Hi PMP aspirants, welcome to AKVTutorials. Do you need a reliable source for PMP Project Management Professional practice questions to assess your readiness? Seamlessly integrate PMP success into your journey using our Practice Questions—a must-have resource for Project Management Professional excellence. In this article, you will get Free PMP Practice Exam Questions Prep Test 54. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

While performing schedule management on your project, you need to determine the relationships between activities so that those activities are sequenced in the proper order. Which of the following is not true about activity sequencing?

Option A : It involves identifying and documenting relationships among tasks.

Option B : It defines the logical sequence of work given certain constraints. 

Option C : It includes assigning resources to activities. 

Option D : Every task (except for the first and last) should have both a predecessor and a successor.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

It includes assigning resources to activities.

PMP Mock Test Question No 2

A construction team can install carpet in a building fifteen days after they begin painting. This is an example of a/an:

Option A : Task 

Option B : Lead 

Option C : Activity 

Option D : Lag

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Lag

PMP Practice Exam Question No 3

After we identify risks that could impact the success of our project and make assessments of their probability and impact, we can begin quantitative risk analysis. In doing so, we may use ______, which helps to determine the individual project risks that have the most potential impact on project outcomes. One way of displaying this information is through a Tornado diagram.

Option A : Sensitivity Analysis 

Option B : Decision Tree Analysis 

Option C : Monte Carlo Simulation 

Option D : Delphi Techniques

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Sensitivity Analysis 

PMP Mock Exam Question No 4

A project to train soldiers for an overseas mission has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. At this time, the scope is clearly defined, and the project manager does not expect any significant changes. She would also like to offer bonuses if the vendors meet certain predefined objectives. In this scenario, which type of contract should be utilized?

Option A : Cost Plus Incentive Fee (CPIF) 

Option B : Fixed Price Incentive Fee (FPIF) 

Option C : Fixed Price with Economic Price Adjustment (FP-EPA)

Option D : Cost Plus Award Fee (CPAF)

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Fixed Price Incentive Fee (FPIF) 

Project Management Professional Question No 5

A project to train a company’s accountants on new bookkeeping software has begun. Currently, the team is performing the create WBS process. In doing so, which of the following activities might they complete?

Option A : Determining which of the documented requirements will be completed as part of the project. 

Option B : Meeting with stakeholders to capture their needs and to ensure they are measureable. 

Option C : Splitting the work of the project to make it easier to manage and monitor. 

Option D : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 Splitting the work of the project to make it easier to manage and monitor. 

PMP Certification Prep Question No 6

A project manager is working with a team to construct a new toll road that will connect two cities. At this point, she needs to understand how to deal with defects in project deliverables when they are identified. Which document should be reviewed to find this information?

Option A : Quality Audits 

Option B : Quality Control Measurements 

Option C : Risk Management Plan 

Option D : Quality Management Plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Quality Management Plan

PMP Exam Question No 7

As a project manager, you know that your projects are impacted by factors that are often outside of your control. Those factors could be internal or external to your organization, and they could have a positive or negative impact. Organizational process assets are one such example. Which of the following is considered an organizational process asset?

Option A : Political Climate 

Option B : Existing Human Resources

Option C : Change Control Procedures 

Option D : Geographic Distribution of Facilities

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Change Control Procedures 

PMP Exam Sample Question No 8

You are working for a car company and are leading a project to construct a new battery factory. Currently, the team is performing the plan risk management process. In doing so, which of the following activities might they complete?

Option A : Exploring options for addressing risks that have been previously identified. 

Option B : Determining the stakeholders’ appetite for risk. 

Option C : Meeting with project team members to brainstorm sources of overall project risk. 

Option D : Determining which risks to transfer to a third party

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Determining the stakeholders’ appetite for risk. 

PMP Exam Practice Question No 9

A project manager has created a dashboard for stakeholders that summarizes the overall status of the project. Among other information, it shows upcoming milestones and whether or not those milestones are expected to complete on time. This dashboard would be classified as which type of project information?

Option A : Work Performance Information 

Option B : Work Performance Data

Option C : Enterprise Environmental Factors 

Option D : Work Performance Reports

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Work Performance Reports

PMP Certification Exam Question No 10

As you work with your sponsor, you communicate how the structure of your organization influences the delivery of your project. Given that your company is considered a functional organization, all of the following would be true except:

Option A : Functional managers hold more authority than project managers 

Option B : Resource availability for projects is moderate 

Option C : Functional managers control the budget 

Option D : Project managers have roles that are part-time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Resource availability for projects is moderate 

PMP Certification Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply