PMP Exam Prep Free Questions Paper 76 Answer Keys

Hi PMP aspirants, welcome to AKVTutorials. Ready to evaluate your knowledge of PMP concepts through scenario-based practice questions that mirror real-world project scenarios? Elevate your leadership and team motivation skills using our practice questions, an essential aspect of Project Management Professional excellence. In this article, you will get PMP Exam Prep Free Questions Paper 76 Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Valid reasons for considering termination of a project include all of the following except: 

Option A : The scope of the project is found to be inconsistent with the organizations financial strength 

Option B : Organizational support is being spread among too many projects 

Option C : Scope change requests are numerous and continuous 

Option D : The project product has become available as a commercial off the shelf product 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Scope change requests are numerous and continuous 

PMP Mock Test Question No 2

Project termination responsibilities include all of the following except: 

Option A : Ensure the completion of work 

Option B : Notify the client of completion and ensure delivery of the product 

Option C : Ensure that documentation is complete

Option D : Ensure that the project baseline is updated to reflect actual project performance 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Ensure that the project baseline is updated to reflect actual project performance 

PMP Practice Exam Question No 3

 Project termination responsibilities include all of the following except: 

Option A : Modify project quality standards to reflect those actually implemented 

Option B : Oversee preparation of final invoices for the client

Option C : Redistribute personnel, materials, equipment, and other resources 

Option D : Record and archive all legal project documents

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Modify project quality standards to reflect those actually implemented 

PMP Mock Exam Question No 4

Project termination responsibilities include all of the following except:

Option A : Archive appropriate project documentation 

Option B : Provide project personnel with favorable performance appraisals to ensure their future cooperation 

Option C : Ensure the fulfillment of product support requirements 

Option D : Oversee the closing of project accounting

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Provide project personnel with favorable performance appraisals to ensure their future cooperation 

Project Management Professional Question No 5

Which equation correctly illustrates the cost variance of a project, in dollars?

Option A : BCWP-ACWP 

Option B : BCWP/ACWP 

Option C : BCWP-BCWS 

Option D : BCWP/BCWS

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

BCWP-ACWP 

PMP Certification Prep Question No 6

The “To Complete Performance Index” (TCPI) is calculated by: 

Option A : Subtracting the actual costs to date from the estimate at completion 

Option B : Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date 

Option C : Multiplying the estimate at completion by the cumulative cost performance index 

Option D : Adding the estimate at completion to the actual costs to date and multiplying by the cumulative cost performance index 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date 

PMP Exam Question No 7

At 40% through your project you have a BCWS of $68,000 and a BCWP of $62,000. Your project is: 

Option A : Ahead of schedule 

Option B : Behind schedule

Option C : A positive cost variance 

Option D : A negative cost variance 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Behind schedule

PMP Exam Sample Question No 8

Under what knowledge area is the primary process area for carrying out the work of the project? 

Option A : Scope 

Option B : Integration 

Option C : Schedule 

Option D : Framework 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Integration 

PMP Exam Practice Question No 9

 Which of the following is not true about Project Plan Development? 

Option A : Wait until all the other planning outputs are complete, then compile them into one final project plan 

Option B : It is used to document project planning assumptions 

Option C : It is an iterative process 

Option D : It involves making trade offs between competing objectives and alternatives 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Wait until all the other planning outputs are complete, then compile them into one final project plan 

PMP Certification Exam Question No 10

Coordinating a schedule, organizational policies, staffing plans and historical information about risk is an example of:

Option A : Overall change control 

Option B : Risk management 

Option C : Communication planning 

Option D : Project plan development

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project plan development

Practice Test PMP Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply