Hi PMP aspirants, welcome to AKVTutorials. Ready to evaluate your understanding of project closure processes with PMP Project Management Professional practice questions? Gain proficiency in various project management methodologies with our practice questions, covering agile, waterfall, and hybrid approaches for comprehensive preparation. In this article, you will get PMP Sample Test Questions Paper 91 with Explanations. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
The first step in WBS creation is
Option A : Determine cost and duration of each project deliverable
Option B : Identify major deliverables of the project
Option C : Identify components of each deliverable of the project
Option D : Determine the key tasks to be performed
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Determine cost and duration of each project deliverable
PMP Mock Test Question No 2
Work package is a
Option A : Element at the lowest level of WBS
Option B : Task with unique identifier
Option C : Required level of reporting
Option D : Task that can be assigned to only one person
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Element at the lowest level of WBS
PMP Practice Exam Question No 3
Going from Level 3 to Level 4 in the work breakdown structure can result in:
Option A : Less estimating accuracy
Option B : Better control of the project
Option C : Lower status reporting costs
Option D : A greater likelihood that something will fall through the cracks
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Better control of the project
PMP Mock Exam Question No 4
A project manager believes that modifying the scope of the project may provide added value
for the customer. The project manager should:
Option A : Change the scope baseline
Option B : Prepare a variance report
Option C : Discuss it in the change control board
Option D : Change the project’s objectives
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Discuss it in the change control board
Project Management Professional Question No 5
Inspection is used for both Scope Verification and Quality Control. But first deals with — of the work while second deals with — of the product
Option A : Testing, quality
Option B : Correctness, acceptance
Option C : Inspection, testing
Option D : Acceptance, correctness
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Acceptance, correctness
PMP Certification Prep Question No 6
A Project Charter includes
Option A : Precedence diagramming methods
Option B : Task estimates
Option C : Detailed resource estimates
Option D : The business need for the project
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The business need for the project
PMP Exam Question No 7
The customer wants to make a major change in the project scope when project is mostly complete. The project manager should.
Option A : Make the change
Option B : Inform the customer of the impact of the change
Option C : Refuse the change
Option D :Complain to management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Inform the customer of the impact of the change
PMP Exam Sample Question No 8
The key reason to use a WBS is to
Option A : Organize the work
Option B : Prevent work from slipping through the cracks
Option C : Provide a basis for estimating the project
Option D : All of the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
All of the above
PMP Exam Practice Question No 9
What does having a project charter do for the project managers?
Option A : Describes the details of what needs to be done
Option B : Describes the names of all team members
Option C : Gives the project manager authority
Option D : Describes the project’s history
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Gives the project manager authority
PMP Certification Exam Question No 10
The subdivision of project deliverables into smaller components is called
Option A : Concept definition
Option B : Flow charting
Option C : Scope definition
Option D : Scope verification
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Scope definition