Hi PMP aspirants, welcome to AKVTutorials. In need of PMP Project Management Professional practice questions that explore the role of the project manager in conflict resolution and stakeholder collaboration? Uphold ethical standards with our PMP practice questions, aligning with the Project Management Professional Code of Ethics and Professional Conduct. In this article, you will get PMI PMP Exam Questions Free Test Paper 97. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Of different forms of Contracts, which one is unilateral (signed by one party)
Option A : Cost Reimbursable
Option B : Time and Material
Option C : Fixed Price
Option D : Purchase Order
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Purchase Order
PMP Mock Test Question No 2
Given are the statistics for a Project. Target Cost = $220,000; Target Fee = $35,000; Target Price = $255, 000; Sharing Ratio = 80/20; Actual Cost = $200,000. Calculate the Fee and Final Price for the project
Option A : Fee = $35,000, Final Price = $235,000
Option B : Fee = $39,000, Final Price = $239,000
Option C : Fee = $39,000, Final Price = $255,000
Option D : Fee = $55,000, Final Price = $255,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Fee = $55,000, Final Price = $255,000
PMP Practice Exam Question No 3
Given are the statistics for a Project. Target Cost = $150,000; Target Fee = $30,000; Target Price = $180,000; Sharing Ratio = 60/40; Ceiling Price = $200,000; Actual Cost = $210,000. Calculate the Fee and the Final Price for the project
Option A : Fee = $30,000, Final Price = $210,000
Option B : Fee = $30,000, Final Price = $200, 000
Option C : Fee = $6,000, Final Price = $200, 000
Option D : Fee = $6,000, Final Price = $240,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Fee = $6,000, Final Price = $240,000
PMP Mock Exam Question No 4
Which of the following must be present to have a contract
Option A : A detailed scope of work
Option B : Acceptance
Option C : The address of the seller
Option D : Various legal words
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
A detailed scope of work
Project Management Professional Question No 5
Which of the following best describes the project manager’s role during the contracting process
Option A : They are not involved
Option B : They should try to be involved
Option C : They supply an understanding of the risks of the project
Option D : They tell the contracts manager how they want the contracting process to be handle
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
They should try to be involved
PMP Certification Prep Question No 6
A key role of the project manager during negotiations is to
Option A : Protect the relationship between buyer and seller
Option B : Make sure their side wins
Option C : Make sure they get all risks assigned to the other side
Option D : Make sure that everyone receives a communication plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Make sure that everyone receives a communication plan
PMP Exam Question No 7
In a fixed price contract, the fee or profit is
Option A : Unknown
Option B : Part of the negotiation involved in paying every invoice
Option C : Applied as a line item to every invoice
Option D : Determined with the other party at the end of the project
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Determined with the other party at the end of the project
PMP Exam Sample Question No 8
Which of the following is an advantage of centralized contracting
Option A : Easier access to contracting expertise
Option B : Increased company expertise in contracting
Option C : More loyalty to the project
Option D : No home for the contracts personnel
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Easier access to contracting expertise
PMP Exam Practice Question No 9
During communication the use of __________ is a means of giving feedback to the speaker by rephrasing the speaker’s word to ensure that there is a good understanding of the message being sent.
Option A : active listening.
Option B : filtering .
Option C : graphics.
Option D : visual ,audio ,and tactile.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
active listening.
PMP Certification Exam Question No 10
In communication , the receiver filter messages based on all but which of the following?
Option A : Culture.
Option B : Semantics.
Option C : Language.
Option D : Distance.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Distance.