PMP Exam Questions With Explanations Free Test Paper 109 Download

Hi PMP aspirants, welcome to AKVTutorials. Are you on the lookout for PMP Project Management Professional practice questions to validate your understanding of key concepts? Fuel your PMP ambitions with our Practice Questions—an invaluable resource for navigating the Project Management Professional certification landscape. In this article, you will get PMP Exam Questions With Explanations Free Test Paper 109 Download. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

Which of the 7 main statistical processing charts determines possible cause of potential problems and actual problems?

Option A : flow charts.

Option B : a fishbone diagram.

Option C : a control chart.

Option D : Scatter diagrams.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

a fishbone diagram.

PMP Exam Preparation Test Question No 2

All of the following are cost estimating tools except:

Option A : alternative identification.

Option B : analogous

Option C : bottom-up.

Option D : parametric.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

alternative identification.

PMP Exam Sample Exam Question No 3

The project is formally initiated or authorized to continue when:

Option A : the budget is assigned.

Option B : the project manager is appointed.

Option C : the charter is completed.

Option D : B and C.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

B and C.

PMP Certification Exam Question No 4

Which is not used as a tool and technique for information gathering during the risk identification process?

Option A : SWOT.

Option B : Delphi.

Option C : Interviewing.

Option D : Simulation.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Simulation.

Free PMP Practice Exam Question No 5

General management encompasses:

Option A : Planning, organizing, Stuffing, executing and controlling the operation of an ongoing enterprise.

Option B : Business policy ,financial management, business economics, contract administration , and legal services necessary for operating an enterprise.

Option C : Business strategy ,planning and controlling, organizational behavior , procurement and personal administration required for managing the ongoing aspect of a

Option D : Organizational development, staffing, marketing and sales ,procurement, and contract administration as part of an ongoing organization.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Planning, organizing, Stuffing, executing and controlling the operation of an ongoing enterprise.

Best PMP Exam Practice Question No 6

Project Management is the art and science of converting abstract into concrete or vision in reality. The realization can be most effective through formula understanding of project management process. What are the 5 management process?

Option A : Conceptualize plan, execute, control, and close-out.

Option B : Initiate ,plan, execute, control, and finish.

Option C : Initiate, plan, execute, control, and close-out.

Option D : Initiate, plan , implementation, control, and close-out.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Initiate, plan, execute, control, and close-out. 

Free PMP Exam Prep Question No 7

All of the following statements concerning project stakeholders are true except?

Option A : Difference should be resolved in favor of the customer whenever possible.

Option B : Managing stakeholder expectation may be difficult because stakeholders do not have very different stage objectives that may come into conflict.

Option C : Project stakeholder may influence the course of the project and its result .

Option D : Key stakeholders are senior management.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Key stakeholders are senior management.

Latest PMP Exam Question No 8

The difference between an activity’s schedule completion and actual completion is called:

Option A : earned value.

Option B : schedule variance.

Option C : schedule performance index.

Option D : Budget variance.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

schedule variance.

PMI PMP Exam Practice Question No 9

From the “view exhibit “ button how many days of float does activity G have?

Option A : 0

Option B : 2

Option C : 10

Option D : 7

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

7

PMP Certification Exam Agile Question No 10

Project performance is impacted by 4 basic cultures. Which of the following is not one of the 4 basic culture?

Option A : leadership.

Option B : world.

Option C : business.

Option D : international

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

international

Free PMP Exam Practice Test Questions And Solutions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply