PMP Exam Sample Questions Online Test Paper 105

Hi PMP aspirants, welcome to AKVTutorials. Are you exploring PMP practice mock tests to sharpen your knowledge and boost your confidence? Navigate the path to PMP mastery with our Practice Questions—a game-changing resource for Project Management Professional hopefuls. In this article, you will get PMP Exam Prep Test 105 Questions Answers Explanations. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

Which of the following statement is true?

Option A : PERT does not show the critical path but CPM does.

Option B : Both PERT and CPM are duration estimates.

Option C : PERT allows for probabilistic sequencing that CPM can’t provide.

Option D : CPM provides more accurate duration estimate than PERT.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Both PERT and CPM are duration estimates.

PMP Exam Preparation Test Question No 2

Your manager gives you a scope of work and ask you to begin work immediately and provide her with a schedule. What should you do first?

Option A : Begin estimating the task necessary to complete the scope of work.

Option B : Identify the stake holders and make sure their requirements are included in the scope of work.

Option C : Create an activity list and then begin to assign the task to resources.

Option D : Identify a team and obtain approval for their participation from their functional managers.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Identify the stake holders and make sure their requirements are included in the scope of work.

PMP Exam Sample Exam Question No 3

Expert judgement will often be required to access the input of initiation , Such expertise may be provided by any group or individual with specialized knowledge or training and is available from many sources ,including the following.

Option A : other units within the organization ,consultant ,and internet.

Option B : industry group, stake holders , and lesion learned from previous objects.

Option C : Consultant, Stake holders and industry groups.

Option D : Other project managers and professionals.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Consultant, Stake holders and industry groups.

PMP Certification Exam Question No 4

Quality controls includes a number of activities and technique within a project that ensure that the organization quality’s objective are being met .Which of the following is not considered part of the quality control process.

Option A : quality audits.

Option B : continually monitoring process.

Option C : identifying and eliminating problem causes.

Option D : use of statistical process control to reduce process variability and increase efficiency.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

quality audits.

Free PMP Practice Exam Question No 5

The tools and technique in the contract admin process are :

Option A : contract change control system, performance reporting , and payment system.

Option B : contract change control system, contract negotiations, and payment system.

Option C : contract change control system, contract negotiations ,and contract changes.

Option D : contract change control system, payment system , and payment requests.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

contract change control system, performance reporting , and payment system.

Best PMP Exam Practice Question No 6

Risk monitoring and control involves all of the following task except:

Option A : identifying new risks.

Option B : ensuring the execution of risk plans.

Option C : evaluating and execution of risk plans.

Option D : Contingency planning

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Contingency planning 

Free PMP Exam Prep Question No 7

Which earned value formula correctly illustrate the cost variance of a project incurrence?

Option A : BCWP-ACWP

Option B : BCWP/ACWP

Option C : ACWP-BCWP

Option D : BCWP/BCWS

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

BCWP-ACWP

Latest PMP Exam Question No 8

Due to bankruptcy reason ,your current vendor has been forced to withdraw from your project. your purchasing department has now informed you the new vendor has been selected, approved and the resources will be arriving on the site ,first thing next Monday. As the project manager what is the first thing you should do on Monday?

Option A : Have the core team on site so you can introduce the new vendor to the project team.

Option B : Establish yourself as the authority in charge.

Option C : Arrange for a tour of the site for the new vendor.

Option D : Review the contract details with the vendor to ensure common understanding.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Establish yourself as the authority in charge.

PMI PMP Exam Practice Question No 9

Formal acceptance by the client or sponsor of the project is prepared and distributed during the ____________ process

Option A : administrative closeout.

Option B : organizational planning.

Option C : performance reporting.

Option D : contract admin.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

administrative closeout.

PMP Certification Exam Agile Question No 10

Considerable time has been spent negotiating the contract between both the vendor and the purchaser over the last 7 months .Today is suppose to be the last meeting to finalize one outstanding issue. At this meeting emotions are now at an all time high, when out of the blue ,the vendor starts to pack her briefcase to leave. What type of negotiating strategy is the vendor using in this situation.

Option A : Missing man

Option B : Fair and reasonable.

Option C : Deadline.

Option D : Withdrawal

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Withdrawal

PMP Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply