Hi PMP aspirants, welcome to AKVTutorials. Ready to challenge your knowledge and skills with PMP practice questions tailored for Project Management Professional success? Propel your PMP success story forward with our Practice Questions—a roadmap to conquering the Project Management Professional exam. In this article, you will get PMP Certification Exam Example Questions Test Paper 68. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Determining what resources and quantities will be used for the project is part of:
Option A : Cost budgeting
Option B : Cost estimating
Option C : Resource planning
Option D : Cost control
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Resource planning
PMP Mock Test Question No 2
The Scope Statement is used in which process
Option A : Resource Planning
Option B : Cost Estimating
Option C : Cost Control
Option D : Cost Planning
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Resource Planning
PMP Practice Exam Question No 3
Inputs into Resource Planning include:
Option A : Staffing requirements, procurement policies, Work Breakdown Structure
Option B : Work Breakdown Structure, Scope Statement, historical information, resource pool description, organizational policies
Option C : Work Breakdown Structure, Scope definition, resource pool description
Option D : Expert judgement, historical information, Work Breakdown Structure, Scope Statement
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Work Breakdown Structure, Scope Statement, historical information, resource pool description, organizational policies
PMP Mock Exam Question No 4
The term resource planning refers to:
Option A : Labor
Option B : Capital equipment
Option C : Materials
Option D : All of the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
All of the above
Project Management Professional Question No 5
Cost estimating includes all of the following except:
Option A : Identifying and considering various costing alternatives
Option B : Pricing strategy
Option C : Developing an assessment of the likely quantitative result
Option D : Baselining
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Baselining
PMP Certification Prep Question No 6
Cost Estimating is most closely linked with which other process?
Option A : Procurement, Risk
Option B : Scope, Procurement
Option C : Time, Scope
Option D : Risk, Time, Integration
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Time, Scope
PMP Exam Question No 7
Parametric Modeling and Analogous Estimating are used in what process:
Option A : Cost Control Tools and Techniques
Option B : Cost Estimating Tools and Techniques
Option C : Risk Analysis Tools and Techniques
Option D : Risk Analysis Outputs
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Cost Estimating Tools and Techniques
PMP Exam Sample Question No 8
You are building the budget for your project. You don’t have detailed requirements for the project yet. However, a fellow project manager completed a similar project year ago, and has his budget assumptions and final costs documented. You decide to use this information as the basis of your cost estimating. This is called:
Option A : Analogous estimating
Option B : Parametric modeling
Option C : Bottom-up estimating
Option D : Spreadsheeting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Analogous estimating
PMP Exam Practice Question No 9
As the Project Cost Engineer on a high rise development you are preparing your budget. You have developed a template, based on similar projects that can be used for buildings with 3-25 stories. It breaks out cost per square foot for plumbing, wiring, HVAC, dry wall, floors etc. This type of cost estimating is called:
Option A : Analogous estimating
Option B : Parametric modeling
Option C : Bottom up estimating
Option D : Spreadsheeting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Parametric modeling
PMP Certification Exam Question No 10
Before you begin the cost budgeting process for building a new school you should make sure your cost engineer has given you:
Option A : Cost estimates, chart of accounts, cost baseline
Option B : Supporting detail, estimate at completion
Option C : Cost estimates and supporting detail,
Option D : Cost management plan, cost change control plan, cost baseline
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Cost estimates and supporting detail,