Hi PMP aspirants, welcome to AKVTutorials. Looking for a diverse set of PMP Project Management Professional practice questions to reinforce your grasp of the PMBOK Guide? Explore the depths of PMP knowledge using our comprehensive set of Project Management Professional practice questions that reinforce your grasp of the PMBOK Guide. In this article, you will get PMP Exam Practice Test 23 Questions And Solutions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
A cost performance index CPI of 0.89 means:
Option A : at this time, we expect the total project to cost 89 percent more than planned.
Option B : when the project is completed we will have spent 89 percent more than planned.
Option C : Earned value management (EVM)
Option D : the project is only getting 89 cents out of every dollar invested.
Show/Hide Answer
Answer Keys: YES
Explanation: YES
Correct Answer: D
the project is only getting 89 cents out of every dollar invested.
Explanation:
the project is only getting 89 cents out of every dollar invested.
PMP Mock Test Question No 2
In a matrix organization, which of the following is true??
Option A : The project manager is responsible for employee skills improvement.
Option B : The functional manager is responsible for employee skills improvement.
Option C : The project manager is responsible for the employees annual appraisal
Option D : The employee is responsible for his or her own skills improvement.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: B
The functional manager is responsible for employee skills improvement.
PMP Practice Exam Question No 3
Your program manager has come to you, the project manager, for help with a bid for her newest project. You want to protect your company from financial risk. You have limited scope definition. What is the BEST type of contract to choose?
Option A : Fixed price FP
Option B : Cost plus percent of cost CPPC
Option C : Time and material T&M
Option D : Cost plus fixed fee CPFF
Show/Hide Answer
Answer Keys: YES
Explanation: YES
Correct Answer: D
Cost plus fixed fee CPFFE
Explanation:
CPFF is the best contract type from buyer perspective as the seller is aware that cost overruns may have to be borne by him.
PMP Mock Exam Question No 4
The project management process groups are:
Option A : Initiating, planning, expediting, and control.
Option B : Plan, organize, develop, and control.
Option C : Plan, do, observe, commit.
Option D : Initiating, planning, executing, monitoring &controlling, and closing.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: D
Initiating, planning, executing, monitoring &controlling, and closing.
Project Management Professional Question No 5
In which project management process group is the detailed project budget created?
Option A : Initiating
Option B : Before the project management process
Option C : Planning
Option D : Executing
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: C
Planning
PMP Certification Prep Question No 6
Which of the following conflict resolution techniques will generate the MOST lasting solution?
Option A : Forcing
Option B : Smoothing
Option C : Compromise
Option D : Problem solving
Show/Hide Answer
Answer Keys: YES
Explanation: YES
Correct Answer: D
Problem solving
Explanation:
Except Problem Solving, all other approaches are temporary solutions resulting in recurring conflicts.
PMP Exam Question No 7
Breaking the major deliverables into smaller, more manageable components to provide better control is called:
Option A : Scope planning.
Option B : Decomposition.
Option C : Scope base lining.
Option D : Bill of Materials BOM.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: B
Decomposition.
PMP Exam Sample Question No 8
Which of the following is NOT an input to the initiating process group?
Option A : Company processes
Option B : The company culture
Option C : Historical WBSs
Option D : Project scope statement
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: D
Project scope statement
PMP Exam Practice Question No 9
Workarounds are determined during which risk management process?
Option A : Identify Risks
Option B : Perform Quantitative Risk Analysis
Option C : Plan Risk Responses
Option D : Control Risks
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Control Risks
PMP Certification Exam Question No 10
A person who is involved in or may be affected by the activities or anyone who has something to gain or lose by the activity of the project is called a:
Option A : Team member.
Option B : Customer
Option C : Stakeholder
Option D : Supporter
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
 Stakeholder