Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want practice questions that align with the agile mindset and principles? Immerse yourself in PMP excellence with our practice questions, covering both predictive and agile methodologies to fortify your Project Management Professional preparation.. In this article, you will get PMP Exam Practice Test Questions Paper 133 Answer Keys. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

Which equation correctly illustrates the cost variance of a project, in currency? 

Option A : BCWP-ACWP 

Option B : BCWP/ACWP

Option C : BCWP-BCWS 

Option D : BCWP/BCWS

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

BCWP-ACWP 

PMP Exam Preparation Test Question No 2

You are approximately 30% through your project and the sponsor wants a forecast of the final budget based on what has already been spent. You create an S curve chart display of what kind of performance report: 

Option A : Earned value 

Option B : Trend analysis 

Option C : Variance analysis 

Option D : Cost distribution curve 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Trend analysis 

PMP Exam Sample Exam Question No 3

At 40% through your project you have a BCWS of $68,000 and a BCWP of $62,000. Your project is: 

Option A : Ahead of schedule 

Option B : Behind schedule 

Option C : A positive cost variance 

Option D : A negative cost variance

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Behind schedule 

PMP Certification Exam Question No 4

In preparing for a team meeting you want to let the team know how they are doing on the project schedule over all. You calculate the task achievements as follows: planning has a BCWS of $20,000 and a BCWP of $25,000, testing has a BCWS of $17,000 and BCWP of $15,000, and design has a BCWS of $34,000 and a BCWP of $42,000. As a whole your project is:

Option A : 15% ahead of schedule 

Option B : 15% behind schedule 

Option C : 15% ahead of schedule, but over budget 

Option D : 15% behind schedule and budget 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

15% ahead of schedule 

Free PMP Practice Exam Question No 5

In order to let the project sponsor know the percentage of cost variance of your project, you calculate: 

Option A : BCWP-BCWS 

Option B : BCWP/BCWS

Option C : BCWP/ACWP 

Option D : BCWP-ACWP

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

BCWP/ACWP

Best PMP Exam Practice Question No 6

 As the project manager, you chair a weekly exchange of information meeting among
team leaders. This is an example of communication that is:

Option A : Internal, formal, and horizontal 

Option B : External, informal, and vertical 

Option C : Oral, internal, and informal 

Option D : Oral, external, and formal 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Oral, internal, and informal 

Free PMP Exam Prep Question No 7

Manual filing systems, electronic text databases, and project management software that allow team members to share information about the project are examples of: 

Option A : A communication management plan 

Option B : An information retrieval system 

Option C : An information distribution system 

Option D : A project management information system

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

An information retrieval system 

Latest PMP Exam Question No 8

During project team formation and during the early phases of a project, the most common source of conflict within the project team is likely to be: 

Option A : Schedules 

Option B : Priorities 

Option C : Technical opinions 

Option D : Cost 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Priorities 

PMI PMP Exam Practice Question No 9

During execution of a project, the most common source of conflict within the project team is likely to be: 

Option A : Schedules 

Option B : Priorities 

Option C : Technical opinions 

Option D : Cost 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Schedules 

PMP Certification Exam Agile Question No 10

Of the following, which conflict resolution strategy is likely to yield the most productive results? 

Option A : Withdrawing 

Option B : Forcing T

Option C : Compromising

Option D : Collaborating 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Collaborating 

PMP Project Management Professional Practice Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply