Hi PMP aspirants, welcome to AKVTutorials. Seeking a comprehensive set of PMP Project Management Professional practice questions to reinforce your understanding of key topics? Revolutionize your approach to PMP preparation with our Practice Questions—your secret weapon for conquering the Project Management Professional exam. In this article, you will get Most Realistic PMP Exam Questions Test Paper 117 Answer Keys. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
You have been asked to coordinate the visit of a number of key stakeholders to a project site in foreign country. Your local contract advices that you must pay a per-person fee to arrange for efficient processing through the airport security checks. One member of the delegation has concurred that this is necessary based on previous experience. What if any, steps should you take prior to making the payment?
Option A : Reduce the size of the delegation to avoid the unbudgeted, aided cost.
Option B : Confirm that the transaction is legitimate not a bribe.
Option C : Refuse to make the payment.
Option D : Investigate the situation upon arrival at the airport
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Confirm that the transaction is legitimate not a bribe.
PMP Exam Preparation Test Question No 2
You have developed a very positive , informal relationship with your client. Over coffee, your clients indicates that his company is about to benefit from a very large multi million dollar contracts. He speculates that the stock price will jump up the day after tomorrow. At a social event , you learn that your manager’s wife who has invested in the company previously ask you how things are going and what the future prospects might be. What do you tell her?
Option A : Share the details of your conversation with the client. And recommended that now may be a good time to invest.
Option B : Suggest that she have your manager, her husband, contract your client directly to talk about the company’s potential.
Option C : Advise your manager’s wife that you must honor and maintain the confidentiality and privacy of your client and client information.
Option D : Tell her that you have no idea how the company is doing financially as you are concerned as with the specifics of the projects.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Advise your manager’s wife that you must honor and maintain the confidentiality and privacy
of your client and client information.
PMP Exam Sample Exam Question No 3
A control chart for a major project process shows that seven consecutive data points of the nine sample averages are above the process average within the control limits. What is indicated by the phenomenon?
Option A : The process average is moving to the upper values and needs to be corrected.
Option B : No action is required because the points are still within the control limits.
Option C : The process is out of control and should be investigated.
Option D : This is consider abnormal behavior and should be investigated.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
This is consider abnormal behavior and should be investigated.
PMP Certification Exam Question No 4
From the “view exhibit” button , Which task(s) have a CPI over budget?
Option A : Task 2 only.
Option B : Task 3 and 4.
Option C : Task 3 and 2.
Option D : Task 1 and 2
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Task 2 only.
Free PMP Practice Exam Question No 5
What is incorrect, or the least true statement about a benefit /cost analysis?
Option A : It should be performed again during project execution using the EAC projections
Option B : It should use present value techniques.
Option C : Never looks beyond the end of the project.
Option D : It should only be performed again after a project is started using the original data
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
It should only be performed again after a project is started using the original data
Best PMP Exam Practice Question No 6
From the “view exhibit” what would the best statement be about the overall project performance?
Option A : We are tracking slightly behind schedule and under budget more than 10%.
Option B : We are tracking slightly behind schedule and are right on target with the budget.
Option C : We are right on schedule and a little over the budget.
Option D : We are tracking slightly behind the schedule and a little over the budget.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
We are tracking slightly behind schedule and under budget more than 10%.
Free PMP Exam Prep Question No 7
You are under pressure to release a new version of software program to avoid serious cash penalties and loss of market share. Two days before the targeted release date, a developer brings a potential bug to your attention .Although the developer and a test engineer have been unable to re-create the bug, the feature in question is critical to meeting legal requirements dictated by the governing regulatory body responsible for public safety. What should you do?
Option A : Postpone the release date.
Option B : Re-assemble the test team and continue the testing until the bug is detected and corrected.
Option C : Re-assemble the test team and continue testing. Develop potential scenarios and advise the appropriate stakeholders of the recommended course of action.
Option D : Release the software and add the item to the list of issues to be addressed by the next patch or release.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Re-assemble the test team and continue testing. Develop potential scenarios and advise the appropriate stakeholders of the recommended course of action.
Latest PMP Exam Question No 8
Regarding management and leadership all of the following are true except:
Option A : On a project, particularly a larger project, the project manager is generally expected to be the project’s leader as well.
Option B : Technical leadership is of primary importance in project management.
Option C : Managing is primarily concerned with consistently producing key results expected by
stakeholders.
Option D : Leading involves establishing direction, aligning people, motivating and inspiring.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Technical leadership is of primary importance in project management.
PMI PMP Exam Practice Question No 9
A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000.
1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.
2. The second project would be the development of a new product which could produce the following net profits after the end of the project:
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000
Assumed is a discount rate of 5 % per year. Looking at the present values of these projects’ revenues in the first 3 years, what is true?
Option A : Both projects are equally attractive.
Option B : The first project is more attractive by app. 7%.
Option C : The second project is more attractive by app. 5%.
Option D : The first project is more attractive by app. 3%.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The first project is more attractive by app. 3%.
PMP Certification Exam Agile Question No 10
A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The acceptable control limits are 19.955 cm and 20.045 cm. The measurements made at the end of the process yielded the following results: 20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm, 19.963 cm, 19.958 cm, 19.962 cm, 19.979 cm, 19.959 cm. What should be done?
Option A : The process is under control. It should not be adjusted.
Option B : The process should be adjusted.
Option C : The control limits should be adjusted.
Option D : The measuring equipment should be recalibrated.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
The process should be adjusted.