Hi PMP aspirants, welcome to AKVTutorials. Are you in search of high-quality PMP Project Management Professional practice questions to elevate your exam preparation? Navigate the path to PMP mastery with our Practice Questions—a game-changing resource for Project Management Professional hopefuls. In this article, you will get PMP Exam Mock Test 51 Questions And Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

On a given project; actual cost (AC) is $500,00; estimate at completion (EAC) is $800,000; and planned value is $850,000. What is estimate to completion (ETC)?

Option A : $50,000

Option B : $350,000 

Option C : $300,000 

Option D : $1,300,000

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

$300,000

PMP Mock Test Question No 2

On a project to setup a technology environment that allows a clothing business to process and gather insights from large volumes of customer data, the team spends time formally closing the project. What is an output from that process?

Option A : Agreements

Option B : Final Report 

Option C : Procurement Documentation

Option D : Accepted Deliverables

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Final Report 

PMP Practice Exam Question No 3

You have just been assigned to lead a project that is already underway. The objective is to design and test a new self-driving car. At this time, the develop team process is being performed. In doing so, which of the following activities might be completed?

Option A : Arranging for key project team members to be at the same site near critical milestones

Option B : Resolving a conflict between two team members.

Option C : Ensuring that assigned resources are available as originally planned. 

Option D : Evaluating alternative resource options, such as renting or buying the needed equipment.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Arranging for key project team members to be at the same site near critical milestones

PMP Mock Exam Question No 4

A fast food restaurant chain is working on a project that involves piloting the use of drone technology to make local deliveries. During the project, the team spends time documenting how the schedule will be developed and controlled. What is an input to that particular process?

Option A : Activity List 

Option B : Schedule Management Plan 

Option C : Work Performance Data 

Option D : Project Charter

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project Charter

Project Management Professional Question No 5

On a given project, the budget at completion (BAC) is $375,000. If your current estimate to completion (ETC) is $50,000 and estimate at completion (EAC) is $300,000; what is the variance at completion (VAC)?

Option A : $75,000

Option B : -$50,000 

Option C : $25,000

Option D : -$25,000

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

$75,000

PMP Certification Prep Question No 6

A project is underway to launch a new service that allows users to share bikes on college campuses. During the project, the team spends time documenting how to estimate, acquire, and manage required project resources. What is an output from that process?

Option A : Resource Breakdown Structure 

Option B : Project Team Assignments 

Option C : Resource Requirements 

Option D : Team Charter

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Team Charter

PMP Exam Question No 7

A project to develop a web-based inventory management system is ongoing. Currently, the team is performing the manage project knowledge process. In doing so, which of the following activities might they complete?

Option A : Evaluating project performance to determine if any preventive or corrective action is needed. 

Option B : Archiving project information and releasing and reallocating project resources. 

Option C : Allocating available resources (labor, material, and equipment) to activities in the project plan. 

Option D : Considering positive and negative experiences from previous projects to increase the  likelihood of success on the current project

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Considering positive and negative experiences from previous projects to increase the likelihood of success on the current project

PMP Exam Sample Question No 8

A project in Europe is underway to secure an electric grid to reduce the likelihood of a computer hack. During the project, the team spends time defining strategies and action to address project risks. Which of the following is not a tool or technique that may be needed to perform this process?

Option A : Contingent Response Strategies

Option B : Cost-Benefit Analysis 

Option C : Decision Tree Analysis 

Option D : Strategies for Threats

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Decision Tree Analysis.

PMP Exam Practice Question No 9

A project to renovate a hotel that was built in the 1970s is underway. Currently, the team is performing the control quality process. In doing so, which of the following activities might they complete?

Option A : Using audits to determine if activities on the project are conforming to organizational policies and then addresses gaps, if needed.

Option B : Testing project deliverables to identify errors or defects. 

Option C : Using the six sigma methodology to identify process improvement opportunities. 

Option D : Determining appropriate investments in prevention and appraisal costs in order to avoid quality failures

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Using audits to determine if activities on the project are conforming to organizational policies and then addresses gaps, if needed.

PMP Certification Exam Question No 10

You were recently hired by a gaming company to lead a strategic project. Before moving forward, you understand that the structure of the organization will influence your work. The gaming company is considered a projectized organization. Which of the following is not true about that organizational type?

Option A : Project managers hold more authority than functional managers

Option B : Resource availability for projects is high

Option C : Functional managers control less of the budgets than project managers

Option D : Project managers have roles that are part-time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Project managers hold more authority than functional managers

PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply