Free PMP Exam Prep Test 62 Questions

Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want access to realistic practice questions for a thorough self-assessment? Unleash your PMP potential with our Practice Questions—your key to mastering the art of Project Management Professional certification. In this article, you will get Free PMP Exam Prep Test 62 Questions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A company that develops software for banks has decided to setup a PMO. Their goal is to increase the likelihood that each of their projects is successful. They have determined that the PMO will require project teams to comply with a set of requirements. Which type of PMO would this represent?

Option A : Supportive 

Option B : Controlling 

Option C : Directive 

Option D : Strategic

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Controlling 

PMP Mock Test Question No 2

A project to procure and configure a tool for tracking sales leads at a security company is ongoing. Currently, the team is performing the validate scope process. In doing so, which of the following activities might they complete?

Option A : Determining which of the documented requirements will be completed as part of the project.

Option B : Reviewing verified deliverables with the sponsor to confirm they have been completed properly

Option C : Evaluating the completion of project deliverables and preventing scope creep. 

Option D : Splitting the work of the project to make it easier to manage and monitor.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Reviewing verified deliverables with the sponsor to confirm they have been completed properly

PMP Practice Exam Question No 3

You were recently hired by a shipping company to lead a high priority project. Before moving forward, you understand that the structure of your organization will influence your work – whether for good or bad. The shipping company is considered a projectized organization. Which of the following is not true about that organizational type?

Option A : Project managers hold more authority than functional managers 

Option B : Resource availability for projects is high

Option C : Project managers control less of the budget than functional managers 

Option D : Project managers have project management staff that are full-time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project managers control less of the budget than functional managers 

PMP Mock Exam Question No 4

Early in your project, you have determined that you will use surveys and interviews as a means to gather requirements from your stakeholders. All of the following would be true about those requirements or the requirements documentation except:

Option A : They describe what the customer or sponsor needs. 

Option B : They describe how requirements meet business objectives. 

Option C : They can be in written or verbal format. 

Option D : The format of requirements documentation may vary from simple list to complicated matrices.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 They can be in written or verbal format. 

Project Management Professional Question No 5

A project to expand a wind farm was undertaken in a coastal community to begin their shift to renewable energy. During the project, the team spends time performing quantitative analysis on the risks that have been identified. What is a tool or technique that may be needed to perform this process?

Option A : Sensitivity Analysis 

Option B : Meetings 

Option C : Risk Report 

Option D : Risk Probability & Impact Assessment

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Sensitivity Analysis 

PMP Certification Prep Question No 6

A small company works closely with their customers, and they want to provide those customers with rapid feedback on their deliverables and make immediate adjustments, when needed. Which project lifecycle would be the best fit for their situation?

Option A : Predictive

Option B : Waterfall 

Option C : Phased 

Option D : Adaptive

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

 Adaptive

PMP Exam Question No 7

You are a leading a project that involves planning and executing a cultural celebration. At this point on the project, you are in the process of closing a phase. Which of the following are inputs of that process?

Option A : Project Management Plan, Accepted Deliverables, Procurement Documentation

Option B : Accepted Deliverables, Approved Change Requests, Agreements

Option C : Business Documents, Change Requests, Deliverables 

Option D : Procurement Documentation, Project Charter, Verified Deliverables

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Project Management Plan, Accepted Deliverables, Procurement Documentation

PMP Exam Sample Question No 8

A project manager is working with a team to plan and host a major sporting event. At this point, she needs to understand what an acceptable range would be as cost estimates are prepared (e.g. +/-20%). Which document should be reviewed to find this information?

Option A : Cost Variance 

Option B : Risk Management Plan 

Option C : Cost Management Plan 

Option D : Cost Baseline

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Cost Management Plan 

PMP Exam Practice Question No 9

A project to construct several wind turbines to begin a town’s shift to renewable sources of energy is underway. Currently, the team is performing the develop schedule process. In doing so, which of the following activities might they complete?

Option A : Adjusting start and finish dates of activities based on the availability of resources. 

Option B : Mapping the flow of activities to most efficiently complete the work given various constraints. 

Option C : After comparing the schedule baseline to actual performance, shortening durations by applying more resources to project activities. 

Option D : Evaluating project scope and required resources in order to approximate the number of work periods needed to complete the activities.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Adjusting start and finish dates of activities based on the availability of resources. 

PMP Certification Exam Question No 10

A project manager is preparing a risk management plan for a project that includes purchasing and configuring a fleet of buses for large city. Which of the following would not be included in that document?

Option A : The procedures for how management or contingency reserves will be used

Option B : A description of the format that will be used to report threat and opportunities on the project 

Option C : The list of identified risks and potential risks responses 

Option D : The funds that will be needed to respond to risks on the project

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 The list of identified risks and potential risks responses

PMP Mock Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply