Hi PMP aspirants, welcome to AKVTutorials. Do you need a reliable source for PMP Project Management Professional practice questions to assess your readiness? Seamlessly integrate PMP success into your journey using our Practice Questions—a must-have resource for Project Management Professional excellence. In this article, you will get Free PMP Practice Exam Questions Prep Test 54. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
While performing schedule management on your project, you need to determine the relationships between activities so that those activities are sequenced in the proper order. Which of the following is not true about activity sequencing?
Option A : It involves identifying and documenting relationships among tasks.
Option B : It defines the logical sequence of work given certain constraints.
Option C : It includes assigning resources to activities.
Option D : Every task (except for the first and last) should have both a predecessor and a successor.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
It includes assigning resources to activities.
PMP Mock Test Question No 2
A construction team can install carpet in a building fifteen days after they begin painting. This is an example of a/an:
Option A : Task
Option B : Lead
Option C : Activity
Option D : Lag
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Lag
PMP Practice Exam Question No 3
After we identify risks that could impact the success of our project and make assessments of their probability and impact, we can begin quantitative risk analysis. In doing so, we may use ______, which helps to determine the individual project risks that have the most potential impact on project outcomes. One way of displaying this information is through a Tornado diagram.
Option A : Sensitivity Analysis
Option B : Decision Tree Analysis
Option C : Monte Carlo Simulation
Option D : Delphi Techniques
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Sensitivity Analysis
PMP Mock Exam Question No 4
A project to train soldiers for an overseas mission has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. At this time, the scope is clearly defined, and the project manager does not expect any significant changes. She would also like to offer bonuses if the vendors meet certain predefined objectives. In this scenario, which type of contract should be utilized?
Option A : Cost Plus Incentive Fee (CPIF)
Option B : Fixed Price Incentive Fee (FPIF)
Option C : Fixed Price with Economic Price Adjustment (FP-EPA)
Option D : Cost Plus Award Fee (CPAF)
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Fixed Price Incentive Fee (FPIF)
Project Management Professional Question No 5
A project to train a company’s accountants on new bookkeeping software has begun. Currently, the team is performing the create WBS process. In doing so, which of the following activities might they complete?
Option A : Determining which of the documented requirements will be completed as part of the project.
Option B : Meeting with stakeholders to capture their needs and to ensure they are measureable.
Option C : Splitting the work of the project to make it easier to manage and monitor.
Option D : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Splitting the work of the project to make it easier to manage and monitor.
PMP Certification Prep Question No 6
A project manager is working with a team to construct a new toll road that will connect two cities. At this point, she needs to understand how to deal with defects in project deliverables when they are identified. Which document should be reviewed to find this information?
Option A : Quality Audits
Option B : Quality Control Measurements
Option C : Risk Management Plan
Option D : Quality Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Quality Management Plan
PMP Exam Question No 7
As a project manager, you know that your projects are impacted by factors that are often outside of your control. Those factors could be internal or external to your organization, and they could have a positive or negative impact. Organizational process assets are one such example. Which of the following is considered an organizational process asset?
Option A : Political Climate
Option B : Existing Human Resources
Option C : Change Control Procedures
Option D : Geographic Distribution of Facilities
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Change Control Procedures
PMP Exam Sample Question No 8
You are working for a car company and are leading a project to construct a new battery factory. Currently, the team is performing the plan risk management process. In doing so, which of the following activities might they complete?
Option A : Exploring options for addressing risks that have been previously identified.
Option B : Determining the stakeholders’ appetite for risk.
Option C : Meeting with project team members to brainstorm sources of overall project risk.
Option D : Determining which risks to transfer to a third party
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Determining the stakeholders’ appetite for risk.
PMP Exam Practice Question No 9
A project manager has created a dashboard for stakeholders that summarizes the overall status of the project. Among other information, it shows upcoming milestones and whether or not those milestones are expected to complete on time. This dashboard would be classified as which type of project information?
Option A : Work Performance Information
Option B : Work Performance Data
Option C : Enterprise Environmental Factors
Option D : Work Performance Reports
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Work Performance Reports
PMP Certification Exam Question No 10
As you work with your sponsor, you communicate how the structure of your organization influences the delivery of your project. Given that your company is considered a functional organization, all of the following would be true except:
Option A : Functional managers hold more authority than project managers
Option B : Resource availability for projects is moderate
Option C : Functional managers control the budget
Option D : Project managers have roles that are part-time
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Resource availability for projects is moderate