Hi PMP aspirants, welcome to AKVTutorials. In need of PMP Project Management Professional practice questions that focus on procurement management and contract types? Explore the depths of PMP knowledge using our comprehensive set of Project Management Professional practice questions that reinforce your grasp of the PMBOK Guide. In this article, you will get PMP Exam Questions Online Test Paper 82 Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
The document that describes the project’s scope baseline is:
Option A : The master schedule
Option B : The Project Definition document
Option C : The Scope Paper
Option D : The Work Breakdown Structure
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The Work Breakdown Structure
PMP Mock Test Question No 2
The two closing procedures are called:
Option A : Contract close out and scope verification
Option B : Contract close out and administrative closure
Option C : Project closure and product verification
Option D : Project closure and lessons learned
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Contract close out and administrative closure
PMP Practice Exam Question No 3
A work package is:
Option A : A task on the Work Breakdown Structure
Option B : A level 1 activity on the Work Breakdown Structure
Option C : A deliverable at the lowest level of the Work Breakdown Structure
Option D : An activity on the Project Schedule
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
A deliverable at the lowest level of the Work Breakdown Structure
PMP Mock Exam Question No 4
A scope change is:
Option A : Any change to the agreed upon project scope as defined by the approved WBS
Option B : Market research
Option C : A result of poor planning
Option D : An output of corrective action
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Any change to the agreed upon project scope as defined by the approved WBS
Project Management Professional Question No 5
Overall change control requires all of the following except:
Option A : Maintaining the integrity of the baseline
Option B : Ensuring that changes to the product scope are reflected in the project scope
Option C : Coordinating changes across knowledge areas
Option D : Making process adjustments as a result of deficiencies
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Making process adjustments as a result of deficiencies
PMP Certification Prep Question No 6
Overall change control is concerned with all of the following except:
Option A : Determining that a change has occurred
Option B : Managing changes as they occur
Option C : Creating change requests
Option D : Influencing factors that create change to ensure that changes are beneficial
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Influencing factors that create change to ensure that changes are beneficial
PMP Exam Question No 7
Which of the following is not an input to overall change control?
Option A : Configuration management system
Option B : Performance reports
Option C : Change requests
Option D : Project plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Configuration management system
PMP Exam Sample Question No 8
Your current project has over 200 specs, 350 engineering drawings and 5500 parts. What tool do you use to apply technical and administrative direction to identify the functional and physical characteristics of items, and control changes to those characteristics?
Option A : Change control system
Option B : Configuration management
Option C : Inventory control
Option D : Operational definitions
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Configuration management
PMP Exam Practice Question No 9
Configuration management does all of the following except:
Option A : Control changes to functional and physical characteristics of an item or a system
Option B : Record and report changes to any functional and physical characteristics of an item or a system
Option C : Defines the steps by which official project documents may be changed
Option D : Audits items and systems to ensure conformance to requirements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Defines the steps by which official project documents may be changed
PMP Certification Exam Question No 10
At the outset of a project you should define the processes necessary to account for change. Which of the following is not a standard inclusion in a change control system?
Option A : Performance reports
Option B : Procedures to handle changes that may be approved without prior review
Option C : How to handle changes in emergencies
Option D : The responsibilities of the change control board
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Performance reports