Hi PMP aspirants, welcome to AKVTutorials. Ready to test your knowledge of project management information systems with PMP practice questions designed to assess your proficiency? Master project management information systems with our PMP Project Management Professional practice questions, a key component of successful project execution. In this article, you will get PMP Exam Questions Test 46 with Answers Keys PDF. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
At this point on your project, you are in the process of controlling costs. You want to determine if you are staying within your budget. Which of the following are outputs of that process?
Option A : Work Performance Information and Cost Forecasts
Option B : Cost Baseline and Project Funding Requirements
Option C : Change Requests and Work Performance Data
Option D : Cost Forecasts and Verified Deliverables
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Work Performance Information and Cost Forecasts
PMP Mock Test Question No 2
A global technology company has several projects that involve large, enterprise-wide system deployments. In other words, they impact several departments across the organization. In these types of scenarios, which of the following project lifecycles are commonly used?
Option A : Agile
Option B : Predictive
Option C : Adaptive
Option D : Iterative
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Predictive
PMP Practice Exam Question No 3
You work at an aerospace company and are leading a project to launch a satellite, which will be used for academic research. Currently, the team is performing the manage communications process. In doing so, which of the following activities might they complete?
Option A : Conducting surveys of stakeholders to see if communication needs have been met.
Option B : Creating an ad-hoc report for a key project stakeholder.
Option C : Evaluating whether or not communication on the project has been effective.
Option D : Determining how information on the project will be distributed and stored.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Creating an ad-hoc report for a key project stakeholder.
PMP Mock Exam Question No 4
All of the following are true about firm fixed price (FFP) contracts except:
Option A : The price is set at the start of the contract.
Option B : The price is not subject to change.
Option C : If a change to scope is needed, the buyer will likely need to pay more.
Option D : They are useful for staff augmentation.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
They are useful for staff augmentation.
Project Management Professional Question No 5
A project manager is working with a team to design a new printer that addresses several flaws in previous models. At this point, she needs to understand what funds will be needed to appropriately respond to risks on the project. Which document should be reviewed to find this information?
Option A : Risk Management Plan
Option B : Cost Management Plan
Option C : Risk Register
Option D : Cost Aggregation
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Risk Management Plan
PMP Certification Prep Question No 6
As a team, you have already verified the quality of several project deliverables. Your next step is to get formal acceptance of those deliverables from your customers. This process is referred to as validating the scope. Which of the following are outputs of that process?
Option A : Work Performance Information, Scope Baseline, Scope Management Plan
Option B : Accepted Deliverables, Work Performance Information, Change Requests
Option C : Change Requests, Scope Baseline, Project Scope Statement
Option D : Scope Baseline, Project Scope Statement, Verified Deliverables
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Accepted Deliverables, Work Performance Information, Change Requests
PMP Exam Question No 7
During a project to migrate user data between database technologies, the project manager spends time tracking team member performance, providing feedback, and resolving issues. What is an output from that process?
Option A : Project Team Assignments
Option B : Team Charter
Option C : Change Requests
Option D : Enterprise Environmental Factors
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Change Requests
PMP Exam Sample Question No 8
A project manager is working with a team to create and test a new flavor of a popular soft drink. Early in the project, she would like to see a high-level summary of project milestones. Which document should be reviewed to find this information?
Option A : Organizational Process Assets
Option B : Schedule Data
Option C : Schedule Management Plan
Option D : Project Charter
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project Charter
PMP Exam Practice Question No 9
A project manager is creating a risk management plan for a project that involves relocating office workers at a technology company to a new building. Which of the following would not be included in that document?
Option A : The funds that will be needed to respond to risks on the project
Option B : The distribution of identified risks across various risk categories
Option C : The procedures for how management and contingency reserves will be used
Option D : A description of the format that will be used to report threat and opportunities on the project
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
The distribution of identified risks across various risk categories
PMP Certification Exam Question No 10
You are managing an effort to remodel three local restaurants. At this point on your project, you are in the process of defining the activities. Which of the following are tools or techniques of that process?
Option A : Rolling Wave Planning, Meetings, Leads & Lags
Option B : Expert Judgment, Decomposition, Rolling Wave Planning
Option C : Resource Optimization, Data Analysis, Decision Making
Option D : Decomposition, Precedence Diagramming Method, Meetings
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Expert Judgment, Decomposition, Rolling Wave Planning