Hi PMP aspirants, welcome to AKVTutorials. Ready to test your understanding of PMP concepts with practice questions that challenge your knowledge of scope management? Immerse yourself in PMP excellence with our practice questions, covering both predictive and agile methodologies to fortify your Project Management Professional preparation. In this article, you will get PMP Exam Questions Paper 81 Examples Answer. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Which of the following is not an output of scope change control?
Option A : Scope changes
Option B : Work arounds
Option C : Corrective action
Option D : Lessons learned
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Work arounds
PMP Mock Test Question No 2
Which of the following is an input of scope change control?
Option A : Performance reports
Option B : Corrective actions
Option C : Work arounds
Option D : Performance measurements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Performance reports
PMP Practice Exam Question No 3
The marketing department has just discovered that most buyers are not willing to pay the extra cost of one of the features planned in your current project. They submit a change request that is a result of:
Option A : An external event
Option B : An error or omission in defining the scope of the product
Option C : An error or omission in defining the scope of the project
Option D : A value-adding change
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
An error or omission in defining the scope of the product
PMP Mock Exam Question No 4
The marketing department has just discovered that a competitor is offering a new feature, using a new technology, on a product similar to the one being created by your project. They submit a change request that is the result of:
Option A : An external event
Option B : An error or omission in defining the scope of the product
Option C : An error or omission in defining the scope of the project
Option D : A value-adding change
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
An external event
Project Management Professional Question No 5
The engineering department has just reported that a small plastic insert can be used as an acceptable substitute for an expensive molybdenum bearing in the warp drive you are creating. They submit a change request that is the result of:
Option A : An external event
Option B : An error or omission in defining the scope of the product
Option C : An error or omission in defining the scope of the project
Option D : A value-adding change
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
A value-adding change
PMP Certification Prep Question No 6
The engineering department has raised a question about the expensive molybdenum bearing you plan to use in your warp drive project. They believe they can find an acceptable but cheaper substitute and submit a change request to do the necessary research. Their request is the result of:
Option A : An external event
Option B : An error or omission in defining the scope of the product
Option C : An error or omission in defining the scope of the project
Option D : A value-adding change
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
A value-adding change
PMP Exam Question No 7
Who originates the Project Charter?
Option A : The Project Manager
Option B : The Project Sponsor
Option C : The client
Option D : A manager external to the project
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
A manager external to the project
PMP Exam Sample Question No 8
What is the document that gives the PM the authority to apply organizational resources?
Option A : The Scope Paper
Option B : The Project Definition Document
Option C : The Project Charter
Option D : The Statement of Work
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The Project Charter
PMP Exam Practice Question No 9
Which is true about a work breakdown structure?
Option A : It is a deliverable oriented grouping of project elements
Option B : It shows work elements that have been assigned to various organizational units
Option C : It is the same as a code of accounts
Option D : It is developed after the baseline schedules and budgets have been developed
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
It is a deliverable oriented grouping of project elements
PMP Certification Exam Question No 10
Scope verification is concerned with:
Option A : Ensuring that all the elements necessary are included in the WBS
Option B : Receiving buy-in from team members
Option C : The acceptance of the work results
Option D : Developing a project base line
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The acceptance of the work results