Hi PMP aspirants, welcome to AKVTutorials. In need of PMP Project Management Professional practice questions that explore the role of the project manager in conflict resolution and stakeholder collaboration? Resolve conflicts and collaborate with stakeholders effectively using our practice questions, reflecting the role of the project manager in fostering positive team dynamics. In this article, you will get PMP Practice Exam Questions Practice Test 47. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

On a given project, the budget at completion (BAC) is $1,00,000. If your current estimate at completion (EAC) is $1,100,000; what is the variance at completion (VAC)?

Option A : -$100,000 

Option B : $1,100,000 

Option C : -$1,100,000 

Option D : $100,000

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

-$100,000 

PMP Mock Test Question No 2

A project to widen broadband access in Poland was undertaken to fulfill a politician’s campaign promise. During the project, the team spends time prioritizing risks by evaluating their probability and impact. What is a tool or technique that may be needed to perform this process?

Option A : Sensitivity Analysis 

Option B : Simulations 

Option C : Organizational Process Assets 

Option D : Risk Probability & Impact Assessment

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Risk Probability & Impact Assessment

PMP Practice Exam Question No 3

A project to construct a grocery store that will specialize in organic foods is underway. Currently, the team is performing the collect requirements process. In doing so, which of the following activities might they complete?

Option A : Determining which of the documented requirements will be completed as part of the project. 

Option B : Meeting with stakeholders to capture their needs and to ensure they are measureable. 

Option C : Splitting the work of the project to make it easier to manage and monitor. 

Option D : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Meeting with stakeholders to capture their needs and to ensure they are measureable. 

PMP Mock Exam Question No 4

A project manager on a software development project was asked by her client to add another feature. (This occurred after the scope had been baselined.) She reviewed the request, assessed the impact, and received approval to update the scope. In this scenario, which of the following processes were used?

Option A : Direct and Manage Project Work 

Option B : Manage Project Knowledge 

Option C : Perform Integrated Change Control 

Option D : Monitor and Control Project Work

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Perform Integrated Change Control 

Project Management Professional Question No 5

Jose is developing the schedule on a project that involves renovating dorms at a nearby university. In order to complete that process, he needs to identify the early and late start and finish dates of activities. Which tool or technique would accomplish this task?

Option A : Leads & Lags

Option B : Critical Path Method

Option C : Schedule Compression 

Option D : Schedule Network Analysis

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Schedule Network Analysis

PMP Certification Prep Question No 6

A project to recall a car part that was found to be defective has nearly begun. Currently, the team is performing the develop project charter process. In doing so, which of the following activities might they complete?

Option A : Coordinating and consolidating various plans that will be baselined and placed under formal change control procedures. 

Option B : Considering positive and negative experiences from previous projects to increase the likelihood of success on the current project. 

Option C : Developing a document that, when approved, will allow the project manager to use organizational resources to complete the project.

Option D : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Developing a document that, when approved, will allow the project manager to use organizational resources to complete the project.

PMP Exam Question No 7

A project manager is creating a quality management plan for a project that involves creating a dashboard that will be used to report on several of the company’s key performance indicators. Which of the following would not be included in that document?

Option A : The roles and responsibilities of those who will perform quality management on the project 

Option B : A list of all the quality management issues that were escalated by the team 

Option C : The process for dealing with defects in project deliverables when they are identified 

Option D : The list of project deliverables that will be subject to a quality review

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

A list of all the quality management issues that were escalated by the team 

PMP Exam Sample Question No 8

Elizabeth is estimating costs on a project that involves deploying asset management software to track technology equipment at an aerospace company. She decides to aggregate estimates of low-level WBS components to generate the estimate. In this case, what estimating technique is being used?

Option A : Bottom-Up Estimating 

Option B : Analogous Estimating 

Option C : Parametric Estimating 

Option D : Three-Point Estimating

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Bottom-Up Estimating 

PMP Exam Practice Question No 9

Which of the following is not true about cost management on agile projects?

Option A : Detailed estimates are primarily for near-term planning

Option B : Lightweight estimates may provide fast, high-level estimates of overall project costs. 

Option C : Detailed estimates are utilized at the start of the project to determine total project costs. 

Option D : Lightweight estimates are for long-term planning.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Detailed estimates are utilized at the start of the project to determine total project costs.

PMP Certification Exam Question No 10

While performing schedule management on your project, you need to determine the relationships between activities so that those activities are sequenced in the proper order. Which of the following is not true about activity sequencing?

Option A : It involves identifying and documenting relationships among tasks. 

Option B : It defines the logical sequence of work given certain constraints. 

Option C : All tasks (including the first and the last) must have both a predecessor and a successor. 

Option D : Sequencing can be done manually by hand or automatically using software.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

All tasks (including the first and the last) must have both a predecessor and a successor.

Free PMP Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply