PMP Certification Exam Questions Test 22 Answer Explanation

Hi PMP aspirants, welcome to AKVTutorials. In the midst of PMP exam preparation, are you on the hunt for practice questions that cover both predictive and agile methodologies? Immerse yourself in PMP excellence with our practice questions, covering both predictive and agile methodologies to fortify your Project Management Professional preparation. In this article, you will get PMP Certification Exam Questions Test 22 Answer Explanation. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Risk tolerances are determined in order to help:

Option A : the team rank the project risks.

Option B : the project manager estimate the project

Option C : the team schedule the project.

Option D : management know how other managers will act on the project.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: A

the team rank the project risks.

PMP Mock Test Question No 2

A project manager is employed by a construction company and is responsible for the furnishing of the completed building. One of the first things that the project manager for this project should do is to write a:

Option A : Work breakdown structure

Option B : Budget baseline.

Option C : Project charter.

Option D : Project plan.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project Charter

PMP Practice Exam Question No 3

Your company has an emergency and needs contracted work done as soon as possible. Under these circumstances, which of the following would be the helpful to add to the contract?

Option A : A clear contract statement of work

Option B : Requirements as to which subcontractors can be used

Option C : Incentives

Option D : A force majeure clause

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: C

Incentives

PMP Mock Exam Question No 4

The “halo effect” refers to the tendency to:

Option A : promote from within.

Option B : hire the best.

Option C : move people into project management because they are good in their technical fields.

Option D : move people into project management because they have had project management
training.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: C

move people into project management because they are good in their technical fields.

Explanation: Flaw in Expert Judgment when people good in certain areas are deemed as good in all areas.

Project Management Professional Question No 5

A project manager is trying to complete a software development project, but cannot get enough attention for the project. Resources are focused on completing process-related work and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in?

Option A : Functional

Option B : Matrix

Option C : Expediter

Option D : Coordinator

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: A

Functional

PMP Certification Prep Question No 6

All of the following are characteristics of a project EXCEPT:

Option A : Temporary

Option B : Definite beginning and end

Option C : Interrelated activities

Option D : Repeats itself every month

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: D

Repeats itself every month

PMP Exam Question No 7

A team is using a fishbone diagram to help determine what quality standards will be used on the project. What part of the quality management process are they in?

Option A : Perform quality control

Option B : Perform quality assurance

Option C : Plan Quality Management

Option D : Variable analysis

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: C

Plan Quality Management

PMP Exam Sample Question No 8

The equivalent of cost reimbursable contracts is frequently termed:

Option A : Back charge contracts.

Option B : Fixed price contracts.

Option C : Progress payment contracts.

Option D : Cost plus contracts.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: D

Cost plus contracts.

PMP Exam Practice Question No 9

A buyer extends a formal invitation containing a scope of work. The invitation seeks a response describing the methodology and results that will be provided to the buyer. This is called:

Option A : Invitation to bid.

Option B : Request for information.

Option C : Request for proposal.

Option D : Request for bid.

Show/Hide Answer

Answer Keys: YES

Explanation: NO

Correct Answer: C

Request for proposal.

PMP Certification Exam Question No 10

A project manager must have some work done by an outside contractor. This work has a great deal of risk associated with it, and it has become very difficult to find a contractor willing to take on the job. Which of the following types of contract would offer the greatest incentive to the contractor?

Option A : Cost plus percentage of cost as an award fee

Option B : Cost plus fixed fee

Option C : Cost plus incentive fee

Option D : Firm fixed price

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Cost plus percentage of cost as an award fee

PPMP Practice Test Exam Questions

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply