Hi PMP aspirants, welcome to AKVTutorials. Ready to test your understanding of PMP concepts with practice questions that challenge your knowledge of scope management? Chart your course to PMP proficiency with our Practice Questions—a vital resource for Project Management Professional excellence. In this article, you will get PMP Course Exam Questions Test Paper 131. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
Core planning processes:
Option A : Include scope planning, cost planning, schedule planning and performance reporting
Option B : Provide a framework for the project
Option C : Are used to track the progress of a project
Option D : Have clear dependencies so they must be executed in essentially the same order on most Projects
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Have clear dependencies so they must be executed in essentially the same order on most Projects
PMP Exam Preparation Test Question No 2
In a weak matrix organization, functional managers are usually responsible for:
Option A : Monitoring personnel performance
Option B : Approval for changes to the project schedule
Option C : Monitoring their project team members deliverables
Option D : Changes that impact their team members participation
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Monitoring personnel performance
PMP Exam Sample Exam Question No 3
As a Project Manager on replacing 2 miles of sewer pipe part of your job is to determine if there are changes to the scope of the project, the schedule, the budget and the technical requirements. These responsibilities are part of which process:
Option A : Executing
Option B : Controlling
Option C : Planning
Option D : Closing
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Controlling
PMP Certification Exam Question No 4
You are one of four full-time project managers in an organization. You all share an administrative person. There are generally 8-10 projects per year that involve about 25% of the organizations employees, however, these employees do not report to you. Your organization can best be classified as:
Option A : Functional
Option B : Strong matrix
Option C : Projectized
Option D : Balanced matrix
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Balanced matrix
Free PMP Practice Exam Question No 5
During the course of a project you have motivated team members, managed conflict, performed personnel administrative functions and negotiated for more resources. These are examples of:
Option A : General Management
Option B : Project Human Resource Management
Option C : Project Execution
Option D : A Projectized organization
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
General Management
Best PMP Exam Practice Question No 6
You have been promoted to Manager, Continuous Process Improvement. Your new position:
Option A : Is a project because the work will be performed by people
Option B : Is not a project because Continuous Process Improvement will continue indefinitely
Option C : Is a project because it is constrained by limited resources
Option D : Is a project because improvements must be planned, executed, and controlled
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Is not a project because Continuous Process Improvement will continue indefinitely
Free PMP Exam Prep Question No 7
Which of the following is not a Project Management knowledge area?
Option A : Project Quality Management
Option B : Project Procurement Management
Option C : Project Configuration Management
Option D : Project Risk Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project Configuration Management
Latest PMP Exam Question No 8
In a matrix organization, which of the following is not a responsibility of the project manager?
Option A : Complete task definitions
Option B : Resource requirement definitions
Option C : Major timetable milestones
Option D : Personnel performance measurements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Personnel performance measurements
PMI PMP Exam Practice Question No 9
Of the following, which usually exhibits the slowest rate of change?
Option A : People
Option B : Technology
Option C : Organizations
Option D : The Environment
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
People
PMP Certification Exam Agile Question No 10
The state of being totally answerable for the satisfactory completion of a specific assignment is called:
Option A : Authority
Option B : Accountability
Option C : Responsibility
Option D : Fiduciary
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Accountability