Hi PMP aspirants, welcome to AKVTutorials. Looking for PMP practice questions that focus on the role of the project manager in promoting diversity, equity, and inclusion within project teams? Foster diversity, equity, and inclusion within project teams using our practice questions, reflecting the evolving role of the project manager in promoting a positive work environment. In this article, you will get PMP Exam Example Questions Paper 49. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
A project manager is working with a team to train employees at a technology company in Lean Six Sigma. At this point, she needs to determine what levels of cost variance are acceptable before action needs to be taken. Which document should be reviewed to find this information?
Option A : Work Performance Report
Option B : Risk Management Plan
Option C : Cost Management Plan
Option D : Cost Baseline
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Cost Management Plan
PMP Mock Test Question No 2
A project to configure new content management software for an online news agency is underway. Currently, the team is performing the plan schedule management process. In doing so, which of the following activities might they complete?
Option A : Evaluating project scope and required resources in order to approximate the number of work periods needed to complete the activities
Option B : Identifying methods that will be used to develop the project timeline.
Option C : Mapping the flow of activities to most efficiently complete the work given various constraints.
Option D : Working with team members to identify the steps required to complete project work packages
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Identifying methods that will be used to develop the project timeline.
PMP Practice Exam Question No 3
Your project team gets together outside of work to socialize and strengthen relationships. As a result, communication and trust improves among team members. In this scenario, which process was used?
Option A : Plan Resource Management
Option B : Manage Team
Option C : Manage Communications
Option D : Develop Team
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Manage Communications
PMP Mock Exam Question No 4
At this point on your project, you are in the process of managing the team, which includes tracking their performance and providing them feedback. Which of the following are inputs of that process?
Option A : Team Charter, Change Requests, Work Performance Data
Option B : Resource Management Plan, Agreements, Resource Calendars
Option C : Work Performance Reports, Team Performance Assessments, Environmental Process Assets
Option D : Team Performance Assessments, Organizational Process Assets, Project Charter
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Work Performance Reports, Team Performance Assessments, Environmental Process Assets
Project Management Professional Question No 5
On a home renovation project, the team aggregates the costs that had been estimated for demolition, paint, flooring, and appliances. They also add reserve for unknown events that arise. In this scenario, which of the following processes were used?
Option A : Estimate Costs
Option B : Determine Budget
Option C : Plan Cost Management
Option D : Control Costs
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Determine Budget
PMP Certification Prep Question No 6
At a recent meeting on a project to remodel a hotel that was constructed more than 60 years ago, you inform your stakeholders that you are in the process of conducting procurements. What is an activity that could be performed during that process?
Option A : Confirming that payments are made to sellers as outlined in the terms of the contract.
Option B : Preparing a request for information to get feedback from potential vendors.
Option C : Defining the portion of scope that will be completed by outside vendors.
Option D : Using advertisements to expand the pool of interested vendor
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Using advertisements to expand the pool of interested vendor
PMP Exam Question No 7
During a project to plan an event for an association of realtors, the team spends time documenting how they will estimate and control costs. What is a tool or technique that may be needed to perform this process?
Option A : Analogous Estimating
Option B : Cost Aggregation
Option C : Expert Judgment
Option D : Alternatives Analysis
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Expert Judgment
PMP Exam Sample Question No 8
As you work with your sponsor, you communicate how the structure of your organization influences the delivery of your project. Which of the following statements, if said, would not be true concerning organizational structures?
Option A : In a weak matrix, project managers have more authority than functional managers
Option B : In a strong matrix, the role of project manager it typically full-time
Option C : In a projectized organization, resource availability for projects is high
Option D : In a weak matrix, project management administrative staff are part-time
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
In a weak matrix, project managers have more authority than functional managers
PMP Exam Practice Question No 9
After a project has been baselined, changes to plans need to be carefully controlled. This process is referred to as integrated change control. Which of the following documents typically outlines who is responsible for approving change requests?
Option A : Stakeholder Register
Option B : Project Management Plan
Option C : Project Charter
Option D : Change Log
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Project Management Plan
PMP Certification Exam Question No 10
On a project to demolish an aging office building (prior to the construction of new condominiums), the team spends time analyzing activity sequences and estimates to create the schedule. What is an input to that particular process?
Option A : Agreements
Option B : Schedule Data
Option C : Project Calendars
Option D : Change Requests
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Agreements