Hi PMP aspirants, welcome to AKVTutorials. In need of PMP Project Management Professional practice questions that explore the role of the project manager in conflict resolution and stakeholder collaboration? Resolve conflicts and collaborate with stakeholders effectively using our practice questions, reflecting the role of the project manager in fostering positive team dynamics. In this article, you will get PMP Practice Exam Questions Practice Test 47. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
On a given project, the budget at completion (BAC) is $1,00,000. If your current estimate at completion (EAC) is $1,100,000; what is the variance at completion (VAC)?
Option A : -$100,000
Option B : $1,100,000
Option C : -$1,100,000
Option D : $100,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
-$100,000
PMP Mock Test Question No 2
A project to widen broadband access in Poland was undertaken to fulfill a politician’s campaign promise. During the project, the team spends time prioritizing risks by evaluating their probability and impact. What is a tool or technique that may be needed to perform this process?
Option A : Sensitivity Analysis
Option B : Simulations
Option C : Organizational Process Assets
Option D : Risk Probability & Impact Assessment
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Risk Probability & Impact Assessment
PMP Practice Exam Question No 3
A project to construct a grocery store that will specialize in organic foods is underway. Currently, the team is performing the collect requirements process. In doing so, which of the following activities might they complete?
Option A : Determining which of the documented requirements will be completed as part of the project.
Option B : Meeting with stakeholders to capture their needs and to ensure they are measureable.
Option C : Splitting the work of the project to make it easier to manage and monitor.
Option D : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Meeting with stakeholders to capture their needs and to ensure they are measureable.
PMP Mock Exam Question No 4
A project manager on a software development project was asked by her client to add another feature. (This occurred after the scope had been baselined.) She reviewed the request, assessed the impact, and received approval to update the scope. In this scenario, which of the following processes were used?
Option A : Direct and Manage Project Work
Option B : Manage Project Knowledge
Option C : Perform Integrated Change Control
Option D : Monitor and Control Project Work
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Perform Integrated Change Control
Project Management Professional Question No 5
Jose is developing the schedule on a project that involves renovating dorms at a nearby university. In order to complete that process, he needs to identify the early and late start and finish dates of activities. Which tool or technique would accomplish this task?
Option A : Leads & Lags
Option B : Critical Path Method
Option C : Schedule Compression
Option D : Schedule Network Analysis
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Schedule Network Analysis
PMP Certification Prep Question No 6
A project to recall a car part that was found to be defective has nearly begun. Currently, the team is performing the develop project charter process. In doing so, which of the following activities might they complete?
Option A : Coordinating and consolidating various plans that will be baselined and placed under formal change control procedures.
Option B : Considering positive and negative experiences from previous projects to increase the likelihood of success on the current project.
Option C : Developing a document that, when approved, will allow the project manager to use organizational resources to complete the project.
Option D : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Developing a document that, when approved, will allow the project manager to use organizational resources to complete the project.
PMP Exam Question No 7
A project manager is creating a quality management plan for a project that involves creating a dashboard that will be used to report on several of the company’s key performance indicators. Which of the following would not be included in that document?
Option A : The roles and responsibilities of those who will perform quality management on the project
Option B : A list of all the quality management issues that were escalated by the team
Option C : The process for dealing with defects in project deliverables when they are identified
Option D : The list of project deliverables that will be subject to a quality review
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
A list of all the quality management issues that were escalated by the team
PMP Exam Sample Question No 8
Elizabeth is estimating costs on a project that involves deploying asset management software to track technology equipment at an aerospace company. She decides to aggregate estimates of low-level WBS components to generate the estimate. In this case, what estimating technique is being used?
Option A : Bottom-Up Estimating
Option B : Analogous Estimating
Option C : Parametric Estimating
Option D : Three-Point Estimating
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Bottom-Up Estimating
PMP Exam Practice Question No 9
Which of the following is not true about cost management on agile projects?
Option A : Detailed estimates are primarily for near-term planning
Option B : Lightweight estimates may provide fast, high-level estimates of overall project costs.
Option C : Detailed estimates are utilized at the start of the project to determine total project costs.
Option D : Lightweight estimates are for long-term planning.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Detailed estimates are utilized at the start of the project to determine total project costs.
PMP Certification Exam Question No 10
While performing schedule management on your project, you need to determine the relationships between activities so that those activities are sequenced in the proper order. Which of the following is not true about activity sequencing?
Option A : It involves identifying and documenting relationships among tasks.
Option B : It defines the logical sequence of work given certain constraints.
Option C : All tasks (including the first and the last) must have both a predecessor and a successor.
Option D : Sequencing can be done manually by hand or automatically using software.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
All tasks (including the first and the last) must have both a predecessor and a successor.