PMP Exam Prep Test Questions Paper 50

Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and need practice questions that cover the latest trends and emerging practices in project management? Stay abreast of the latest trends and emerging practices in project management with our PMP Project Management Professional practice questions, ensuring your preparation is comprehensive and up-to-date. In this article, you will get PMP Exam Prep Test Questions Paper 50. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

At a recent meeting on a project to transition a company’s headquarters from California to Texas, you discuss progress being made on monitoring stakeholder engagement. What is an activity that could be performed during that process?

Option A : Conducting surveys of stakeholders to see if communication needs have been met. 

Option B : Creating an ad-hoc report for a key project stakeholder. 

Option C : Determining how to modify the plan for engaging stakeholders to ensure their ongoing commitment. 

Option D : Classifying stakeholders based on their level of authority.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Determining how to modify the plan for engaging stakeholders to ensure their ongoing commitment. 

PMP Mock Test Question No 2

A project manager is working with a team to design new cases for the next version of a popular smartphone. At this point, she needs to understand what financial incentives may be offered to project team members upon successful completion of the project. Which document should be reviewed to find this information?

Option A : Benefits Management Plan 

Option B : Cost Baseline 

Option C : Cost Management Plan 

Option D : Resource Management Plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Resource Management Plan

PMP Practice Exam Question No 3

You are soliciting advice from several experts, who have worked on similar projects, as you prepare the work breakdown structure (WBS). Which of the following is not a purpose of this document?

Option A : Articulate the components of work that will satisfy project objectives. 

Option B : Subdivide the project work into more manageable components. 

Option C : Diligence

Option D : Provide a hierarchical structure for assigning costs to work packages.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Outline the duration required to complete project activities. 

PMP Mock Exam Question No 4

As you collect requirements for a new laptop, you choose to share a model of the final product with your stakeholders. You believe that you will receive much better feedback through this method than if you simply attempted to explain the product. In this case, which of the following tools and technique should be used?

Option A : Prototypes 

Option B : Observations 

Option C : Benchmarking

Option D : Focus Groups

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Prototypes 

Project Management Professional Question No 5

A project manager is leading an effort to launch a small satellite into low-earth orbit. During the project, she uses earned value analysis and determines that the CPI is 0.90 and the SPI is 0.85. What does this indicate?

Option A : The project is under budget and ahead of schedule.

Option B : The project is over budget and behind schedule. 

Option C : The project is under budget and behind schedule. 

Option D : The project is over budget and ahead of schedule

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

The project is over budget and behind schedule.

PMP Certification Prep Question No 6

A project is underway to evaluate the impact of rising sea levels on oceanfront homes in Hawaii. During the project, the team spends time creating and distributing project information. What is an input to that particular process?

Option A : Project Communications

Option B : Project Reporting 

Option C : Communication Technology

Option D : Stakeholder Engagement Plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Stakeholder Engagement Plan

PMP Exam Question No 7

A project to construct a new high school to alleviate overcrowding at three other local schools is underway. Currently, the team is performing the manage quality process. In doing so, which of the following activities might they complete?

Option A : Using the six sigma methodology to identify process improvement opportunities. 

Option B : Determining if the deliverables are complete, correct, and compliant with appropriate standards. 

Option C : Testing project deliverables to identify errors or defects. 

Option D : Using a SIPOC diagram to understand a process and predict where quality defects may occur.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Using the six sigma methodology to identify process improvement opportunities. 

PMP Exam Sample Question No 8

On your project, 15 stakeholders have been identified. Based on this information, how many possible communication channels exist?

Option A : 210

Option B : 105

Option C : 113

Option D : 29

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

105

PMP Exam Practice Question No 9

On a project to identify a solution to address a major software vulnerability, the team spends time obtaining the manpower, materials, and equipment needed to complete the project. In this scenario, what process is being performed?

Option A : Estimate Activity Resources

Option B : Acquire Resources

Option C : Control Resources

Option D : Plan Resource Management 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Acquire Resources 

PMP Certification Exam Question No 10

You have just been assigned to lead a project that is already underway. The objective is to migrate several production databases to cloud servers. At this point, the team is acquiring resources. In doing so, which of the following activities might they perform?

Option A : Arranging for key project team members to be at the same site near critical milestones 

Option B : Consulting with experts in talent management and training. 

Option C : Evaluating alternative resource options, such as renting or buying the needed equipment. 

Option D : Working with functional managers to assign the appropriate resources to project work.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Working with functional managers to assign the appropriate resources to project work.

PMI PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122