PMP Certification Practice Exam Questions Test 99 Paper

Hi PMP aspirants, welcome to AKVTutorials. Looking for PMP practice questions that focus on the role of the project manager in promoting diversity, equity, and inclusion within project teams? Stay abreast of the latest trends and emerging practices in project management with our PMP Project Management Professional practice questions, ensuring your preparation is comprehensive and up-to-date. In this article, you will get PMP Certification Practice Exam Questions Test 99 Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

 You are reviewing a risk of lists identified by the team and now need to “categorize ”the risk s which will facilitate the risk monitoring process. Which of the following risk events would present the highest risk to the “schedule category” of risks.

Option A : Substantial increase in the cost of purchased materials.

Option B : Delays in obtaining required approvals.

Option C : Contract disputes that generate back charges.

Option D : Deffral of the scheduled post implementation review meeting

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Delays in obtaining required approvals.

PMP Mock Test Question No 2

 The “Tuckman Model “ refers to the 4 stage of the team development .What is the correct sequence of stages each team will go through?

Option A : Forming, Norming, Storming and performing.

Option B : Forming , Storming, Norming and performing.

Option C : Norming, Forming , Storming and performing.

Option D : Storming, Forming, Norming and performing.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Forming , Storming, Norming and performing

PMP Practice Exam Question No 3

An input to staff Acquisition does not include:

Option A : Staffing management plan.

Option B : Staffing requirement

Option C : Staffing pool description.

Option D : Requirement practices.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Staffing requirement

PMP Mock Exam Question No 4

Pareto diagrams cause and effect diagrams flow charts and trend analysis are used in quality:

Option A : Control.

Option B : Assurance.

Option C : Planning.

Option D : Verification.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Control.

Project Management Professional Question No 5

 The main purpose of risk management planning is to create a plan for dealing with each high priority risk that you have identified in the various phase. A good risk management plan will not contain ____________.

Option A : a contingency plan to monitor risk and trigger a predetermined response when a potential risk is detected.

Option B : The resources that are needed for your risk management activity.

Option C : What information you need to track and monitor the risk.

Option D : all of the above. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

all of the above. 

PMP Certification Prep Question No 6

 What does the accounting term BCR 1.5 mean?

Option A : The cost are higher than the benefits.

Option B : The profit is 1.5 times the cost.

Option C : The payback is 1.5 times the cost

Option D : The cost is 1.5 times the profit.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The payback is 1.5 times the cost

PMP Exam Question No 7

 From the “view exhibit” we can state task _____________ is the furtherest behind
schedule task _________ has the largest budget variance

Option A : 3,2

Option B : 1,2 

Option C : 1,3 

Option D : 1,4 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

1,2

PMP Exam Sample Question No 8

From the view “exhibit” button ,which task list contains the critical list for the path?

Option A : ABCDEI

Option B : ABGHIF

Option C : ABCDEF

Option D : CDEF

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

ABCDEF

PMP Exam Practice Question No 9

You need to define the high level project objectives .Which of the following technique is the best method to define the project objectives?

Option A : Delphi.

Option B : Earned value.

Option C : Expert interviews.

Option D : Cost benefit analysis.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Delphi.

PMP Certification Exam Question No 10

 Outputs of administrative closure include all of the following except.

Option A : Project archives

Option B : formal acceptance

Option C : lessons learned.

Option D : performance reports.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

performance reports.

PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply