Hi PMP aspirants, welcome to AKVTutorials. Are you aiming for PMP success and need practice questions that align with the latest changes in the Project Management Professional exam content? Propel yourself toward PMP success by practicing with our updated questions, aligning with the latest changes in the Project Management Professional exam content. In this article, you will get PMP Exam Practice Test 24 Study Guide Latest Edition. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Quality is:

Option A : meeting and exceeding the customer’s expectations.

Option B : adding extras to make the customer happy

Option C : the degree to which the inherent characteristics fulfill requirements.

Option D : conformance to management’s objectives

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

the degree to which the inherent characteristics fulfill requirements.

PMP Mock Test Question No 2

A schedule performance index SPI of 0.76 means:

Option A : you are over budget.

Option B : you are ahead of schedule

Option C : you are only progressing at 76 percent of the rate originally planned.

Option D : you are only progressing at 24 percent of the rate originally planned.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

you are only progressing at 76 percent of the rate originally planned.

PMP Practice Exam Question No 3

Contract closure is different from administrative closure in that contract closure:

Option A : occurs before administrative closure.

Option B : is the only one to involve the customer.

Option C : includes the return of property.

Option D : may be done more than once for each contract

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

occurs before administrative closure.

PMP Mock Exam Question No 4

During the full life cycle of the project, a plot of the projects expected expenditures will usually follow a characteristic ..S.. shape. This indicates that:

Option A : There is a cyclic nature to all projects.

Option B : Problems will always occur in the execution phase.

Option C : There are high expenditures during closeout.

Option D : The bulk of the project budget will be spent in the execution phase.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Cause-and-effect analysis

Project Management Professional Question No 5

An output of administrative closure is the creation of:

Option A : project archives.

Option B : a project charter.

Option C : a project management plan

Option D : a risk analysis plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

project archives.

PMP Certification Prep Question No 6

A temporary endeavor undertaken to create a new product or service is called a:

Option A : New product development.

Option B : Project.

Option C : Program.

Option D : Enterprise.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Project.

PMP Exam Question No 7

An example of scope validation is:

Option A : Reviewing the performance of an installed software module.

Option B : Managing changes to the project schedule

Option C : Decomposing the WBS to a work package level.

Option D : Performing a benefit-cost analysis to determine if we should proceed.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Reviewing the performance of an installed software module.

PMP Exam Sample Question No 8

What conflict resolution technique is a project manager using when he says, “I cannot deal with this issue now!”

Option A : Problem solving

Option B : Forcing.

Option C : Withdrawal

Option D : Conduct a meeting to understand the impact of this issue and document the lessons learned.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 Withdrawal

Explanation: Avoidance or procrastination to deal with an issue comes under Withdrawal

PMP Exam Practice Question No 9

Approved Change Requests are an input to:

Option A : Control Scope and Validate Scope.

Option B : Direct and Manage Project Work.

Option C : develop project management plan and develop project charter.

Option D : Develop Project Management Plan and Develop Schedule.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Direct and Manage Project Work.

PMP Certification Exam Question No 10

A group of related projects that are managed in a coordinated way that usually include an element of ongoing activity is called a:

Option A : Major project.

Option B : Project office.

Option C : Program.

Option D : Group of projects.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Program.

PMP Certification Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply