PMP Exam Prep Test 26 Questions With Explanations

Hi PMP aspirants, welcome to AKVTutorials. Ready to evaluate your knowledge of PMP concepts through scenario-based practice questions that mirror real-world project scenarios? Evaluate your readiness for real-world scenarios with our scenario-based PMP Project Management Professional practice questions, a key to comprehensive preparation. In this article, you will get PMP Exam Prep Test 26 Questions With Explanations. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Being assigned as a project manager, you noticed during project execution that conflicts arise in the team on both technical and interpersonal levels. What is an appropriate way of handling conflicts?

Option A : Conflicts distract the team and disrupt the work rhythm. You should always smooth them when they surface.

Option B : A conflict should be handled in a meeting so that the entire team can participate in finding a
solution. 

Option C : Conflicts should be addressed early and usually in private, using a direct, collaborative approach.

Option D : You should use your coercive power to quickly resolve conflicts and then focus on goal
achievement.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Conflicts should be addressed early and usually in private, using a direct, collaborative approach.

PMP Mock Test Question No 2

What is the purpose of a project charter?

Option A : To formally authorize a project or a phase and document initial requirements which satisfy the stakeholder’s needs and expectations.

Option B : To document how the project will be planned, executed, monitored/controlled, and closed.

Option C : To link the project, which is going to be planned, executed, and monitored/controlled to the ongoing work of the organization. 

Option D : To describe the process of performing the work defined in the project management plan in order to achieve the project’s objectives.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

To formally authorize a project or a phase and document initial requirements which satisfy the stakeholder’s needs and expectations.

PMP Practice Exam Question No 3

Which is a central objective of using a Kanban board?

Option A : Allowing for three-point estimation of work items

Option B : Limiting the number of items in the Work in Progress column

Option C : Allowing for Fibonacci numbers in estimation of epics

Option D : Giving the Scrum Master a tool to add stories to the backlog

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Limiting the number of items in the Work in Progress column

PMP Mock Exam Question No 4

What does the term continuous delivery often refer to?

Option A : A standardized set of deliverables, like plans, reports, and checklists.

Option B : A set of tools and techniques that a project manager should master. 

Option C : Increasing customer satisfaction by delivering valuable products and increments early. 

Option D : A specific sequence of work, described in terms of soft logic.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

A specific sequence of work, described in terms of soft logic.

Project Management Professional Question No 5

The communications management plan is a document which includes descriptions of

Option A : Project level performance reports 

Option B : Activity level status reports 

Option C : Stakeholder communication requirements

Option D : Project benefit analysis results

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Stakeholder communication requirements

PMP Certification Prep Question No 6

_________ are usually not a manifestation of unique organizational cultures and styles.

Option A : Shared visions, values, norms, beliefs, and expectations 

Option B : Individual traits and attitudes of co-workers 

Option C : Views of authority relationships 

Option D : Policies, methods, and procedures

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Individual traits and attitudes of co-workers 

PMP Exam Question No 7

Which of the following are generally regarded as elements of active listening?

Option A : Making eye contact

Option B : Pressurizing the speaker

Option C : Paraphrasing

Option D : Interpreting the information

Option E : Interrupting when appropriate

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A,C,D

Making eye contact, Paraphrasing, Interpreting the information

PMP Exam Sample Question No 8

As the project manager, you decided to arrange a team meeting to identify and analyze lessons learned from quality control with stakeholders. What should you do with them?

Option A : Document them and make them part of the historical database for the project and the performing organization.

Option B : Discuss them with management and make sure that they remain otherwise confidential

Option C : Publish them in the corporate newsletter.

Option D : Follow your strategic decisions, independent from lessons learned. These decisions have been made and should be implemented whatever the outcomes are.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Document them and make them part of the historical database for the project and the performing organization.

PMP Exam Practice Question No 9

Your Scrum Team is working with a Product Owner. During daily Scrum meetings, the person criticizes your team’s perceived “dysfunctionality” and requires that one developer should be delegated to take the lead? What could be an appropriate response to that? (Choose 2) 

Option A : The Product Owner’s job is to guide the direction of the product.

Option B : The Product Owner’s job is to validate the final deliverables of the project.

Option C : The Product Owner’s job is to verify that the rules of Scrum are adhered to.

Option D : The Product Owner should not join the Daily Scrums as he/she is not a member of the Scrum Team

Option E : The Product owner manages the product backlog for the Developer Team.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A,E

The Product Owner’s job is to guide the direction of the product, The Product owner manages the product backlog for the Developer Team.

PMP Certification Exam Question No 10

How should change management be planned for?

Option A : Changes are generally not predictable, therefore planning for change management cannot be reasonable. 

Option B : Planning for change management should be done while the various change control processes are being applied.

Option C : Change management can be planned in a set of management plans or a specific change
management plan. 

Option D : Changes are a sign of bad planning. One should avoid changes during a project, thus eliminating the need to manage them.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Change management can be planned in a set of management plans or a specific change management plan. 

New PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply