PMP Exam Sample Questions Paper 84 with Answers Keys

Hi PMP aspirants, welcome to AKVTutorials. Seeking a reliable source of PMP practice questions to reinforce your understanding of project resource management and team dynamics? Secure your PMP success by mastering risk management with our practice questions, focusing on this critical aspect of Project Management Professional certification. In this article, you will get PMP Exam Sample Questions Paper 84 with Answers Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

.Which of the following is not provided by the framework of a Work Breakdown structure? 

Option A : All tasks to be performed can be identified and resources allocated to them 

Option B : Once resource levels have been allocated to tasks, estimates of task duration can be made

Option C : A network diagram, illustrating task dependencies, can be constructed 

Option D : All cost and resource allocations can be totaled to develop the overall project budget

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A network diagram, illustrating task dependencies, can be constructed 

PMP Mock Test Question No 2

According to James P. Lewis, which of the following is not provided by the framework of a Work Breakdown structure?

Option A : network diagram, illustrating task dependencies, can be constructed 

Option B : All cost and resource allocations can be totaled to develop the overall project budget. 

Option C : Performance can be tracked against the identified cost, schedule, and resource allocations 

Option D : Assignment of responsibility for each element can be made 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

network diagram, illustrating task dependencies, can be constructed 

PMP Practice Exam Question No 3

As a project manager in a project organization you are constantly dealing with conditions that breed conflict as you execute your project. Which of the following is not a condition of conflict in a project organization? 

Option A : High stress 

Option B : Multiple bosses 

Option C : Ambiguous roles 

Option D : Low position power

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Low position power

PMP Mock Exam Question No 4

You are in the implementation phase of a project. At this point, which of the following is the lowest source of conflict for you? 

Option A : Conflict over technical opinions 

Option B : Conflict over schedule and cost 

Option C : Conflict over personnel resources 

Option D : Conflict over personality issues 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Conflict over personality issues 

Project Management Professional Question No 5

 According to John R. Adams Ph.D., there are five sources of power that people have: legitimate, coercive, reward, expert and referent. If the team knows that the project manager who is managing the project is reporting straight up to the President, what type of power is most prevalent? 

Option A : Legitimate 

Option B : Coercive 

Option C : Referent 

Option D : Reward

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Referent 

PMP Certification Prep Question No 6

 Two weeks ago the project manager was fired for not managing the project well. The project is behind schedule, over cost and the morale on the team is very low. The new project manager is having a team meeting. She starts out by telling the team about the last three projects she worked on, how they were similar to this one and how she brought them in ahead of schedule and on budget. What type of power is she establishing? 

Option A : Legitimate

Option B : Expert

Option C : Referent 

Option D : Reward

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Expert

PMP Exam Question No 7

The BCWP is 65%, the BCWS is 70%. The project manager wants to make up for the 5%. The project sponsor has set aside $5000 as a reserve to remedy this situation. Instead of using it to hire temporary labor, or pay overtime, the project manager is using it as an incentive for the team to catch up in 60 days. If they do, the money will be used to take the team members and their guests to Catalina for an all expenses paid weekend. What type of power is the project manager referencing?

Option A : Referent 

Option B : Coercive 

Option C : Reward 

Option D : Expert

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Reward 

PMP Exam Sample Question No 8

Project execution is very much an integrative process whereby all the work that was planned is actually accomplished. During this integrative process, what is the area that the project manager will spend the least amount of time on? 

Option A : Conflict resolution 

Option B : Documentation and planning

Option C : Prioritization and removal of road blocks 

Option D : Trade off among schedule, cost and scope

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Documentation and planning

PMP Exam Practice Question No 9

 The CFO wants to know how the project is going. You put together a presentation that shows the milestones, progress to date against schedule and budget, and projected progress in the next 30 days. What type of power does this demonstrate to senior management? 

Option A : Coercive 

Option B : Reward

Option C : Legitimate

Option D : Expert 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Expert 

PMP Certification Exam Question No 10

What two main knowledge areas are not listed in the execution process of the project, but rather a part of the controlling process? 

Option A : Schedule and cost 

Option B : Cost and communication 

Option C : Quality and risk 

Option D : Risk and procurement

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Schedule and cost

PMP Certification Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply