PMP Exam Test Paper 83 Questions With Answers

Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want practice questions that align with the agile mindset and principles? Propel yourself toward PMP success by practicing with our updated questions, aligning with the latest changes in the Project Management Professional exam content. In this article, you will get PMP Project Management Professional Certification Exam Test 83 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Which of the following is not a type of baseline from which to measure change? 

Option A : Project plan 

Option B : WBS 

Option C : Operational definitions 

Option D : Project schedule

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Operational definitions 

PMP Mock Test Question No 2

There are three outputs that are common to scope, schedule and cost control processes. Which of the following is not a common output to these control processes? 

Option A : Baseline updates/changes

Option B : Lessons learned 

Option C : Corrective action

Option D : Process adjustments

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Process adjustments 

PMP Practice Exam Question No 3

Performance reports are an input to overall change control. Which of the following statements is not necessarily true about performance reports?

Option A : They provide information on past project performance 

Option B : They provide information on current status 

Option C : They may alert the team to potential future problems 

Option D : They are the outcome of project reviews 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

They are the outcome of project reviews 

PMP Mock Exam Question No 4

You are continually faced with tasks coming in late because your resources are being pulled off to handle other “urgent” situatins. You have set up a conference with several of the managers who have been doing this on a regular basis. What technique might you use to alleviate the current situation? 

Option A : Forcing 

Option B : Problem solving 

Option C : Smoothing

Option D : Ignoring

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Problem solving 

Project Management Professional Question No 5

In a team meeting, two of the managers start a discussion that escalates into an argument. In order to restore peace to the meeting you point out the part of the conflict that they both agree to and using friendly tones try to defuse the current situation. This is an example of what type of conflict management? 

Option A : Smoothing 

Option B : Problem solving 

Option C : Withdrawal 

Option D : Compromising 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Smoothing 

PMP Certification Prep Question No 6

A WBS provides a framework from which all of the following can be done except: 

Option A : All tasks to be performed can be identified and resources allocated to them 

Option B : Once resource levels have been allocated to tasks, estimates of task duration can be made 

Option C : A network diagram, illustrating task dependencies, can be constructed 

Option D : All cost and resource allocations can be totaled to develop the overall project budget 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A network diagram, illustrating task dependencies, can be constructed

PMP Exam Question No 7

A WBS provides a framework from which all of the following can be done except: 

Option A : A network diagram, illustrating task dependencies, can be constructed 

Option B : All cost and resource allocations can be totaled to develop the overall project budget. 

Option C : Performance can be tracked against the identified cost, schedule, and resource allocations 

Option D : Assignment of responsibility for each element can be made

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

A network diagram, illustrating task dependencies, can be constructed 

PMP Exam Sample Question No 8

Part of being a project manager involves dealing with conflict. According to John Adams, Ph.D., there are five methods for dealing with conflict. Some of them are used for temporary fixes, some provide more permanent resolutions. Which of the following is used for temporary resolution?

Option A : Smoothing 

Option B : Problem solving

Option C : Forcing 

Option D : Compromising 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Smoothing 

PMP Exam Practice Question No 9

A Work Breakdown Structure provides a framework from which all of the following can be done except: 

Option A : Task durations can be used in developing a working schedule for the project 

Option B : A network diagram, illustrating task dependencies, can be constructed 

Option C : Performance can be tracked against the identified cost, schedule, and resource allocations 

Option D : Assignment of responsibility for each element can be made 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

A network diagram, illustrating task dependencies, can be constructed 

PMP Certification Exam Question No 10

Which of the following is least likely to be a source of conflict in a matrix environment? 

Option A : Competing priorities between the project and functional manager 

Option B : Competing for resources between the functional and project manager 

Option C : Project team member working at a different site than the project manager 

Option D : Ambiguous lines of authority between the functional and project manager

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project team member working at a different site than the project manager 

Project Management Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply