PMP Exam Practice Test 23 Questions And Solutions

Hi PMP aspirants, welcome to AKVTutorials. Looking for a diverse set of PMP Project Management Professional practice questions to reinforce your grasp of the PMBOK Guide? Explore the depths of PMP knowledge using our comprehensive set of Project Management Professional practice questions that reinforce your grasp of the PMBOK Guide. In this article, you will get PMP Exam Practice Test 23 Questions And Solutions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A cost performance index CPI of 0.89 means:

Option A : at this time, we expect the total project to cost 89 percent more than planned.

Option B : when the project is completed we will have spent 89 percent more than planned.

Option C : Earned value management (EVM)

Option D : the project is only getting 89 cents out of every dollar invested.

Show/Hide Answer

Answer Keys: YES

Explanation: YES

Correct Answer: D

the project is only getting 89 cents out of every dollar invested.

Explanation:

the project is only getting 89 cents out of every dollar invested.

PMP Mock Test Question No 2

In a matrix organization, which of the following is true??

Option A : The project manager is responsible for employee skills improvement.

Option B : The functional manager is responsible for employee skills improvement.

Option C : The project manager is responsible for the employees annual appraisal

Option D : The employee is responsible for his or her own skills improvement.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: B

The functional manager is responsible for employee skills improvement.

PMP Practice Exam Question No 3

Your program manager has come to you, the project manager, for help with a bid for her newest project. You want to protect your company from financial risk. You have limited scope definition. What is the BEST type of contract to choose?

Option A : Fixed price FP

Option B : Cost plus percent of cost CPPC

Option C : Time and material T&M

Option D : Cost plus fixed fee CPFF

Show/Hide Answer

Answer Keys: YES

Explanation: YES

Correct Answer: D

Cost plus fixed fee CPFFE

Explanation:

CPFF is the best contract type from buyer perspective as the seller is aware that cost overruns may have to be borne by him.

PMP Mock Exam Question No 4

The project management process groups are:

Option A : Initiating, planning, expediting, and control.

Option B : Plan, organize, develop, and control.

Option C : Plan, do, observe, commit.

Option D : Initiating, planning, executing, monitoring &controlling, and closing.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: D

Initiating, planning, executing, monitoring &controlling, and closing.

Project Management Professional Question No 5

In which project management process group is the detailed project budget created?

Option A : Initiating

Option B : Before the project management process

Option C : Planning

Option D : Executing

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: C

Planning

PMP Certification Prep Question No 6

Which of the following conflict resolution techniques will generate the MOST lasting solution?

Option A : Forcing

Option B : Smoothing

Option C : Compromise

Option D : Problem solving

Show/Hide Answer

Answer Keys: YES

Explanation: YES

Correct Answer: D

Problem solving

Explanation:

Except Problem Solving, all other approaches are temporary solutions resulting in recurring conflicts.

PMP Exam Question No 7

Breaking the major deliverables into smaller, more manageable components to provide better control is called:

Option A : Scope planning.

Option B : Decomposition.

Option C : Scope base lining.

Option D : Bill of Materials BOM.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: B

Decomposition.

PMP Exam Sample Question No 8

Which of the following is NOT an input to the initiating process group?

Option A : Company processes

Option B : The company culture

Option C : Historical WBSs

Option D : Project scope statement

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: D

Project scope statement

PMP Exam Practice Question No 9

Workarounds are determined during which risk management process?

Option A : Identify Risks

Option B : Perform Quantitative Risk Analysis

Option C : Plan Risk Responses

Option D : Control Risks

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Control Risks

PMP Certification Exam Question No 10

A person who is involved in or may be affected by the activities or anyone who has something to gain or lose by the activity of the project is called a:

Option A : Team member.

Option B : Customer

Option C : Stakeholder

Option D : Supporter

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 Stakeholder

Project Management Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply