Hi PMP aspirants, welcome to AKVTutorials. Seeking a reliable platform for PMP practice questions that focus on risk management, a critical aspect of Project Management Professional certification? Conquer risk management challenges with our PMP practice questions, evaluating your ability to identify, analyze, and respond to project risks. In this article, you will get PMP Exam Practice Questions Paper 75 Solutions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Inputs to overall change control include all of the following except: 

Option A : The project plan 

Option B : Performance reports 

Option C : Change requests

Option D : Corrective action

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Corrective action

PMP Mock Test Question No 2

Where is the bulk of the project budget spent? 

Option A : Scope management 

Option B : Production 

Option C : Labor and materials

Option D : Project plan execution 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project plan execution 

PMP Practice Exam Question No 3

A work authorization system is: 

Option A : The control mechanism used to track cost packages

Option B : A variation of the work breakdown structure 

Option C : A formal procedure for sanctioning project work 

Option D : A policy and procedure that sets the days and hours for the project schedule 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A formal procedure for sanctioning project work 

PMP Mock Exam Question No 4

Which is not a tool or technique for project plan execution 

Option A : General management skills 

Option B : Work authorization system 

Option C : Work breakdown structure 

Option D : Product skills and knowledge

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Work breakdown structure 

Project Management Professional Question No 5

All of the following are true of Administrative Closure except: 

Option A : It includes verifying and documenting project results 

Option B : It includes collection of project records 

Option C : It includes analysis of project success and effectiveness

Option D : It should be delayed until project completion 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

It should be delayed until project completion 

PMP Certification Prep Question No 6

Meredith & Mantel describe four varieties of project termination which include all of the following except: 

Option A : Termination by Extinction 

Option B : Termination by Subtraction

Option C : Termination by Integration 

Option D : Termination by Starvation 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Termination by Subtraction

PMP Exam Question No 7

 Your new product development project has resulted in a highly successful new product. The property, equipment, materials, and personnel of your project are now being integrated into the functional organization. Your project is being terminated by: 

Option A : Extinction 

Option B : Addition 

Option C : Integration

Option D : Starvation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 Integration 

PMP Exam Sample Question No 8

Your project to create a new time tracking and accounting system has been put on hold pending a decision to bring in a third party human resources system that will handle multiple functions. If this decision is made, your project will be terminated by: 

Option A : Extinction 

Option B : Subtraction 

Option C : Integration 

Option D : Starvation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Extinction 

PMP Exam Practice Question No 9

As the most recent in a succession of project managers assigned to the project, you discover that one of your projects has no people assigned to it, no deliverables scheduled for development, and an extremely small budget. Nevertheless, you are expected to report status for the project periodically. This project has, in fact, experienced termination by: 

Option A : Extinction

Option B : Addition 

Option C : Integration

Option D : Starvation 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Starvation 

PMP Certification Exam Question No 10

Your new product development project has resulted in a highly successful new product. You find that you are being promoted to lead a new business unit to produce and market the product. Your project is being terminated by:

Option A : Extinction 

Option B : Addition 

Option C : Integration 

Option D : Starvation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Addition 

PMP Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply