PMP Certification Exam Questions Paper 69 Answers

Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and looking for a resource that provides insightful practice questions for effective study sessions? Unearth the secrets to PMP success through our Practice Questions—an essential companion for every Project Management Professional aspirant. In this article, you will get PMP Certification Exam Questions Paper 69 Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

You are the program manager for a new commercial jet. A new robotic technology has just emerged that will improve the accuracy of machining connectors to within 3 microns. This technology will also result in a savings from the previous method. As a result of this, all program managers are being asked to come up with a new estimate at completion for their in-process projects. The most accurate method to develop the new estimate is to: 

Option A : Complete and earned value analysis to determine the cost index 

Option B : Take the actuals to date and add the remaining budget modified by a performance factor 

Option C : Take the actuals to date and develop a new estimate for all remaining work

Option D : Add the remaining budget to what has already been spent 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Take the actuals to date and develop a new estimate for all remaining work

PMP Mock Test Question No 2

 Which of the following is not an input to cost budgeting? 

Option A : Cost estimates 

Option B : Work breakdown schedule 

Option C : Project schedule 

Option D : Risk management plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Risk management plan

PMP Practice Exam Question No 3

A project team member decides that engaging the customer on some alternative designs is unnecessary if all functionalities are delivered. The Which of the following is not an input to the cost control process?

Option A :Performance measurement

Option B : Cost baseline 

Option C : Performance reports 

Option D : Change requests 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Performance measurement

PMP Mock Exam Question No 4

Which of the following is not a tool or technique for cost control? 

Option A : Cost change control system 

Option B : Revised cost estimates 

Option C : Performance measurement 

Option D : Additional planning

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Revised cost estimates 

Project Management Professional Question No 5

Which of the following is not an output of the cost control process? 

Option A : Revised cost estimates 

Option B : Budget updates 

Option C : Workarounds 

Option D : Estimate at completion

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Workarounds 

PMP Certification Prep Question No 6

As project manager, which of the following activities most deserves your immediate attention? 

Option A : ACWP = $3,000 and BCWP = $2,900 

Option B : BCWS = $3,000 and BCWP = $2,900 

Option C : ACWP = $3,000 and BCWP = $3,200 

Option D : BCWP = $3,000 and ACWP = $2,400

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

BCWP = $3,000 and ACWP = $2,400

PMP Exam Question No 7

Your project will require use of a high pressure punch press for four months. You can rent the press for $10,000 payable at the end of each month. You may also choose to make a lump sum payment on the day the press is delivered. Using a discount rate of 1% per month, the maximum lump sum payment you should choose to make is:

Option A : $38,000 

Option B : $38,500

Option C : $39,000 

Option D : $39,250 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

$39,000 

PMP Exam Sample Question No 8

A work package, scheduled for one year from today, will cost $114,000 at that time. It can be done now at a reduced cost. Using a 12% discount rate, the maximum cost you should authorize for doing the work now is: 

Option A : 100,320 

Option B : 101,750 

Option C : 102,500 

Option D : 103,000 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

100,320 

PMP Exam Practice Question No 9

At what stage in the project life cycle would costs be the lowest? 

Option A : Concept 

Option B : Development 

Option C : Implementation 

Option D : Close out

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Concept

PMP Certification Exam Question No 10

At what point in the project would stakeholders have the most ability to influence the final outputs of the project product? 

Option A : Implementation 

Option B : Development 

Option C : Concept 

Option D : Close out

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Concept 

PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply