Hi PMP aspirants, welcome to AKVTutorials. Are you exploring PMP practice mock tests to sharpen your knowledge and boost your confidence? Navigate the path to PMP mastery with our Practice Questions—a game-changing resource for Project Management Professional hopefuls. In this article, you will get PMP Exam Prep Test 105 Questions Answers Explanations. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
Which of the following statement is true?
Option A : PERT does not show the critical path but CPM does.
Option B : Both PERT and CPM are duration estimates.
Option C : PERT allows for probabilistic sequencing that CPM can’t provide.
Option D : CPM provides more accurate duration estimate than PERT.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Both PERT and CPM are duration estimates.
PMP Exam Preparation Test Question No 2
Your manager gives you a scope of work and ask you to begin work immediately and provide her with a schedule. What should you do first?
Option A : Begin estimating the task necessary to complete the scope of work.
Option B : Identify the stake holders and make sure their requirements are included in the scope of work.
Option C : Create an activity list and then begin to assign the task to resources.
Option D : Identify a team and obtain approval for their participation from their functional managers.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Identify the stake holders and make sure their requirements are included in the scope of work.
PMP Exam Sample Exam Question No 3
Expert judgement will often be required to access the input of initiation , Such expertise may be provided by any group or individual with specialized knowledge or training and is available from many sources ,including the following.
Option A : other units within the organization ,consultant ,and internet.
Option B : industry group, stake holders , and lesion learned from previous objects.
Option C : Consultant, Stake holders and industry groups.
Option D : Other project managers and professionals.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Consultant, Stake holders and industry groups.
PMP Certification Exam Question No 4
Quality controls includes a number of activities and technique within a project that ensure that the organization quality’s objective are being met .Which of the following is not considered part of the quality control process.
Option A : quality audits.
Option B : continually monitoring process.
Option C : identifying and eliminating problem causes.
Option D : use of statistical process control to reduce process variability and increase efficiency.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
quality audits.
Free PMP Practice Exam Question No 5
The tools and technique in the contract admin process are :
Option A : contract change control system, performance reporting , and payment system.
Option B : contract change control system, contract negotiations, and payment system.
Option C : contract change control system, contract negotiations ,and contract changes.
Option D : contract change control system, payment system , and payment requests.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
contract change control system, performance reporting , and payment system.
Best PMP Exam Practice Question No 6
Risk monitoring and control involves all of the following task except:
Option A : identifying new risks.
Option B : ensuring the execution of risk plans.
Option C : evaluating and execution of risk plans.
Option D : Contingency planning
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Contingency planning
Free PMP Exam Prep Question No 7
Which earned value formula correctly illustrate the cost variance of a project incurrence?
Option A : BCWP-ACWP
Option B : BCWP/ACWP
Option C : ACWP-BCWP
Option D : BCWP/BCWS
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
BCWP-ACWP
Latest PMP Exam Question No 8
Due to bankruptcy reason ,your current vendor has been forced to withdraw from your project. your purchasing department has now informed you the new vendor has been selected, approved and the resources will be arriving on the site ,first thing next Monday. As the project manager what is the first thing you should do on Monday?
Option A : Have the core team on site so you can introduce the new vendor to the project team.
Option B : Establish yourself as the authority in charge.
Option C : Arrange for a tour of the site for the new vendor.
Option D : Review the contract details with the vendor to ensure common understanding.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Establish yourself as the authority in charge.
PMI PMP Exam Practice Question No 9
Formal acceptance by the client or sponsor of the project is prepared and distributed during the ____________ process
Option A : administrative closeout.
Option B : organizational planning.
Option C : performance reporting.
Option D : contract admin.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
administrative closeout.
PMP Certification Exam Agile Question No 10
Considerable time has been spent negotiating the contract between both the vendor and the purchaser over the last 7 months .Today is suppose to be the last meeting to finalize one outstanding issue. At this meeting emotions are now at an all time high, when out of the blue ,the vendor starts to pack her briefcase to leave. What type of negotiating strategy is the vendor using in this situation.
Option A : Missing man
Option B : Fair and reasonable.
Option C : Deadline.
Option D : Withdrawal
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Withdrawal