Hi PMP aspirants, welcome to AKVTutorials. Ready to take your PMP exam preparation to the next level with a comprehensive set of practice questions? Propel your PMP success story forward with our Practice Questions—a roadmap to conquering the Project Management Professional exam. In this article, you will get PMP Exam Prep Test 103 Questions Answers Explanations. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
A contingency plan___________.
Option A : identifies alternative strategies to be used to ensure project success if a specified risk event occurs.
Option B : is a work around.
Option C : is part of the management reserve
Option D : is the same as a fallback plan.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
identifies alternative strategies to be used to ensure project success if a specified risk event occurs.
PMP Exam Preparation Test Question No 2
All of the following are examples of theory X assumptions with the exception of:
Option A : employees avoid work.
Option B : employees need constant direction.
Option C : employees are self-directed.
Option D : employees are self-centered.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
employees are self-directed.
PMP Exam Sample Exam Question No 3
You have determined the duration for your project is 18.5 months with a standard deviation of 1.2 months. What technique will u use to determine the confidence level and the probability of completing the project on a specific day ?
Option A : PERT formula.
Option B : Monte carlo simulation.
Option C : Probability analysis.
Option D : Variance analysis.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Monte carlo simulation.
PMP Certification Exam Question No 4
Caltural noise in the communication channel can be caused by all of the following except?
Option A : Ethnocentric
Option B : Stereotyping.
Option C : Decorum.
Option D : Proximity distance between people
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Proximity distance between people
Free PMP Practice Exam Question No 5
If PV $ 24000 and AC is $27000 and EV is 25000 we can report the project as follow:
Option A : Ahead of schedule and over budget .
Option B : Ahead of schedule and behind budget.
Option C : Behind schedule and over budget.
Option D : Behind schedule and under budget.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Ahead of schedule and over budget .
Best PMP Exam Practice Question No 6
“For Consideration” in contract management means:
Option A : money must be paid from one party to another.
Option B : the contract must be signed.
Option C : the contract must be agreed to buy both parties.
Option D : there must be an exchange of things.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
there must be an exchange of things.
Free PMP Exam Prep Question No 7
The contemporary view of conflict is that :
Option A : conflict is bad.
Option B : conflict is caused by trouble maker.
Option C : conflict should be avoided.
Option D : conflict is often beneficial.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
conflict is often beneficial.
Latest PMP Exam Question No 8
A cost base line is an output of the _____________ management process.
Option A : Resource planning
Option B : Cost estimating
Option C : Cost budgeting
Option D : Cost control
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Cost budgeting
PMI PMP Exam Practice Question No 9
There are a variety of methods to select a projects. Which of the following is not a project selection criteria method.
Option A : Benefit measurement.
Option B : NPVA
Option C : The number of resources required to complete the project.
Option D : Value analysis.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Value analysis.
PMP Certification Exam Agile Question No 10
Who originates the project charter ?
Option A : The project manager.
Option B : The project spencer
Option C : The client
Option D : A manager external to the project.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
A manager external to the project.