Hi PMP aspirants, welcome to AKVTutorials. Ready to test your knowledge of project management information systems with PMP practice questions designed to assess your proficiency? Master project management information systems with our PMP Project Management Professional practice questions, a key component of successful project execution. In this article, you will get PMP Exam Questions Test 46 with Answers Keys PDF. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

At this point on your project, you are in the process of controlling costs. You want to determine if you are staying within your budget. Which of the following are outputs of that process?

Option A : Work Performance Information and Cost Forecasts 

Option B : Cost Baseline and Project Funding Requirements 

Option C : Change Requests and Work Performance Data 

Option D : Cost Forecasts and Verified Deliverables

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Work Performance Information and Cost Forecasts 

PMP Mock Test Question No 2

A global technology company has several projects that involve large, enterprise-wide system deployments. In other words, they impact several departments across the organization. In these types of scenarios, which of the following project lifecycles are commonly used?

Option A : Agile 

Option B : Predictive

Option C : Adaptive 

Option D : Iterative

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Predictive

PMP Practice Exam Question No 3

You work at an aerospace company and are leading a project to launch a satellite, which will be used for academic research. Currently, the team is performing the manage communications process. In doing so, which of the following activities might they complete?

Option A : Conducting surveys of stakeholders to see if communication needs have been met. 

Option B : Creating an ad-hoc report for a key project stakeholder. 

Option C : Evaluating whether or not communication on the project has been effective. 

Option D : Determining how information on the project will be distributed and stored.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Creating an ad-hoc report for a key project stakeholder. 

PMP Mock Exam Question No 4

All of the following are true about firm fixed price (FFP) contracts except:

Option A : The price is set at the start of the contract. 

Option B : The price is not subject to change. 

Option C : If a change to scope is needed, the buyer will likely need to pay more. 

Option D : They are useful for staff augmentation.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

They are useful for staff augmentation.

Project Management Professional Question No 5

A project manager is working with a team to design a new printer that addresses several flaws in previous models. At this point, she needs to understand what funds will be needed to appropriately respond to risks on the project. Which document should be reviewed to find this information?

Option A : Risk Management Plan 

Option B : Cost Management Plan 

Option C : Risk Register 

Option D : Cost Aggregation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Risk Management Plan 

PMP Certification Prep Question No 6

As a team, you have already verified the quality of several project deliverables. Your next step is to get formal acceptance of those deliverables from your customers. This process is referred to as validating the scope. Which of the following are outputs of that process?

Option A : Work Performance Information, Scope Baseline, Scope Management Plan 

Option B : Accepted Deliverables, Work Performance Information, Change Requests 

Option C : Change Requests, Scope Baseline, Project Scope Statement 

Option D : Scope Baseline, Project Scope Statement, Verified Deliverables

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Accepted Deliverables, Work Performance Information, Change Requests 

PMP Exam Question No 7

During a project to migrate user data between database technologies, the project manager spends time tracking team member performance, providing feedback, and resolving issues. What is an output from that process?

Option A : Project Team Assignments 

Option B : Team Charter 

Option C : Change Requests 

Option D : Enterprise Environmental Factors

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Change Requests 

PMP Exam Sample Question No 8

A project manager is working with a team to create and test a new flavor of a popular soft drink. Early in the project, she would like to see a high-level summary of project milestones. Which document should be reviewed to find this information?

Option A : Organizational Process Assets 

Option B : Schedule Data 

Option C : Schedule Management Plan

Option D : Project Charter

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project Charter

PMP Exam Practice Question No 9

A project manager is creating a risk management plan for a project that involves relocating office workers at a technology company to a new building. Which of the following would not be included in that document?

Option A : The funds that will be needed to respond to risks on the project 

Option B : The distribution of identified risks across various risk categories 

Option C : The procedures for how management and contingency reserves will be used 

Option D : A description of the format that will be used to report threat and opportunities on the project

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

The distribution of identified risks across various risk categories 

PMP Certification Exam Question No 10

You are managing an effort to remodel three local restaurants. At this point on your project, you are in the process of defining the activities. Which of the following are tools or techniques of that process?

Option A : Rolling Wave Planning, Meetings, Leads & Lags 

Option B : Expert Judgment, Decomposition, Rolling Wave Planning 

Option C : Resource Optimization, Data Analysis, Decision Making 

Option D : Decomposition, Precedence Diagramming Method, Meetings

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Expert Judgment, Decomposition, Rolling Wave Planning 

Practice Test PMP Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply