Hi PMP aspirants, welcome to AKVTutorials. Need a reliable platform for PMP Project Management Professional practice questions to ensure you are well-prepared for the exam? Test your understanding of scope management with our PMP Project Management Professional practice questions, a vital step in your exam preparation. In this article, you will get PMP Certification Exam Sample Questions Paper 70. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
At what point in the project is there the most risk of project failure?
Option A : Close out
Option B : Development
Option C : Implementation
Option D : Concept
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Implementation
PMP Mock Test Question No 2
Phase exits, kill points and stage gates are used for what purpose?
Option A : Planning the next stage in the project
Option B : Communicating milestones to stakeholders
Option C : Determining if the project should continue into the next phase
Option D : Measuring earned value
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Measuring earned value
PMP Practice Exam Question No 3
A complex project will fit best in what type of organization?
Option A : Functional
Option B : Cross-functional
Option C : Matrix
Option D : Balanced
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Matrix
PMP Mock Exam Question No 4
Which knowledge area involves organizational theory as a tool/technique?
Option A : Communications Management
Option B : Cost Management
Option C : Risk Management
Option D : Human Resource Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Human Resource Management
Project Management Professional Question No 5
Human Resource Management is tightly linked to which other knowledge area?
Option A : Cost Management
Option B : Risk Management
Option C : Communications Management
Option D : Time Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Communications Management
PMP Certification Prep Question No 6
Which of the following is not considered a constraint in Organizational Planning?
Option A : Recruitment practices
Option B : Collective bargaining agreements
Option C : Preferences of the project management team
Option D : Expected staff assignments
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Recruitment practices
PMP Exam Question No 7
Outputs from Organizational Planning include all of the following except:
Option A : Staffing Management Plan
Option B : Organization Chart
Option C : Project Team Directory
Option D : Role and Responsibility Matrix
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project Team Directory
PMP Exam Sample Question No 8
Inputs to Staff Acquisition include all of the following except:
Option A : Staffing Management Plan
Option B : Resource Histogram
Option C : Staffing pool description
Option D : Recruitment practices
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Resource Histogram
PMP Exam Practice Question No 9
Which of the following is not an input to Team Development?
Option A : Project Plan
Option B : Staffing Management Plan
Option C : Performance Reports
Option D : Reward and recognition systems
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Reward and recognition systems
PMP Certification Exam Question No 10
Cost Budgeting is defined as:
Option A : The estimated total cost of the project when done
Option B : Allocating the cost estimates to the individual work items
Option C : Estimating the cost of the resources needed to complete project activities
Option D : The sum of the approved cost estimates
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Allocating the cost estimates to the individual work items