Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and need practice questions that cover the latest trends and emerging practices in project management? Stay abreast of the latest trends and emerging practices in project management with our PMP Project Management Professional practice questions, ensuring your preparation is comprehensive and up-to-date. In this article, you will get PMP Exam Prep Test Questions Paper 50. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
At a recent meeting on a project to transition a company’s headquarters from California to Texas, you discuss progress being made on monitoring stakeholder engagement. What is an activity that could be performed during that process?
Option A : Conducting surveys of stakeholders to see if communication needs have been met.
Option B : Creating an ad-hoc report for a key project stakeholder.
Option C : Determining how to modify the plan for engaging stakeholders to ensure their ongoing commitment.
Option D : Classifying stakeholders based on their level of authority.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Determining how to modify the plan for engaging stakeholders to ensure their ongoing commitment.
PMP Mock Test Question No 2
A project manager is working with a team to design new cases for the next version of a popular smartphone. At this point, she needs to understand what financial incentives may be offered to project team members upon successful completion of the project. Which document should be reviewed to find this information?
Option A : Benefits Management Plan
Option B : Cost Baseline
Option C : Cost Management Plan
Option D : Resource Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Resource Management Plan
PMP Practice Exam Question No 3
You are soliciting advice from several experts, who have worked on similar projects, as you prepare the work breakdown structure (WBS). Which of the following is not a purpose of this document?
Option A : Articulate the components of work that will satisfy project objectives.
Option B : Subdivide the project work into more manageable components.
Option C : Diligence
Option D : Provide a hierarchical structure for assigning costs to work packages.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Outline the duration required to complete project activities.
PMP Mock Exam Question No 4
As you collect requirements for a new laptop, you choose to share a model of the final product with your stakeholders. You believe that you will receive much better feedback through this method than if you simply attempted to explain the product. In this case, which of the following tools and technique should be used?
Option A : Prototypes
Option B : Observations
Option C : Benchmarking
Option D : Focus Groups
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Prototypes
Project Management Professional Question No 5
A project manager is leading an effort to launch a small satellite into low-earth orbit. During the project, she uses earned value analysis and determines that the CPI is 0.90 and the SPI is 0.85. What does this indicate?
Option A : The project is under budget and ahead of schedule.
Option B : The project is over budget and behind schedule.
Option C : The project is under budget and behind schedule.
Option D : The project is over budget and ahead of schedule
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
The project is over budget and behind schedule.
PMP Certification Prep Question No 6
A project is underway to evaluate the impact of rising sea levels on oceanfront homes in Hawaii. During the project, the team spends time creating and distributing project information. What is an input to that particular process?
Option A : Project Communications
Option B : Project Reporting
Option C : Communication Technology
Option D : Stakeholder Engagement Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Stakeholder Engagement Plan
PMP Exam Question No 7
A project to construct a new high school to alleviate overcrowding at three other local schools is underway. Currently, the team is performing the manage quality process. In doing so, which of the following activities might they complete?
Option A : Using the six sigma methodology to identify process improvement opportunities.
Option B : Determining if the deliverables are complete, correct, and compliant with appropriate standards.
Option C : Testing project deliverables to identify errors or defects.
Option D : Using a SIPOC diagram to understand a process and predict where quality defects may occur.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Using the six sigma methodology to identify process improvement opportunities.
PMP Exam Sample Question No 8
On your project, 15 stakeholders have been identified. Based on this information, how many possible communication channels exist?
Option A : 210
Option B : 105
Option C : 113
Option D : 29
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
105
PMP Exam Practice Question No 9
On a project to identify a solution to address a major software vulnerability, the team spends time obtaining the manpower, materials, and equipment needed to complete the project. In this scenario, what process is being performed?
Option A : Estimate Activity Resources
Option B : Acquire Resources
Option C : Control Resources
Option D : Plan Resource Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Acquire Resources
PMP Certification Exam Question No 10
You have just been assigned to lead a project that is already underway. The objective is to migrate several production databases to cloud servers. At this point, the team is acquiring resources. In doing so, which of the following activities might they perform?
Option A : Arranging for key project team members to be at the same site near critical milestones
Option B : Consulting with experts in talent management and training.
Option C : Evaluating alternative resource options, such as renting or buying the needed equipment.
Option D : Working with functional managers to assign the appropriate resources to project work.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Working with functional managers to assign the appropriate resources to project work.