Hi PMP aspirants, welcome to AKVTutorials. Are you exploring PMP practice questions that emphasize integration management, a key knowledge area in Project Management Professional certification? Navigate change management principles confidently with our practice questions, a key focus area for effective Project Management Professional practice. In this article, you will get PMP Exam Preparation Test 78 Questions Answers Explanations. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
In taking over a failing project you hold a status meeting and find that the IS department and the business operations representatives are avoiding each other. You realize that before moving on you need to do some team building. The type of behavior that the IS and operations people are demonstrating is:
Option A : Problem solving
Option B : Withdrawal
Option C : Forcing
Option D : Smoothing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Withdrawal
PMP Mock Test Question No 2
In taking over a failing project you hold a status meeting where the marketing person and the finance person get into a heated discussion, each trying to push their viewpoint on the other without listening. You realize that before moving on you need to do some conflict resolution. The type of behavior that the marketing and finance people are demonstrating is:
Option A : Problem solving
Option B : Withdrawal
Option C : Forcing
Option D : Smoothing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Forcing
PMP Practice Exam Question No 3
Which of the following models of conflict resolution allows a cooling off period, but seldom resolves the issue in the long term?
Option A : Problem solving
Option B : Withdrawal
Option C : Forcing
Option D : Smoothing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Withdrawal
PMP Mock Exam Question No 4
Which method of conflict resolution tends to increase conflict rather than resolve it?
Option A : Problem solving
Option B : Compromising
Option C : Smoothing
Option D : Forcing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Forcing
Project Management Professional Question No 5
Which method of conflict resolution tends to be the most effective in resolving conflicts?
Option A : Confrontation
Option B : Withdrawal
Option C : Forcing
Option D : Organizational development
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Confrontation
PMP Certification Prep Question No 6
Which conflict resolution style emphasizes agreement rather than focusing on areas of disagreement?
Option A : Problem solving
Option B : Withdrawal
Option C : Forcing
Option D : Smoothing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Smoothing
PMP Exam Question No 7
All of the following are common uses for a “War Room” except:
Option A : A repository for project artifacts
Option B : A place where project team members can discuss their common problems
Option C : A location where the up-to-the-minute wall charts of technical performance are housed
Option D : The project wrap up party
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The project wrap up party
PMP Exam Sample Question No 8
Stock options, assigned parking spaces and a company car are all examples of what?
Option A : Perks associated with functional management
Option B : Non-monetary rewards
Option C : Leverage to encourage better performance
Option D : Ways to justify paying a lower salary
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Non-monetary rewards
PMP Exam Practice Question No 9
Project Procurement Management has the following processes:
Option A : Solicitation planning, source selection, contract close-out
Option B : Procurement planning, solicitation planning, contract award
Option C : Contract solicitation, contract award, contract administration
Option D : Contract award, contract administration, contract close-out
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Solicitation planning, source selection, contract close-out
PMP Certification Exam Question No 10
A complex project will fit best in what type of organization?
Option A : Functional Product scope description
Option B : Cross-functional
Option C : Matrix
Option D : Balanced
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Matrix