PMP Course Exam Questions Test Paper 131

Hi PMP aspirants, welcome to AKVTutorials. Ready to test your understanding of PMP concepts with practice questions that challenge your knowledge of scope management? Chart your course to PMP proficiency with our Practice Questions—a vital resource for Project Management Professional excellence. In this article, you will get PMP Course Exam Questions Test Paper 131. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

 Core planning processes: 

Option A : Include scope planning, cost planning, schedule planning and performance reporting 

Option B : Provide a framework for the project 

Option C : Are used to track the progress of a project 

Option D : Have clear dependencies so they must be executed in essentially the same order on most Projects 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Have clear dependencies so they must be executed in essentially the same order on most Projects

PMP Exam Preparation Test Question No 2

In a weak matrix organization, functional managers are usually responsible for: 

Option A : Monitoring personnel performance 

Option B : Approval for changes to the project schedule 

Option C : Monitoring their project team members deliverables 

Option D : Changes that impact their team members participation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Monitoring personnel performance 

PMP Exam Sample Exam Question No 3

As a Project Manager on replacing 2 miles of sewer pipe part of your job is to determine if there are changes to the scope of the project, the schedule, the budget and the technical requirements. These responsibilities are part of which process: 

Option A : Executing 

Option B : Controlling 

Option C : Planning 

Option D : Closing 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Controlling 

PMP Certification Exam Question No 4

You are one of four full-time project managers in an organization. You all share an administrative person. There are generally 8-10 projects per year that involve about 25% of the organizations employees, however, these employees do not report to you. Your organization can best be classified as: 

Option A : Functional 

Option B : Strong matrix 

Option C : Projectized 

Option D : Balanced matrix 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

 Balanced matrix 

Free PMP Practice Exam Question No 5

During the course of a project you have motivated team members, managed conflict, performed personnel administrative functions and negotiated for more resources.  These are examples of: 

Option A : General Management 

Option B : Project Human Resource Management 

Option C : Project Execution 

Option D : A Projectized organization 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

General Management 

Best PMP Exam Practice Question No 6

You have been promoted to Manager, Continuous Process Improvement. Your new position: 

Option A : Is a project because the work will be performed by people 

Option B : Is not a project because Continuous Process Improvement will continue indefinitely 

Option C : Is a project because it is constrained by limited resources 

Option D : Is a project because improvements must be planned, executed, and controlled

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Is not a project because Continuous Process Improvement will continue indefinitely 

Free PMP Exam Prep Question No 7

 Which of the following is not a Project Management knowledge area? 

Option A : Project Quality Management 

Option B : Project Procurement Management 

Option C : Project Configuration Management 

Option D : Project Risk Management 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project Configuration Management 

Latest PMP Exam Question No 8

In a matrix organization, which of the following is not a responsibility of the project manager? 

Option A : Complete task definitions 

Option B : Resource requirement definitions 

Option C : Major timetable milestones

Option D : Personnel performance measurements 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Personnel performance measurements 

PMI PMP Exam Practice Question No 9

Of the following, which usually exhibits the slowest rate of change? 

Option A : People

Option B : Technology 

Option C : Organizations 

Option D : The Environment 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

People

PMP Certification Exam Agile Question No 10

The state of being totally answerable for the satisfactory completion of a specific assignment is called: 

Option A : Authority 

Option B : Accountability 

Option C : Responsibility 

Option D : Fiduciary 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Accountability 

PMP Exam Practice Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply