Hi PMP aspirants, welcome to AKVTutorials. Are you in search of PMP practice mock tests that mimic the complexity and diversity of the Project Management Professional exam? Embark on a journey to PMP excellence with our meticulously crafted Practice Questions—a vital asset for success. In this article, you will get PPMI PMP Exam Practice Test 66 Questions Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Which of the following is not a technology factor that may affect the project communications plan:
Option A : Immediacy of the need for the information
Option B : Length of the project
Option C : Expected project staffing
Option D : Logistics of how many individuals will be involved with the project and at what locations
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Logistics of how many individuals will be involved with the project and at what locations
PMP Mock Test Question No 2
Where is the bulk of the project budget spent?
Option A : Scope management
Option B : Production
Option C : Labor and materials
Option D : Project plan execution
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project plan execution
PMP Practice Exam Question No 3
Which of the following is not a type of performance reporting:
Option A : Status reporting
Option B : Progress reporting
Option C : Forecasting
Option D : Benchmark reporting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Benchmark reporting
PMP Mock Exam Question No 4
Which tool and technique integrates scope, cost and schedule in measuring project performance?
Option A : Variance analysis
Option B : Earned value
Option C : Trend analysis
Option D : Performance report
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Earned value
Project Management Professional Question No 5
Inputs to Administrative Closure include all of the following except:
Option A : Performance measurement documentation
Option B : Other project records
Option C : Documentation of the product
Option D : Project archives
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project archives
PMP Certification Prep Question No 6
Which equation correctly illustrates the cost variance of a project, in currency?
Option A : BCWP-ACWP
Option B : BCWP/ACWP
Option C : BCWP-BCWS
Option D :BCWP/BCWS
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
BCWP-ACWP
PMP Exam Question No 7
You are approximately 30% through your project and the sponsor wants a forecast of the final budget based on what has already been spent. You create an S curve chart display of what kind of performance report:
Option A : Earned value
Option B : Trend analysis
Option C : Variance analysis
Option D : Cost distribution curve
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Trend analysis
PMP Exam Sample Question No 8
At 40% through your project you have a BCWS of $68,000 and a BCWP of $62,000. Your project is:
Option A : Ahead of schedule
Option B : Behind schedule
Option C : A positive cost variance
Option D : A negative cost variance
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Behind schedule
PMP Exam Practice Question No 9
In preparing for a team meeting you want to let the team know how they are doing on the project schedule over all. You calculate the task achievements as follows: planning has a BCWS of $20,000 and a BCWP of $25,000, testing has a BCWS of $17,000 and BCWP of $15,000, and design has a BCWS of $34,000 and a BCWP of $42,000. As a whole your project is:
Option A : 15% ahead of schedule
Option B : 15% behind schedule
Option C : 15% ahead of schedule, but over budget
Option D : 15% behind schedule and budget
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
15% ahead of schedule
PMP Certification Exam Question No 10
In order to let the project sponsor know the percentage of cost variance of your project, you calculate:
Option A : BCWP-BCWS
Option B : BCWP/BCWS
Option C : BCWP/ACWP
Option D : BCWP-ACWPS
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
BCWP/ACWP