PMP Sample Exam Mock Test 38 Questions With Explanations

Hi PMP aspirants, welcome to AKVTutorials. Are you exploring PMP Project Management Professional practice questions that focus on the application of earned value management for performance measurement? Apply earned value management effectively with our PMP Project Management Professional practice questions, ensuring accurate project performance measurement. In this article, you will get PMP Sample Exam Mock Test 38 Questions With Explanations. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

You are running a project to develop the production process for a future electronic component. Evaluating some first test batches, you found out that the precision is generally quite good, but that you have some irregular outliers in an increasing frequency. You believe that motivators in use for workers making the batches are losing their effectiveness and complacency creeps in. According to D. Pink. which motivators are least likely to lose effectiveness?

Option A : Extrinsic motivators 

Option B : Intrinsic motivators 

Option C : Hygiene factors 

Option D : Salary

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Intrinsic motivators 

PMP Mock Test Question No 2

As a leader, how should you deem ethical conduct?

Option A : You should ensure ethical conduct throughout the team by use of means including recognition and awards and in tight cooperation with the team members’ line managers.

Option B : Ethical conduct is all right as long as it does not impact the achievement of objectives and does not damage the performing organization’s immediate options for profits.

Option C : You are the role model for the team. Your personal integrity demonstrates the desired skills, behavior, and attitudes whose adoption may benefit team members. 

Option D : There are often dilemma situations in business. Then you may have to suspend your integrity and do what is appropriate. There may be long term negative effects, but these are not your responsibility

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

You are the role model for the team. Your personal integrity demonstrates the desired skills, behavior, and attitudes whose adoption may benefit team members.

PMP Practice Exam Question No 3

You have recently been named as the manager of a new project under contract. The sponsor of the project gave you the contract signed by the customer and a statement of work. He asked you to go on with initiation. Which document should you develop next?

Option A : Project management plan 

Option B : Milestone schedule

Option C : Project charter 

Option D : Scope statement 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project charter

PMP Mock Exam Question No 4

When is passive risk acceptance an appropriate approach?

Option A : When the likeliness of risk occurrence is very low. 

Option B : When the risk occurrence is hard to identify. 

Option C : When it is best to deal with a risk as it occurs. 

Option D : When the risk cannot be assessed or analyzed.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

When it is best to deal with a risk as it occurs. 

Project Management Professional Question No 5

You are running a project to engineer and implement a set of business processes and a software solution for customer relationship management. The project involves a big number of performing organizations―a major corporation and many suppliers of different sizes. During the project you observed a restraining effect of differences between the companies’ corporate cultures. This leads to different expectations on how such a project should be handled and to frequent misunderstandings between stakeholders. Another effect is a growing degree of distrust and skepticism. What should you try first to integrate the diverse stakeholder groups?

Option A : Focus on project work. As a project manager you should not get distracted by big egos. 

Option B : Let the problems grow further until they are obvious for all. Then escalate them. 

Option C : Develop a joint quality policy for the project and seek commitment by all organizations. 

Option D : Analyze probability and impact of the risks linked with the situation and plan how to respond to them

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Develop a joint quality policy for the project and seek commitment by all organizations. 

PMP Certification Prep Question No 6

During execution of your project you have observed that a team member is getting isolated by other team members. Which is a wrong approach in such a situation?

Option A : The interpersonal relationships between team members are their private issue. You should not interfere. 

Option B : You should apply team building measures to improve the team’s effectiveness.

Option C : You should try to get feedback from the isolated team member to understand the situation.

Option D : You should try to get feedback from the other team members to understand the situation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

The interpersonal relationships between team members are their private issue. You should not interfere

PMP Exam Question No 7

In an organization, project managers report directly to the head of a project management office (PMO). In this case, which statement is probably not true?

Option A : The head of the project management office can strengthen the matrix as a manager of project managers. 

Option B : The project management office will actually be responsible for direct management of the projects.

Option C : Projects will be run by the functional organization and project managers expedite change control. 

Option D : It will be easier for the PMO to ensure that the organizational process assets provided are used.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Projects will be run by the functional organization and project managers expedite change control.

PMP Exam Sample Question No 8

During a project, you applied a series of measurements relating to team performance and product performance. You were warned that the act of measurement may influence the outcomes. What is this measurement pitfall referred to?

Option A : Hawthorne effect 

Option B : Confirmation bias 

Option C : Correlation vs. causation 

Option D : Root cause analysis

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Hawthorne effect 

PMP Exam Practice Question No 9

The use of scarce resources must be decided upon with functional managers before it causes delays in your project. Which is probably your most important skill right now?

Option A : Planning

Option B : Negotiating 

Option C : Facilitating

Option D : Documenting

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Negotiating 

PMP Certification Exam Question No 10

Which question is not appropriate for a weighting system to evaluate seller’s performance according to weighted criteria?

Option A : What is the yearly investment in development of personnel per year and employee?

Option B : How many reference customers have been verified by the seller in the specific field?

Option C : What financial status and reputation in the market place could be assessed? 

Option D : Has a CV of the prospective project manager been sent with the proposal?

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Has a CV of the prospective project manager been sent with the proposal?

Questions Bank For The PMP Exam

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122