PMP Exam Questions Free Test 8 Download

Hi PMP aspirants, welcome to AKVTutorials. Ready to challenge yourself with PMP practice questions designed to mirror the actual Project Management Professional exam? Transform your PMP ambitions into reality using our Practice Questions—a catalyst for mastering Project Management Professional concepts. In this article, you will get PMP Project Management Professional Certification Exam Test 8 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A competitor launches a new product that may make the product that company X is developing obsolete. To remain competitive, company X considers a scope change. What should a project manager do before executing a scope change?

Option A : Ask experts for their input.

Option B : Issue a change request.

Option C : Use rolling wave planning.

Option D : Reschedule the project using the critical path method (CPM)

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Issue a change request.

PMP Mock Test Question No 2

A project has been long and difficult. The team is relieved that the project is ending soon, and they begin to submit final reports before an approved one-week break. Overall, the project was successful. However, the project manager realizes that lessons learned were not recorded throughout the project. Who should the project manager consult during the project to obtain lessons learned?

Option A : Project specialist

Option B : Quality assurance team

Option C : Junior project manager

Option D : Project team

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project team

PMP Practice Exam Question No 3

A project manager meets with the managers of project resources and the directors of areas that the project will benefit. During the meeting, the project manager explains the project objectives and the activities needed to complete the project. What project activity is the project manager accomplishing with this meeting?

Option A : Project kick-off

Option B : Stakeholder engagement

Option C : Team formation

Option D : Risk mitigation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Project kick-off

PMP Mock Exam Question No 4

Six weeks after the addition of new project resources, the project team completes the work. However, the project sponsor refuses to pay for the additional resources. What should the project manager have done before adding resources?

Option A : Reviewed the contract requirements

Option B : Reviewed the communications management plan

Option C : Processed a change request

Option D : Updated the contingency reserve

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Processed a change request

Project Management Professional Question No 5

In a control chart, three measurement points in a process are below the mean and within control limits. Four measurement points are above the mean and outside the control limits. How is this process performing?

Option A : The process is under control.

Option B : The process is out of control.

Option C : The process is within specification limits.

Option D : The process is under the seven-point rule

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

The process is out of control.

PMP Certification Prep Question No 6

A project manager is unable to explain why several Scrum team members have been unhappy with the team’s performance for the past year. What would have assisted in identifying these issues?

Option A : Having more team-building exercises to form better personal relationships

Option B : Having retrospectives at the end of every iteration so that processes were changed immediately

Option C : Asking team members individually which resources were not performing as expected

Option D : Removing team members with the lowest number of completed story points

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Having retrospectives at the end of every iteration so that processes were changed immediately

PMP Exam Question No 7

A low probability/high impact technical risk occurs. What should the project manager do?

Option A : Submit a change request to adjust the cost and schedule baselines.

Option B : Conduct a risk review to evaluate its impact on project deliverables.

Option C : Implement the mitigation plan outlined in the risk register.

Option D : Consult the lessons learned repository for possible risk mitigation options

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Conduct a risk review to evaluate its impact on project deliverables.

PMP Exam Sample Question No 8

A project manager arranges quality management training for the entire project team. The training will relate to the project’s final product deliverable. In what cost of quality (COQ) category should the project manager classify this training?

Option A : Prevention

Option B : Internal failure

Option C : Appraisal

Option D : External failure

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Prevention

PMP Exam Practice Question No 9

A project manager working with a risk-averse financial firm has just started a new project. The project sponsor is extremely concerned that the project may run over budget and is looking to the project manager for confirmation that this won’t happen. In order to alleviate the sponsor’s concern, what should the project manager do?

Option A : Create the probability and impact matrix.

Option B : Use historical data analysis.

Option C : Run a monte carlo simulation.

Option D : Perform a strengths, weaknesses, opportunities, and threats (SWOT) analysis

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Run a monte carlo simulation.

PMP Certification Exam Question No 10

The sponsor of a project requests to see a prototype for a project deliverable. Three options are provided, and the sponsor accepts one of these options. While implementing the deliverable, a team member informs the project manager that the approved sample does not meet a particular government standard, and will not be suitable for use. What should the project manager have done to avoid this mistake?

Option A : Request that the sponsor check the quality reports before making a decision.

Option B : Consult the lessons learned archive for sample acceptance.

Option C : Conduct quality assurance during the project.

Option D : Verify that the samples provided conform with quality standards.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Verify that the samples provided conform with quality standards.

PMP Practice Exam Question Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply