PMP Exam Example Questions Paper 49

Hi PMP aspirants, welcome to AKVTutorials. Looking for PMP practice questions that focus on the role of the project manager in promoting diversity, equity, and inclusion within project teams? Foster diversity, equity, and inclusion within project teams using our practice questions, reflecting the evolving role of the project manager in promoting a positive work environment. In this article, you will get PMP Exam Example Questions Paper 49. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A project manager is working with a team to train employees at a technology company in Lean Six Sigma. At this point, she needs to determine what levels of cost variance are acceptable before action needs to be taken. Which document should be reviewed to find this information?

Option A : Work Performance Report 

Option B : Risk Management Plan 

Option C : Cost Management Plan 

Option D : Cost Baseline

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Cost Management Plan 

PMP Mock Test Question No 2

A project to configure new content management software for an online news agency is underway. Currently, the team is performing the plan schedule management process. In doing so, which of the following activities might they complete?

Option A : Evaluating project scope and required resources in order to approximate the number of work periods needed to complete the activities

Option B : Identifying methods that will be used to develop the project timeline. 

Option C : Mapping the flow of activities to most efficiently complete the work given various constraints. 

Option D : Working with team members to identify the steps required to complete project work packages

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Identifying methods that will be used to develop the project timeline. 

PMP Practice Exam Question No 3

Your project team gets together outside of work to socialize and strengthen relationships. As a result, communication and trust improves among team members. In this scenario, which process was used?

Option A : Plan Resource Management 

Option B : Manage Team 

Option C : Manage Communications 

Option D : Develop Team

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Manage Communications 

PMP Mock Exam Question No 4

At this point on your project, you are in the process of managing the team, which includes tracking their performance and providing them feedback. Which of the following are inputs of that process?

Option A : Team Charter, Change Requests, Work Performance Data

Option B : Resource Management Plan, Agreements, Resource Calendars 

Option C : Work Performance Reports, Team Performance Assessments, Environmental Process Assets 

Option D : Team Performance Assessments, Organizational Process Assets, Project Charter

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Work Performance Reports, Team Performance Assessments, Environmental Process Assets 

Project Management Professional Question No 5

On a home renovation project, the team aggregates the costs that had been estimated for demolition, paint, flooring, and appliances. They also add reserve for unknown events that arise. In this scenario, which of the following processes were used?

Option A : Estimate Costs 

Option B : Determine Budget 

Option C : Plan Cost Management 

Option D : Control Costs

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Determine Budget 

PMP Certification Prep Question No 6

At a recent meeting on a project to remodel a hotel that was constructed more than 60 years ago, you inform your stakeholders that you are in the process of conducting procurements. What is an activity that could be performed during that process?

Option A : Confirming that payments are made to sellers as outlined in the terms of the contract. 

Option B : Preparing a request for information to get feedback from potential vendors.

Option C : Defining the portion of scope that will be completed by outside vendors. 

Option D : Using advertisements to expand the pool of interested vendor

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Using advertisements to expand the pool of interested vendor

PMP Exam Question No 7

During a project to plan an event for an association of realtors, the team spends time documenting how they will estimate and control costs. What is a tool or technique that may be needed to perform this process?

Option A : Analogous Estimating 

Option B : Cost Aggregation

Option C : Expert Judgment 

Option D : Alternatives Analysis

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Expert Judgment 

PMP Exam Sample Question No 8

As you work with your sponsor, you communicate how the structure of your organization influences the delivery of your project. Which of the following statements, if said, would not be true concerning organizational structures?

Option A : In a weak matrix, project managers have more authority than functional managers 

Option B : In a strong matrix, the role of project manager it typically full-time

Option C : In a projectized organization, resource availability for projects is high 

Option D : In a weak matrix, project management administrative staff are part-time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

In a weak matrix, project managers have more authority than functional managers 

PMP Exam Practice Question No 9

After a project has been baselined, changes to plans need to be carefully controlled. This process is referred to as integrated change control. Which of the following documents typically outlines who is responsible for approving change requests?

Option A : Stakeholder Register 

Option B : Project Management Plan

Option C : Project Charter 

Option D : Change Log

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Project Management Plan

PMP Certification Exam Question No 10

On a project to demolish an aging office building (prior to the construction of new condominiums), the team spends time analyzing activity sequences and estimates to create the schedule. What is an input to that particular process?

Option A : Agreements 

Option B : Schedule Data 

Option C : Project Calendars 

Option D : Change Requests

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

 Agreements 

Free PMP Exam Practice Test Questions And Solutions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply