Free PMP Exam Questions Test 64 with Answers Keys

Hi PMP aspirants, welcome to AKVTutorials. Need a reliable source of PMP Project Management Professional practice questions to reinforce your exam preparation strategy? Empower your PMP preparation with our Practice Questions—a tailored resource sculpted for Project Management Professional triumph. In this article, you will get Free PMP Exam Questions Test 64 with Answers Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A Project Manager is most likely to have the strongest influence in an organization that is:

Option A : Balanced Matrix

Option B : Functional 

Option C : Projectized 

Option D : Strong Matrix

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Projectized

PMP Mock Test Question No 2

Project Management processes are:

Option A : A series of actions bringing about a result 

Option B : Concerned with describing and organizing the work of the project 

Option C : Concerned with specifying and creating the product 

Option D : Broken into core and non-core processes

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Concerned with describing and organizing the work of the project

PMP Practice Exam Question No 3

Executing processes are concerned with: 

Option A : Recognizing that a project or phase should begin 

Option B : Coordinating people and other resources to carry out the plan

Option C : Devising and maintaining a workable method to accomplish the business need that the project was undertaken to address 

Option D : Ensuring that the project objectives are met by monitoring and measuring progress and taking corrective action when necessary

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Coordinating people and other resources to carry out the plan

PMP Mock Exam Question No 4

Controlling processes are concerned with:

Option A : Coordinating people and other resources to carry out the plan 

Option B : Recognizing that a project or phase should begin

Option C : Ensuring that the project objectives are met by monitoring and measuring progress and taking corrective action when necessary

Option D : Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Ensuring that the project objectives are met by monitoring and measuring progress and taking corrective action when necessary

Project Management Professional Question No 5

A complex project will fit best in what type of organization? 

Option A : Functional 

Option B : Cross-functional 

Option C : Matrix 

Option D : Balanced

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Matrix 

PMP Certification Prep Question No 6

Core planning processes: 

Option A : Include scope planning, cost planning, schedule planning and performance reporting.

Option B : Provide a framework for the project 

Option C : Are used to track the progress of a project 

Option D : Have clear dependencies so they must be executed in essentially the same order on most project

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Have clear dependencies so they must be executed in essentially the same order on most project

PMP Exam Question No 7

 In a weak matrix organization, functional managers are usually responsible for: 

Option A : Monitoring personnel performance 

Option B : Approval for changes to the project schedule 

Option C : Monitoring their project team member’s deliverables 

Option D : Changes that impact their team member’s participation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Monitoring personnel performance 

PMP Exam Sample Question No 8

As a Project Manager on replacing 2 miles of sewer pipe part of your job is to determine if there are changes to the scope of the project, the schedule, the budget and the technical requirements. These responsibilities are part of which process: 

Option A : Executing

Option B : Controlling 

Option C : Planning 

Option D : Closing 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Controlling 

PMP Exam Practice Question No 9

You are one of four full-time project managers in an organization. You all share an administrative person. There are generally 8-10 projects per year that involve about 25% of the organization’s employees, however, these employees do not report to you. Your organization can best be classified as:

Option A : Functional 

Option B : Strong matrix 

Option C : Projectized 

Option D : Balanced matrix 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Balanced matrix 

PMP Certification Exam Question No 10

During the course of a project you have motivated team members, managed conflict, performed personnel administrative functions and negotiated for more resources. These are examples of:

Option A : General Management 

Option B : Project Human Resource Management 

Option C : Project Execution

Option D : A Projectized organization

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

General Management 

PMP Mock Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply