Hi PMP aspirants, welcome to AKVTutorials. Seeking PMP practice questions that cover the intricacies of project governance and compliance with organizational policies and procedures? Uphold project governance and compliance standards with our PMP Project Management Professional practice questions, ensuring alignment with organizational policies. In this article, you will get PMP Certification Exam Questions Paper 43. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Which of the following is usually recognized as a form of power for a project manager?
Option A : Legal power
Option B : Budgetary power
Option C : Reward-oriented power
Option D : Culture-oriented power
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Reward-oriented power
PMP Mock Test Question No 2
A project manager hears about an issue and decides to ask the project team about more details as to how and when this happened. Is this more of a team management or more of a team leadership approach in this moment?
Option A : More of a team management approach
Option B : More of a team leadership approach
Option C : Both
Option D : Neither
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
More of a team management approach
PMP Practice Exam Question No 3
A Scrum Master talks to you about the impact and value of servant leadership. What is the person probably referring to?
Option A : The idea that an organization can be leaderless and still fully functioning.
Option B : The belief that wishes and requirements of a leader have no importance.
Option C : The commitment to serve the team as a leader, and to put them first.
Option D : The idea of management by objectives when telling a team what to do.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The commitment to serve the team as a leader, and to put them first.
PMP Mock Exam Question No 4
What is a purpose of agile release planning?
Option A : Develop an early understanding what the final product, service or result will in exactly look like in the end.
Option B : Create a precise project schedule with long-term forecasts and accurate estimations
Option C : Providing a high-level summary timeline of the release schedule in less predictive projects
Option D : Outline the requirements in detail and make sure they are described as use cases
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Providing a high-level summary timeline of the release schedule in less predictive projects
Project Management Professional Question No 5
What is a product backlog?
Option A :A description of what is to be delivered in a product
Option B : A to-do list of tasks to be finished
Option C : A breakdown of scope for an iteration
Option D : A time-phased list of technical requirements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
A description of what is to be delivered in a product
PMP Certification Prep Question No 6
What does an iteration burndown chart track?
Option A : Work remaining to be completed for the product
Option B : Work remaining to be completed in the iteration backlog
Option C : Work finished so far in the iteration
Option D : Work ideally completed on average in every iteration
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Work remaining to be completed in the iteration backlog
PMP Exam Question No 7
Which is not one of the five levels of increasingly effective quality management?
Option A : Detect and correct defects before the customer finds them
Option B : Use quality assurance to examine and correct the process itself
Option C : Create a culture committed to quality throughout the organization
Option D : Write test cases before writing software code
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Write test cases before writing software code
PMP Exam Sample Question No 8
Which is an advantage of self-organizing teams?
Option A : Freedom of the project manager to make decisions
Option B : Faster decision-making processes by the project manager
Option C : Increased sense of responsibility of team members
Option D : Higher visibility of individual team members
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Increased sense of responsibility of team members
PMP Exam Practice Question No 9
Which is a category framework that is suitable for prompt lists?
Option A : S.C.O.P.E.
Option B : V.U.C.A.
Option C : F.R.E.S.H.
Option D : S.O.F.T.E.N.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
V.U.C.A.
PMP Certification Exam Question No 10
How are a procurement lifecycle and contracts related?
Option A : A project procurement lifecycles for a project can include several contracts.
Option B : A contract lifecycle is always longer than a procurement lifecycle.
Option C : A project contract lifecycle should always equal a procurement lifecycle.
Option D : Project lifecycle, contract lifecycle, and procurement lifecycle are unrelated.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
A project procurement lifecycles for a project can include several contracts.