Management Plan
Option D : Stakeholder Engagement Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project schedule
PMP Certification Prep Question No 6
A project to construct a bypass has the goal of easing traffic congestion near a large city. During the project, the team spends time communicating with their stakeholders and addressing their issues and concerns. In this scenario, what process is being performed?
Option A : Manage Stakeholder Engagement
Option B : Monitor Stakeholder Engagement
Option C : Manage Communications
Option D : Plan Stakeholder Engagement
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Monitor Stakeholder Engagement
PMP Exam Question No 7
Your project team has been tasked with designing a new, more fuel-efficient truck. At this time, the team is implementing risk responses. In doing so, which of the following activities might they perform?
Option A : Exploring options for addressing risks that have been previously identified.
Option B : Evaluating whether or not risks responses have been effective.
Option C : Performing sensitivity analysis and displaying the results using a tornado diagram.
Option D : Taking action to increase the likelihood that opportunities on the project occur.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Performing sensitivity analysis and displaying the results using a tornado diagram.
PMP Exam Sample Question No 8
An issue will cause the project team to miss a critical milestone. The project manager realizes that this issue could have been avoided if the risk had been addressed earlier. What should the project manager do next?
Option A : Hold a meeting with the sponsor and key stakeholders to inform them of the issue.
Option B : Consult with the team and update the project management plan based on their inputs.
Option C : Create and submit a change request that includes a recommendation for corrective action.
Option D : Taking action to increase the likelihood that opportunities on the project occur.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Taking action to increase the likelihood that opportunities on the project occur.
PMP Exam Practice Question No 9
A project manager is preparing a cost management plan for a project that includes constructing a hanger for military aircrafts. Which of the following would not be included in that document?
Option A : An explanation of how earned value management will be used on the project
Option B : The format for reporting cost performance
Option C : The degree of cost variance that would be acceptable before action needs to be taken
Option D : The basis of estimates that provides additional detail and supports cost estimate
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The degree of cost variance that would be acceptable before action needs to be taken
PMP Certification Exam Question No 10
On a given project; earned value (EV) is $30,000; actual cost (AC) is $35,000; and planned value (PV) is $28,000. What is the cost variance (CV)?
Option A : $2,000
Option B : -$5,000
Option C : $5,000
Option D : -$2,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
-$2,000