Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want access to realistic practice questions for a thorough self-assessment? Unleash your PMP potential with our Practice Questions—your key to mastering the art of Project Management Professional certification. In this article, you will get Free PMP Exam Prep Test 62 Questions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
A company that develops software for banks has decided to setup a PMO. Their goal is to increase the likelihood that each of their projects is successful. They have determined that the PMO will require project teams to comply with a set of requirements. Which type of PMO would this represent?
Option A : Supportive
Option B : Controlling
Option C : Directive
Option D : Strategic
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Controlling
PMP Mock Test Question No 2
A project to procure and configure a tool for tracking sales leads at a security company is ongoing. Currently, the team is performing the validate scope process. In doing so, which of the following activities might they complete?
Option A : Determining which of the documented requirements will be completed as part of the project.
Option B : Reviewing verified deliverables with the sponsor to confirm they have been completed properly
Option C : Evaluating the completion of project deliverables and preventing scope creep.
Option D : Splitting the work of the project to make it easier to manage and monitor.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Reviewing verified deliverables with the sponsor to confirm they have been completed properly
PMP Practice Exam Question No 3
You were recently hired by a shipping company to lead a high priority project. Before moving forward, you understand that the structure of your organization will influence your work – whether for good or bad. The shipping company is considered a projectized organization. Which of the following is not true about that organizational type?
Option A : Project managers hold more authority than functional managers
Option B : Resource availability for projects is high
Option C : Project managers control less of the budget than functional managers
Option D : Project managers have project management staff that are full-time
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project managers control less of the budget than functional managers
PMP Mock Exam Question No 4
Early in your project, you have determined that you will use surveys and interviews as a means to gather requirements from your stakeholders. All of the following would be true about those requirements or the requirements documentation except:
Option A : They describe what the customer or sponsor needs.
Option B : They describe how requirements meet business objectives.
Option C : They can be in written or verbal format.
Option D : The format of requirements documentation may vary from simple list to complicated matrices.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
They can be in written or verbal format.
Project Management Professional Question No 5
A project to expand a wind farm was undertaken in a coastal community to begin their shift to renewable energy. During the project, the team spends time performing quantitative analysis on the risks that have been identified. What is a tool or technique that may be needed to perform this process?
Option A : Sensitivity Analysis
Option B : Meetings
Option C : Risk Report
Option D : Risk Probability & Impact Assessment
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Sensitivity Analysis
PMP Certification Prep Question No 6
A small company works closely with their customers, and they want to provide those customers with rapid feedback on their deliverables and make immediate adjustments, when needed. Which project lifecycle would be the best fit for their situation?
Option A : Predictive
Option B : Waterfall
Option C : Phased
Option D : Adaptive
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Adaptive
PMP Exam Question No 7
You are a leading a project that involves planning and executing a cultural celebration. At this point on the project, you are in the process of closing a phase. Which of the following are inputs of that process?
Option A : Project Management Plan, Accepted Deliverables, Procurement Documentation
Option B : Accepted Deliverables, Approved Change Requests, Agreements
Option C : Business Documents, Change Requests, Deliverables
Option D : Procurement Documentation, Project Charter, Verified Deliverables
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Project Management Plan, Accepted Deliverables, Procurement Documentation
PMP Exam Sample Question No 8
A project manager is working with a team to plan and host a major sporting event. At this point, she needs to understand what an acceptable range would be as cost estimates are prepared (e.g. +/-20%). Which document should be reviewed to find this information?
Option A : Cost Variance
Option B : Risk Management Plan
Option C : Cost Management Plan
Option D : Cost Baseline
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Cost Management Plan
PMP Exam Practice Question No 9
A project to construct several wind turbines to begin a town’s shift to renewable sources of energy is underway. Currently, the team is performing the develop schedule process. In doing so, which of the following activities might they complete?
Option A : Adjusting start and finish dates of activities based on the availability of resources.
Option B : Mapping the flow of activities to most efficiently complete the work given various constraints.
Option C : After comparing the schedule baseline to actual performance, shortening durations by applying more resources to project activities.
Option D : Evaluating project scope and required resources in order to approximate the number of work periods needed to complete the activities.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Adjusting start and finish dates of activities based on the availability of resources.
PMP Certification Exam Question No 10
A project manager is preparing a risk management plan for a project that includes purchasing and configuring a fleet of buses for large city. Which of the following would not be included in that document?
Option A : The procedures for how management or contingency reserves will be used
Option B : A description of the format that will be used to report threat and opportunities on the project
Option C : The list of identified risks and potential risks responses
Option D : The funds that will be needed to respond to risks on the project
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The list of identified risks and potential risks responses