PMP Exam Agile Questions Test 71 Paper

Hi PMP aspirants, welcome to AKVTutorials. Are you actively seeking PMP practice questions to simulate the exam environment and enhance your time management skills? Master procurement management and contract types with our PMP practice questions, essential components of Project Management Professional success. In this article, you will get PMP Exam Agile Questions Test 71 Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

The cost baseline is an output of what process? 

Option A : Cost planning 

Option B : Cost estimating 

Option C : Cost budgeting 

Option D : Cost control

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Cost budgeting

PMP Mock Test Question No 2

The time phased budget that is used to measure and monitor cost performance is:

Option A : The project budget 

Option B : The cost budget 

Option C : The cost baseline 

Option D : The cost estimate 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The cost baseline 

PMP Practice Exam Question No 3

 Which knowledge area does not provide input into cost budgeting? 

Option A : Time 

Option B : Quality 

Option C : Scope 

Option D : Cost 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Quality 

PMP Mock Exam Question No 4

At the beginning of a project you are asked for an order of magnitude budget. What type of budget estimate are you likely to use? 

Option A : Analogous 

Option B : Parametric modeling 

Option C : Bottom-up 

Option D : Detailed

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Analogous 

Project Management Professional Question No 5

The major process groups of project management are:

Option A : Planning, control, initiation, closing, execution 

Option B : Monitoring, start up, execution, close out, planning 

Option C : Conceptual, demonstration, validation, development, production 

Option D : Feasibility, planning, design, production, close out

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Planning, control, initiation, closing, execution 

PMP Certification Prep Question No 6

Project Stakeholder are: 

Option A : Anybody who is actively working on the project 

Option B : Individuals and organizations who are actively involved in the project, or whose interests may be positively or negatively affected as a result of project execution or successful project completion. 

Option C : The plan sponsor, project manager, team members, client 

Option D : The customer 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Individuals and organizations who are actively involved in the project, or whose interests may be positively or negatively affected as a result of project execution or successful project completion. 

PMP Exam Question No 7

The Project Life Cycle:

Option A : Defines the Product Life Cycle 

Option B : Has distinct phases that are the same for all projects 

Option C : Defines what work should be done in each phase 

Option D : Has gates that must be completed before moving onto the next phase of the project

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Defines what work should be done in each phase 

PMP Exam Sample Question No 8

In planning your resources for a new building project you are working with an engineering firm, a construction management firm and a general contractor. You are mindful that the general contractor will have to manage several sub-contractors over the next 9 months and that the structural and civil engineers will need to communicate frequently. You must select the best reporting relationships among the parties. This is an example of: 

Option A : Staffing requirements 

Option B : Communication planning 

Option C : Project interface planning 

Option D : Staffing management plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project interface planning 

PMP Exam Practice Question No 9

As a Project Manager you have just completed a 9-month project where you had accountability for the schedule, budget, team members and quality of the end product. You are up for your annual review and expect a bonus based on your performance. What is not an area that you would expect to be rewarded for?

Option A : Meeting 95% of your milestones on time 

Option B : Finding a way to use Jr. Level Engineers to complete tasks that Sr. Level Engineers were scheduled for 

Option C : Inspiring the team to work overtime due to an oversight in the scope plan 

Option D : Developing project management skills in a Jr. Project Manager who was assigned to the project 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Inspiring the team to work overtime due to an oversight in the scope plan 

PMP Certification Exam Question No 10

You have inherited a project that is in trouble. The team members are spread out in 5 states, the schedule is behind by 20%, the former project manager alienated the team and there is no communication plan. The first issue you must work on is building a cohesive team to get the project back on track. Which of the following is not a technique that you would use in team development: 

Option A : Flying everyone in for a team meeting 

Option B : Provide training for those areas that are suffering the most 

Option C : Establish a reward system that will pay out based on getting the critical path back within the established time frame 

Option D : Use performance reports to get feedback on individual performance

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Use performance reports to get feedback on individual performance

PMP Exam Practice Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply