Hi PMP aspirants, welcome to AKVTutorials. In the midst of PMP exam preparation, are you on the hunt for practice questions that cover both predictive and agile methodologies? Immerse yourself in PMP excellence with our practice questions, covering both predictive and agile methodologies to fortify your Project Management Professional preparation. In this article, you will get PMP Certification Exam Questions Test 22 Answer Explanation. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Risk tolerances are determined in order to help:
Option A : the team rank the project risks.
Option B : the project manager estimate the project
Option C : the team schedule the project.
Option D : management know how other managers will act on the project.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: A
the team rank the project risks.
PMP Mock Test Question No 2
A project manager is employed by a construction company and is responsible for the furnishing of the completed building. One of the first things that the project manager for this project should do is to write a:
Option A : Work breakdown structure
Option B : Budget baseline.
Option C : Project charter.
Option D : Project plan.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project Charter
PMP Practice Exam Question No 3
Your company has an emergency and needs contracted work done as soon as possible. Under these circumstances, which of the following would be the helpful to add to the contract?
Option A : A clear contract statement of work
Option B : Requirements as to which subcontractors can be used
Option C : Incentives
Option D : A force majeure clause
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: C
Incentives
PMP Mock Exam Question No 4
The “halo effect” refers to the tendency to:
Option A : promote from within.
Option B : hire the best.
Option C : move people into project management because they are good in their technical fields.
Option D : move people into project management because they have had project management
training.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: C
move people into project management because they are good in their technical fields.
Explanation: Flaw in Expert Judgment when people good in certain areas are deemed as good in all areas.
Project Management Professional Question No 5
A project manager is trying to complete a software development project, but cannot get enough attention for the project. Resources are focused on completing process-related work and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in?
Option A : Functional
Option B : Matrix
Option C : Expediter
Option D : Coordinator
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: A
Functional
PMP Certification Prep Question No 6
All of the following are characteristics of a project EXCEPT:
Option A : Temporary
Option B : Definite beginning and end
Option C : Interrelated activities
Option D : Repeats itself every month
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: D
Repeats itself every month
PMP Exam Question No 7
A team is using a fishbone diagram to help determine what quality standards will be used on the project. What part of the quality management process are they in?
Option A : Perform quality control
Option B : Perform quality assurance
Option C : Plan Quality Management
Option D : Variable analysis
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: C
Plan Quality Management
PMP Exam Sample Question No 8
The equivalent of cost reimbursable contracts is frequently termed:
Option A : Back charge contracts.
Option B : Fixed price contracts.
Option C : Progress payment contracts.
Option D : Cost plus contracts.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: D
Cost plus contracts.
PMP Exam Practice Question No 9
A buyer extends a formal invitation containing a scope of work. The invitation seeks a response describing the methodology and results that will be provided to the buyer. This is called:
Option A : Invitation to bid.
Option B : Request for information.
Option C : Request for proposal.
Option D : Request for bid.
Show/Hide Answer
Answer Keys: YES
Explanation: NO
Correct Answer: C
Request for proposal.
PMP Certification Exam Question No 10
A project manager must have some work done by an outside contractor. This work has a great deal of risk associated with it, and it has become very difficult to find a contractor willing to take on the job. Which of the following types of contract would offer the greatest incentive to the contractor?
Option A : Cost plus percentage of cost as an award fee
Option B : Cost plus fixed fee
Option C : Cost plus incentive fee
Option D : Firm fixed price
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Cost plus percentage of cost as an award fee