Hi PMP aspirants, welcome to AKVTutorials. Are you in search of PMP practice mock tests that mimic the complexity and diversity of the Project Management Professional exam? Embark on a journey to PMP excellence with our meticulously crafted Practice Questions—a vital asset for success. In this article, you will get PPMI PMP Exam Practice Test 66 Questions Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Which of the following is not a technology factor that may affect the project communications plan: 

Option A : Immediacy of the need for the information 

Option B : Length of the project

Option C : Expected project staffing 

Option D : Logistics of how many individuals will be involved with the project and at what locations

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Logistics of how many individuals will be involved with the project and at what locations

PMP Mock Test Question No 2

Where is the bulk of the project budget spent? 

Option A : Scope management 

Option B : Production 

Option C : Labor and materials 

Option D : Project plan execution

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project plan execution

PMP Practice Exam Question No 3

Which of the following is not a type of performance reporting: 

Option A : Status reporting 

Option B : Progress reporting 

Option C : Forecasting

Option D : Benchmark reporting

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Benchmark reporting

PMP Mock Exam Question No 4

 Which tool and technique integrates scope, cost and schedule in measuring project performance?

Option A : Variance analysis 

Option B : Earned value 

Option C : Trend analysis 

Option D : Performance report

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Earned value 

Project Management Professional Question No 5

Inputs to Administrative Closure include all of the following except:

Option A : Performance measurement documentation

Option B : Other project records 

Option C : Documentation of the product 

Option D : Project archives

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project archives

PMP Certification Prep Question No 6

Which equation correctly illustrates the cost variance of a project, in currency? 

Option A : BCWP-ACWP 

Option B : BCWP/ACWP

Option C : BCWP-BCWS 

Option D :BCWP/BCWS 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

BCWP-ACWP

PMP Exam Question No 7

You are approximately 30% through your project and the sponsor wants a forecast of the final budget based on what has already been spent. You create an S curve chart display of what kind of performance report: 

Option A : Earned value 

Option B : Trend analysis 

Option C : Variance analysis 

Option D : Cost distribution curve

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Trend analysis 

PMP Exam Sample Question No 8

 At 40% through your project you have a BCWS of $68,000 and a BCWP of $62,000. Your project is: 

Option A : Ahead of schedule

Option B : Behind schedule 

Option C : A positive cost variance 

Option D : A negative cost variance

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Behind schedule 

PMP Exam Practice Question No 9

In preparing for a team meeting you want to let the team know how they are doing on the project schedule over all. You calculate the task achievements as follows: planning has a BCWS of $20,000 and a BCWP of $25,000, testing has a BCWS of $17,000 and BCWP of $15,000, and design has a BCWS of $34,000 and a BCWP of $42,000. As a whole your project is: 

Option A : 15% ahead of schedule 

Option B : 15% behind schedule 

Option C : 15% ahead of schedule, but over budget 

Option D : 15% behind schedule and budget

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

15% ahead of schedule 

PMP Certification Exam Question No 10

 In order to let the project sponsor know the percentage of cost variance of your project, you calculate: 

Option A : BCWP-BCWS 

Option B : BCWP/BCWS 

Option C : BCWP/ACWP

Option D : BCWP-ACWPS

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

BCWP/ACWP

Practice Test PMP Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply