Hi PMP aspirants, welcome to AKVTutorials. Seeking a reliable platform for PMP practice questions that focus on risk management, a critical aspect of Project Management Professional certification? Secure your PMP success by mastering risk management with our practice questions, focusing on this critical aspect of Project Management Professional certification. In this article, you will get PMP Exam Practice Test 25 Questions Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
Option A : Critical path method
Option B : Flowchart
Option C : Precedence diagramming
Option D : Work breakdown structure
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Critical path method
PMP Mock Test Question No 2
A project manager has assembled the project team, identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions and assessed the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?
Option A : Simulation
Option B : Risk mitigation
Option C : Overall risk ranking for the project
Option D : Involving of other stakeholders
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Involving of other stakeholders
PMP Practice Exam Question No 3
Configuration management plan is:
Option A : Used to ensure that the description of the project product is correct and complete.
Option B : The creation of the work breakdown structure.
Option C : The set of procedures developed to control changes.
Option D : A mechanism to track budget and schedule variances.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The set of procedures developed to control changes.
PMP Mock Exam Question No 4
A rough order of magnitude estimate is made during which project management process group?
Option A : Project planning
Option B : Project closing
Option C : Project executing
Option D : Project initiating
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project initiating
Project Management Professional Question No 5
The work defined at the lowest level of the breakdown structure to estimate as well as manage time and cost is called the:
Option A : Activity
Option B : Task
Option C : Work package
Option D : Cost account
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Work package
PMP Certification Prep Question No 6
A project manager is working on an assessment project with a tight timeline. What should the project manager do first?
Option A : Develop a data-capturing system.
Option B : Look for lessons learned from previous, similar projects
Option C : Create a questionnaire for assessor proposals.
Option D : Appoint assessors and resources.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Look for lessons learned from previous, similar projects
PMP Exam Question No 7
All of the following are examples of the cost of nonconformance EXCEPT?
Option A : Rework
Option B : Quality training
Option C : Scrap
Option D : Warranty costs
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Quality training
PMP Exam Sample Question No 8
What type of contract do you not want to use if you do not have enough labor to audit invoices?
Option A : Cost plus fixed fee CPFF
Option B : Time & material T&M
Option C : Fixed price FPC
Option D : Fixed price incentive fee FPIF
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Cost plus fixed fee CPFF
PMP Exam Practice Question No 9
A project manager has just been assigned to a project. The document that recognizes the existence of the project is called:
Option A : The statement of work
Option B : The project assignment.
Option C : The project charter
Option D : The product description.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The project charter.
PMP Certification Exam Question No 10
The WBS for the project represents:
Option A : All the tangible items that must be delivered to the client.
Option B : All the work that must be completed for the project.
Option C : The work that must be performed by the project team.
Option D : All the activities of the project.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
All the work that must be completed for the project.