Hi PMP aspirants, welcome to AKVTutorials. Looking for PMP practice questions that focus on the role of the project manager in promoting diversity, equity, and inclusion within project teams? Stay abreast of the latest trends and emerging practices in project management with our PMP Project Management Professional practice questions, ensuring your preparation is comprehensive and up-to-date. In this article, you will get PMP Certification Practice Exam Questions Test 99 Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
You are reviewing a risk of lists identified by the team and now need to “categorize ”the risk s which will facilitate the risk monitoring process. Which of the following risk events would present the highest risk to the “schedule category” of risks.
Option A : Substantial increase in the cost of purchased materials.
Option B : Delays in obtaining required approvals.
Option C : Contract disputes that generate back charges.
Option D : Deffral of the scheduled post implementation review meeting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Delays in obtaining required approvals.
PMP Mock Test Question No 2
The “Tuckman Model “ refers to the 4 stage of the team development .What is the correct sequence of stages each team will go through?
Option A : Forming, Norming, Storming and performing.
Option B : Forming , Storming, Norming and performing.
Option C : Norming, Forming , Storming and performing.
Option D : Storming, Forming, Norming and performing.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Forming , Storming, Norming and performing
PMP Practice Exam Question No 3
An input to staff Acquisition does not include:
Option A : Staffing management plan.
Option B : Staffing requirement
Option C : Staffing pool description.
Option D : Requirement practices.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Staffing requirement
PMP Mock Exam Question No 4
Pareto diagrams cause and effect diagrams flow charts and trend analysis are used in quality:
Option A : Control.
Option B : Assurance.
Option C : Planning.
Option D : Verification.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Control.
Project Management Professional Question No 5
The main purpose of risk management planning is to create a plan for dealing with each high priority risk that you have identified in the various phase. A good risk management plan will not contain ____________.
Option A : a contingency plan to monitor risk and trigger a predetermined response when a potential risk is detected.
Option B : The resources that are needed for your risk management activity.
Option C : What information you need to track and monitor the risk.
Option D : all of the above.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all of the above.
PMP Certification Prep Question No 6
What does the accounting term BCR 1.5 mean?
Option A : The cost are higher than the benefits.
Option B : The profit is 1.5 times the cost.
Option C : The payback is 1.5 times the cost
Option D : The cost is 1.5 times the profit.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The payback is 1.5 times the cost
PMP Exam Question No 7
From the “view exhibit” we can state task _____________ is the furtherest behind
schedule task _________ has the largest budget variance
Option A : 3,2
Option B : 1,2
Option C : 1,3
Option D : 1,4
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
1,2
PMP Exam Sample Question No 8
From the view “exhibit” button ,which task list contains the critical list for the path?
Option A : ABCDEI
Option B : ABGHIF
Option C : ABCDEF
Option D : CDEF
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
ABCDEF
PMP Exam Practice Question No 9
You need to define the high level project objectives .Which of the following technique is the best method to define the project objectives?
Option A : Delphi.
Option B : Earned value.
Option C : Expert interviews.
Option D : Cost benefit analysis.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Delphi.
PMP Certification Exam Question No 10
Outputs of administrative closure include all of the following except.
Option A : Project archives
Option B : formal acceptance
Option C : lessons learned.
Option D : performance reports.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
performance reports.