Hi PMP aspirants, welcome to AKVTutorials. Ready to challenge your knowledge and skills with PMP practice questions tailored for Project Management Professional success? Dive into PMP success with our Practice Questions, meticulously designed to simulate the exam environment and enhance your time management skills. In this article, you will get New PMP Exam Practice Questions Paper 118 Test Paper. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
What are the 4 stages of team development?
Option A : Forming, Storming, Norming, Performing.
Option B : Enthusiasm, Hope, Panic, Solution.
Option C : Assignment, Kickoff, Training, Communicating.
Option D : Direction, Motivation, Cooperation, Collaboration
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Forming, Storming, Norming, Performing.
PMP Exam Preparation Test Question No 2
During a software project Earned Value Analysis is performed and gives the following results: EV: 523,000; PV: 623,000; AC: 643,000. Which results are correct?
Option A : CV: +120,000; SV: +100,000.
Option B : CV: +100,000; SV: +120,000.
Option C : CV: -100,000; SV: -120,000.
Option D : CV: -120,000; SV: -100,000.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
CV: -120,000; SV: -100,000
PMP Exam Sample Exam Question No 3
Which of the following is not normally an element of the Project Charter?
Option A : The formal authorization to apply organizational resources to project activities.
Option B : Work package descriptions.
Option C : The business need that the project was undertaken to address.
Option D : The product description or a reference to this document.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Work package descriptions.
PMP Certification Exam Question No 4
Which process is applied to break down the project into smaller, more manageable elements?
Option A : Scope Planning.
Option B : Activity Duration Estimating.
Option C : Scope Definition.
Option D : Scope Verification.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Scope Definition.
Free PMP Practice Exam Question No 5
Which of the following Tools and Techniques are part of Risk Management Planning?
Option A : Risk planning meetings.
Option B : Documentation reviews.
Option C : Data precision rankings.
Option D : Diagramming techniques.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Risk planning meetings.
Best PMP Exam Practice Question No 6
All of the following statements concerning project stakeholders are true except :
Option A : Differences between or among stakeholders should be resolved in favor of the customer.
Option B : Managing stakeholder expectations may be difficult because stakeholders often have very different objectives, that may come into conflict.
Option C : Project stakeholders may influence the course of the project and its results.
Option D : Differences between or among stakeholders should be resolved in the most cost efficient manner consistent with project objectives.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Differences between or among stakeholders should be resolved in the most cost efficient manner consistent with project objectives.
Free PMP Exam Prep Question No 7
Which of the following is the output of Source Selection?
Option A : Proposals.
Option B : Evaluation criteria.
Option C : Contract negotiation
Option D : Contract.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Contract.
Latest PMP Exam Question No 8
Which of the following statements is not true?
Option A : Standards and regulations are mandatory.
Option B : According to ISO, standards are not mandatory, but regulations are.
Option C : Standards often begin as guidelines that are not mandatory. With later widespread adoption, they can become de facto regulations.
Option D : Standards and regulations are socio-economic influences to a project.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Standards and regulations are mandatory.
PMI PMP Exam Practice Question No 9
Which type of leadership is best suited for optimizing team performance in projects?
Option A : Democratic leadership.
Option B : Participative leadership.
Option C : Autocratic leadership.
Option D : Benevolent authoritative leadership.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Participative leadership.
PMP Certification Exam Agile Question No 10
Where is the result node (outcome) shown on a typical Ishikawa or Fishbone diagram?
Option A : Top.
Option B : Bottom.
Option C : Right hand side.
Option D : Center.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Right hand side.