Hi PMP aspirants, welcome to AKVTutorials. In need of PMP exam preparation resources that include practice questions covering the principles of leadership and team motivation? Achieve integration mastery with our PMP Project Management Professional practice questions, a resource designed to enhance your understanding of this knowledge area. In this article, you will get PMP Project Management Professional Certification Exam Test 87 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Should historical information be used during resource planning?
Option A : no, since there is rarely any correlation between resource expectations on one project when compared to another.
Option B : Yes, as historical information is available can provide insight into what type of resources were required on previous projects of similar nature.
Option C : No, since historical information is usually misleading, given the cost of resources have undoubtedly changed since the completion of the prior project.
Option D : .Yes ,since historical information can be easily adjusted to accurately determined current project costs.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Yes, as historical information is available can provide insight into what type of resources were required on previous projects of similar nature.
PMP Mock Test Question No 2
Analogous estimating is a :
Option A : ”bottom-up” estimating technique.
Option B : ”drop-down” estimating technique.
Option C : more costly and more accurately estimating technique.
Option D : technique used when you have no subject matter experts available.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
”drop-down” estimating technique.
PMP Practice Exam Question No 3
Cost estimates:
Option A : are usually presented at a detailed level.
Option B : can be presented in summary of detail.
Option C : are summarized for senior management.
Option D : are provided in detail for senior management.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
can be presented in summary of detail.
PMP Mock Exam Question No 4
In cost monitoring, the s-curve depicts the relation between:
Option A : Schedule completion and time.
Option B : Cumulative value and time.
Option C : Schedule completion and value resources.
Option D : resources and time
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Cumulative value and time.
Project Management Professional Question No 5
In order to produce a cost base line, the project manager requires
Option A : Work packages, work breakdown structure and project schedule
Option B : cost estimates, work breakdown structure and the project schedule.
Option C : cost estimates, work packages `and project schedule.
Option D : cost estimates ,work packages and work breakdown structure
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
cost estimates, work breakdown structure and the project schedule.
PMP Certification Prep Question No 6
Which of the following is an indirect cost?
Option A : Units of Production.
Option B : Lights in the Project War Room
Option C : Tax cost of Salary of project developers.
Option D : Paper purchased by the project.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Units of Production.
PMP Exam Question No 7
Which of the following method is not a depreciation method ?
Option A : Units of production.
Option B : Some of year’s digits
Option C : Declining balance
Option D : Straight line
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Some of year’s digits
PMP Exam Sample Question No 8
An ordered of magnitude estimate is not also known as
Option A : a control estimate.
Option B : a ball park estimate.
Option C : a conceptual estimate
Option D : a preliminary estimate.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
a control estimate.
PMP Exam Practice Question No 9
When the expected cash flow s –curve is above the cost performance base line the project manager should
Option A : investigate the variance to determine if corrective reaction is required.
Option B : bring the situation to the attention of senior management for action.
Option C : adjust the cost baseline to reflect the actual cost to this point.
Option D : do nothing since the project is performing above plan.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
investigate the variance to determine if corrective reaction is required.
PMP Certification Exam Question No 10
Cost estimates may also be expressed in hours days etc. as long as
Option A : it does not result in a misstatement of project cost.
Option B : the program manager agrees.
Option C : the unit of measure is consistent within the project.
Option D : the project manager agrees.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
it does not result in a misstatement of project cost.