Hi PMP aspirants, welcome to AKVTutorials. Ready to boost your confidence and mastery of PMP concepts through targeted practice questions? Supercharge your PMP readiness with our Practice Questions—an indispensable tool in your Project Management Professional certification arsenal. In this article, you will get Free Sample PMP Exam Test 65 Questions Paper with Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
You have been promoted to Manager, Continuous Process Improvement. Your new position:
Option A : Is a project because the work will be performed by people
Option B : Is not a project because Continuous Process Improvement will continue indefinitely
Option C : Is a project because it is constrained by limited resources
Option D : Is a project because improvements must be planned, executed, and controlled
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Is not a project because Continuous Process Improvement will continue indefinitely
PMP Mock Test Question No 2
Which of the following is not a Project Management knowledge area?
Option A : Project Quality Management
Option B : Project Procurement Management
Option C : Project Configuration Management
Option D : Project Risk Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project Configuration Management
PMP Practice Exam Question No 3
In a matrix organization, which of the following is not a responsibility of the project manager?
Option A : Complete task definitions
Option B : Resource requirement definitions
Option C : Major timetable milestones
Option D : Personnel performance measurements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Personnel performance measurements
PMP Mock Exam Question No 4
Of the following, which usually exhibits the slowest rate of change?
Option A : People
Option B : Technology
Option C : Organizations
Option D : The Environment
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
People
Project Management Professional Question No 5
The state of being totally answerable for the satisfactory completion of a specific assignment is called:
Option A : Authority
Option B : Accountability
Option C : Responsibility
Option D : Fiduciary
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Accountability
PMP Certification Prep Question No 6
During the planning phase of your current project, you prepare a detailed financial plan. For this process, you are using:
Option A : A general management skill
Option B : An industry specific skill
Option C : A skill that is common to general management and project management
Option D : A project management skill
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
A skill that is common to general management and project management
PMP Exam Question No 7
You are responsible for the communication controls for the Genesis series of satellites. Your current assignment is:
Option A : Project management
Option B : Functional management
Option C : Facility management
Option D : Program management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Program management
PMP Exam Sample Question No 8
Which of the following knowledge areas are part of Project Closure?
Option A : Communications
Option B : Scope
Option C : Cost
Option D : Human Resources
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Communications
PMP Exam Practice Question No 9
The process of determining who needs what information, when they need it, and how it will be given to them is:
Option A : Information distribution
Option B : Communications requirements
Option C : Communications planning
Option D : Communications management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Communications planning
PMP Certification Exam Question No 10
Communication planning is most tightly linked with what process:
Option A : Cost estimating
Option B : Organizational planning
Option C : Cost budgeting
Option D : Performance reporting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Organizational planning