Hi PMP aspirants, welcome to AKVTutorials. Ready to evaluate your knowledge of PMP concepts through scenario-based practice questions that mirror real-world project scenarios? Elevate your leadership and team motivation skills using our practice questions, an essential aspect of Project Management Professional excellence. In this article, you will get PMP Exam Prep Free Questions Paper 76 Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Valid reasons for considering termination of a project include all of the following except:
Option A : The scope of the project is found to be inconsistent with the organizations financial strength
Option B : Organizational support is being spread among too many projects
Option C : Scope change requests are numerous and continuous
Option D : The project product has become available as a commercial off the shelf product
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Scope change requests are numerous and continuous
PMP Mock Test Question No 2
Project termination responsibilities include all of the following except:
Option A : Ensure the completion of work
Option B : Notify the client of completion and ensure delivery of the product
Option C : Ensure that documentation is complete
Option D : Ensure that the project baseline is updated to reflect actual project performance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Ensure that the project baseline is updated to reflect actual project performance
PMP Practice Exam Question No 3
Project termination responsibilities include all of the following except:
Option A : Modify project quality standards to reflect those actually implemented
Option B : Oversee preparation of final invoices for the client
Option C : Redistribute personnel, materials, equipment, and other resources
Option D : Record and archive all legal project documents
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Modify project quality standards to reflect those actually implemented
PMP Mock Exam Question No 4
Project termination responsibilities include all of the following except:
Option A : Archive appropriate project documentation
Option B : Provide project personnel with favorable performance appraisals to ensure their future cooperation
Option C : Ensure the fulfillment of product support requirements
Option D : Oversee the closing of project accounting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Provide project personnel with favorable performance appraisals to ensure their future cooperation
Project Management Professional Question No 5
Which equation correctly illustrates the cost variance of a project, in dollars?
Option A : BCWP-ACWP
Option B : BCWP/ACWP
Option C : BCWP-BCWS
Option D : BCWP/BCWS
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
BCWP-ACWP
PMP Certification Prep Question No 6
The “To Complete Performance Index” (TCPI) is calculated by:
Option A : Subtracting the actual costs to date from the estimate at completion
Option B : Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date
Option C : Multiplying the estimate at completion by the cumulative cost performance index
Option D : Adding the estimate at completion to the actual costs to date and multiplying by the cumulative cost performance index
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date
PMP Exam Question No 7
At 40% through your project you have a BCWS of $68,000 and a BCWP of $62,000. Your project is:
Option A : Ahead of schedule
Option B : Behind schedule
Option C : A positive cost variance
Option D : A negative cost variance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Behind schedule
PMP Exam Sample Question No 8
Under what knowledge area is the primary process area for carrying out the work of the project?
Option A : Scope
Option B : Integration
Option C : Schedule
Option D : Framework
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Integration
PMP Exam Practice Question No 9
Which of the following is not true about Project Plan Development?
Option A : Wait until all the other planning outputs are complete, then compile them into one final project plan
Option B : It is used to document project planning assumptions
Option C : It is an iterative process
Option D : It involves making trade offs between competing objectives and alternatives
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Wait until all the other planning outputs are complete, then compile them into one final project plan
PMP Certification Exam Question No 10
Coordinating a schedule, organizational policies, staffing plans and historical information about risk is an example of:
Option A : Overall change control
Option B : Risk management
Option C : Communication planning
Option D : Project plan development
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project plan development