Hi PMP aspirants, welcome to AKVTutorials. Looking for a comprehensive set of PMP practice questions that address the nuances of stakeholder engagement and communication management? Excel in the PMP realm using our Practice Questions—a strategic asset designed for Project Management Professional victory. In this article, you will get PMP Exam Prep Test 129 Questions Answers Explanations PDF Free. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
The actual cost of work performed (ACWP) is the total of ___________________ incurred in accomplishing work on the activity during a given period
Option A : direct cost
Option B : indirect cost
Option C : overhead cost
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
during closure
PMP Exam Preparation Test Question No 2
A negative cost variance for a period indicates
Option A : cost underrun
Option B : cost overrun
Option C : scope creep in
Option D : data not sufficient to predict the cost performance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
cost overrun
PMP Exam Sample Exam Question No 3
A positive schedule variance for a period indicates
Option A : project can be completed in time
Option B : a delay is expected in the project execution
Option C : the project is ahead of schedule for the given time period
Option D : none of the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
the project is ahead of schedule for the given time period
PMP Certification Exam Question No 4
The value of 1.25 as cost performance index indicates
Option A : there is a cost overrun during the reporting period
Option B : more scope changes came in during the reporting period
Option C : the cost is under control for the reporting period
Option D : we should not assume anything while reporting the performance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
the cost is under control for the reporting period
Free PMP Practice Exam Question No 5
Some of the common formats used for performance reporting are
Option A : Gantt charts and tables
Option B : PERT charts and tables
Option C : S curves ,histograms
Option D : a and c
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and c
Best PMP Exam Practice Question No 6
Analysis of project performance often generates _____________ to some aspect of the project
Option A : request for change
Option B : action against the lagging team
Option C : cost cutting measures
Option D : fast tracking or crashing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
request for change
Free PMP Exam Prep Question No 7
The key output(s) from performance reporting process includes
Option A : performance reports
Option B : change requests.
Option C : project termination
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and b
Latest PMP Exam Question No 8
A project or phase needs a formal closure when
Option A : when the project objectives are met D
Option B : when the project /phase is terminated for various reasons
Option C : when there is no further funding is available for the project
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and b
PMI PMP Exam Practice Question No 9
Administrative closure for a project consists of
Option A : verification of project results D
Option B : documentation or project results
Option C : formalizing the acceptance of project product by the sponsor, client or customer
Option D : all the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all the above
PMP Certification Exam Agile Question No 10
Administrative closure for a project includes
Option A : collection of project records D
Option B : confirm that the results meet the final specifications
Option C : analysis of project success and effectiveness
Option D : all the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all the above