Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want practice questions that align with the agile mindset and principles? Immerse yourself in PMP excellence with our practice questions, covering both predictive and agile methodologies to fortify your Project Management Professional preparation.. In this article, you will get PMP Exam Practice Test Questions Paper 133 Answer Keys. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
Which equation correctly illustrates the cost variance of a project, in currency?
Option A : BCWP-ACWP
Option B : BCWP/ACWP
Option C : BCWP-BCWS
Option D : BCWP/BCWS
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
BCWP-ACWP
PMP Exam Preparation Test Question No 2
You are approximately 30% through your project and the sponsor wants a forecast of the final budget based on what has already been spent. You create an S curve chart display of what kind of performance report:
Option A : Earned value
Option B : Trend analysis
Option C : Variance analysis
Option D : Cost distribution curve
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Trend analysis
PMP Exam Sample Exam Question No 3
At 40% through your project you have a BCWS of $68,000 and a BCWP of $62,000. Your project is:
Option A : Ahead of schedule
Option B : Behind schedule
Option C : A positive cost variance
Option D : A negative cost variance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Behind schedule
PMP Certification Exam Question No 4
In preparing for a team meeting you want to let the team know how they are doing on the project schedule over all. You calculate the task achievements as follows: planning has a BCWS of $20,000 and a BCWP of $25,000, testing has a BCWS of $17,000 and BCWP of $15,000, and design has a BCWS of $34,000 and a BCWP of $42,000. As a whole your project is:
Option A : 15% ahead of schedule
Option B : 15% behind schedule
Option C : 15% ahead of schedule, but over budget
Option D : 15% behind schedule and budget
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
15% ahead of schedule
Free PMP Practice Exam Question No 5
In order to let the project sponsor know the percentage of cost variance of your project, you calculate:
Option A : BCWP-BCWS
Option B : BCWP/BCWS
Option C : BCWP/ACWP
Option D : BCWP-ACWP
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
BCWP/ACWP
Best PMP Exam Practice Question No 6
As the project manager, you chair a weekly exchange of information meeting among
team leaders. This is an example of communication that is:
Option A : Internal, formal, and horizontal
Option B : External, informal, and vertical
Option C : Oral, internal, and informal
Option D : Oral, external, and formal
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Oral, internal, and informal
Free PMP Exam Prep Question No 7
Manual filing systems, electronic text databases, and project management software that allow team members to share information about the project are examples of:
Option A : A communication management plan
Option B : An information retrieval system
Option C : An information distribution system
Option D : A project management information system
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
An information retrieval system
Latest PMP Exam Question No 8
During project team formation and during the early phases of a project, the most common source of conflict within the project team is likely to be:
Option A : Schedules
Option B : Priorities
Option C : Technical opinions
Option D : Cost
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Priorities
PMI PMP Exam Practice Question No 9
During execution of a project, the most common source of conflict within the project team is likely to be:
Option A : Schedules
Option B : Priorities
Option C : Technical opinions
Option D : Cost
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Schedules
PMP Certification Exam Agile Question No 10
Of the following, which conflict resolution strategy is likely to yield the most productive results?
Option A : Withdrawing
Option B : Forcing T
Option C : Compromising
Option D : Collaborating
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Collaborating