Hi PMP aspirants, welcome to AKVTutorials. Are you in search of high-quality PMP Project Management Professional practice questions to elevate your exam preparation? Embark on a journey to PMP excellence with our meticulously crafted Practice Questions—a vital asset for success. In this article, you will get PMP Exam Prep Test 101 Questions Answers Explanations. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
Product documentation is a input to what process?
Option A : Scope verification.
Option B : Performance rating.
Option C : Risks Analysis.
Option D : Scope planning.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Scope verification.
PMP Exam Preparation Test Question No 2
The best approach to conflict resolution is:
Option A : Withdrawal
Option B : Smoothing.
Option C : Compromising.
Option D : Confronting.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Confronting.
PMP Exam Sample Exam Question No 3
Which of the following activities is completed during scope verification?
Option A : Product analysis.
Option B : Creation of work breakdown structure.
Option C : Performance measurement
Option D : Inspection
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Inspection
PMP Certification Exam Question No 4
Generally speaking an advantage of a fixed price contract is:
Option A : the cost risk is higher.
Option B : the cost risk is lower.
Option C : there is a medium amount of risk.
Option D : the risk is shared by all parties.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
the cost risk is lower.
Free PMP Practice Exam Question No 5
A relationship in a activity-on-arrow diagram are(is):
Option A : finish to start.
Option B : finish to finish.
Option C : finish to start, start to finish, finish to finish or start to start.
Option D : start to start or start to finish.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
finish to start.
Best PMP Exam Practice Question No 6
your project work was put on hold for 6 weeks due to the unforeseen backorder of the hardware equipment. You have confirmed with the supplier the hardware will be delivered to the second week of December. In order to keep to the customer schedule which is the first priority considerable overtime will be required by the technical team members during the upcoming holiday season. You know the technical team was only working over the holidays with a skeleton crew .What is the best action to take to
Option A : explain to the client that the backorder was unforeseen and it is now impossible to meet the original schedule.
Option B : First, give the employees the option to cancel their vacations and work the overtime.
Option C : Meet with the technical team and profusely apologize , but explain your hands are tied and they will have to unfortunately cancel their schedule vacations and work.
Option D : Arrange to hire contract employees to work over the holiday.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
First, give the employees the option to cancel their vacations and work the overtime.
Free PMP Exam Prep Question No 7
A war room is ________________
Option A : a required part of every project.
Option B : a room to give the project a physical location
Option C : the place where the office is
Option D : an advantage since all the project information can be located in one geographic location.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
an advantage since all the project information can be located in one geographic location.
Latest PMP Exam Question No 8
_____________, a well known motivational theorist , stated people can’t ascend to the next level of needs until the levels below have been fulfilled.
Option A : Maslow.
Option B : McGregor
Option C : Herzberg
Option D : Alderfer.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Maslow.
PMI PMP Exam Practice Question No 9
Look at the following depreciation example : Depreciable balance is $10,000,expected useful life is 4 years. Depreciations in the first year under double declining balance depreciation is _____________.
Option A : 2500
Option B : 4000
Option C : 5000
Option D : 10,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
5000
PMP Certification Exam Agile Question No 10
There are a number of estimating levels of accuracy , which one is defined as the budget estimate?
Option A : -25% to +75%
Option B : 5% to 10%
Option C : -10% to +25%
Option D : +/-5%
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
-10% to +25%