Hi PMP aspirants, welcome to AKVTutorials. Seeking PMP practice questions to fine-tune your Project Management Professional skills? Dive into PMP success with our Practice Questions—a strategic blend of challenge and insight for Project Management Professional aspirants. In this article, you will get PMP Project Management Professional Certification Exam Test 2 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

While meeting with the project team the project manager learns that the new department manager, while abroad, is raising questions. What should the project manager do next ?

Option A : Raise the issue with the project sponsor

Option B : Conduct a stakeholder analysis 

Option C : Refer the department manager to the change control board (CCB)

Option D : Provide the kick-off meeting notes to the department manager. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Conduct a stakeholder analysis

PMP Mock Test Question No 2

At the end of project execution, a project manager has retained some team members. What should the team be primarily focused on doing at this point?

Option A : Operating the newly completed facilities until the owners are fully competent

Option B : Assisting with clean up, site restoration, commissioning and personnel training 

Option C : Providing support as the part of warranty period associated with the handover

Option D : Supporting administrative project closure procedures as per companies policies

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Supporting administrative project closure procedures as per companies policies 

PMP Practice Exam Question No 3

During project execution, the quality controller becomes ill and will be out for two weeks. What should the project manager do?

Option A : Contract a quality controller from another similar company 

Option B : Assign another team member to control quality in the interim

Option C : Wait for the quality controller to return 

Option D : Allow each team member to verify their own deliverables

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Assign another team member to control quality in the interim

PMP Mock Exam Question No 4

As a project nears completion, the project manager learns that some stakeholders believe that the project failed to meet the schedule and ran over budget. The project
manager wants to invalidate that belief by providing data on project plans and end results. What type of analysis should the project manager conduct

Option A : Document 

Option B : Trend

Option C : Regression

Option D : Variance

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Trend

Project Management Professional Question No 5

The table lists project activities, with activities A and H as start and end activities. What is the project’s critical path?

Option A : A-B-D-G-H

Option B : A-C-F-G-H

Option C : A-B-D-E-H

Option D : A-C-D-G-H

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

A-C-D-G-H

PMP Certification Prep Question No 6

A team needs to install a large piece of equipment for a project, which can only be done when the plant is shut down. Plant shutdown is planned every year during the second week of May. Earlier in the project, the project manager identified a corresponding risk of project delay due to missing an installation window. At the end of April, an accident occurs that causes the plant to have an unplanned shutdown. The project team reschedules and completes the installation of the major equipment during this time. What should the project manager do next?

Option A : Keep the risk open until the plan target date

Option B : Create a lessons learned item for the resolution of the risk

Option C : Reward the team’s efforts 

Option D : Update the risk register by closing the risk 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Update the risk register by closing the risk 

PMP Exam Question No 7

A project manager is preparing a project closure presentation for stakeholders. One stakeholder has a history of refusing to sign off on project closures. What should the project manager do prior to the presentation?

Option A : Ask all stakeholders to review a detailed reports of project results. 

Option B : Ask the project sponsor to intervene with that stakeholders.

Option C : Prepare a response to a stakeholders most likely points of concern 

Option D : Talk to the stakeholder to understand any concern 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Talk to the stakeholder to understand any concern 

PMP Exam Sample Question No 8

While inspecting a contractor’s progress, the project manager notices that the contractor is behind schedule. The project manager speaks to the contractor who requests an extension. What should the project manager do next?

Option A : Conduct a performance review 

Option B : Issue a change requests 

Option C : Update the project schedule 

Option D : Verify the scope 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Conduct a performance review 

PMP Exam Practice Question No 9

An issue is raised during project execution but is not addressed. This delays product authorization. What should the project manager have done?

Option A : Assigned the issue to a responsible project team member and provided them with a realistic due date

Option B : Updated the change management plan to allow for changes during project execution

Option C : Followed the escalation process and engaged the project sponsor

Option D : Revised the schedule baseline to account for the change in the schedule

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Assign the responsibility to team experts for evaluation of the best use of this technology.

PMP Certification Exam Question No 10

A project manager learns that the development team is constantly delaying deliverables. Upon further inquiry, the project manager discovers that some members of the development team are trainees with inadequate experience. The development manager obtained prior information about the trainees, but failed to inform the project manager. The first deadline for submission of the design has already passed. What should the project manager do?

Option A : Schedule training for the inexperienced team members.

Option B : Request additional resources to complete the outstanding work.

Option C : Perform a qualitative risk analysis, and inform the client

Option D : Meet with the development manager to discuss the problem

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Meet with the development manager to discuss the problem

PMP Practice Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply