Free PMP Exam Prep Test 45 Questions Answer Keys

Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and in search of practice questions that emphasize the principles of benefits realization management? Emphasize benefits realization management with our PMP practice questions, ensuring your readiness to achieve project objectives and outcomes. In this article, you will get Free PMP Exam Prep Test 45 Questions Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

On a project to educate users on how use “two-factor authentication” to protect their bank accounts, the team spends time improving team skills and relations to enhance project performance. What is an input to that particular process?

Option A : Resource Management Plan 

Option B : Team Performance Assessments

Option C : Conflict Management 

Option D : Leadership

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Resource Management Plan 

PMP Mock Test Question No 2

On a given project; earned value (EV) is $30,000; actual cost (AC) is $35,000; and planned value (PV) is $28,000. What is the schedule performance index (SPI)?

Option A : 0.86 

Option B : 1.16 

Option C : 1.07

Option D : 0.93

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

1.07

PMP Practice Exam Question No 3

At a grocery store chain, a project is in process to deploy self-checkout registers at all of the company’s California locations. During the project, the team spends time creating and using knowledge to support the project and the organization. What is a tool or technique that may be needed to perform this process?

Option A : Lessons Learned Register 

Option B : Project Management Information System 

Option C : Information Management 

Option D : Issue Log

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Information Management 

PMP Mock Exam Question No 4

As a team, you have already planned and implemented responses to risks that were identified. Your task now is to monitor those risks. Which of the following are inputs to that process?

Option A : Risk Register, Work Performance Information, Risk Report 

Option B : Risk Report, Work Performance Reports, Stakeholder Register 

Option C : Project Management Plan, Issue Log, Agreements 

Option D : Risk Management Plan, Work Performance Data, Risk Register

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Risk Management Plan, Work Performance Data, Risk Register

Project Management Professional Question No 5

A project team is designing a bracelet with a microchip that allows parents to track the location of their children. During the project, the team identifies quality requirements and documents how to comply with them. What is a tool or technique that may be needed to perform this process?

Option A : Test & Inspection Planning 

Option B : Quality Improvement Methods 

Option C : Checklists 

Option D : Statistical Sampling

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Test & Inspection Planning 

PMP Certification Prep Question No 6

Which of the following is true about predictive life cycles?

Option A : Requirements and plans are handled and expanded on frequently during delivery 

Option B : Delivery is divided into subsets of the overall product 

Option C : Risk and costs are controlled as requirements and constraints emerge 

Option D : Change is limited as much as possible

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Change is limited as much as possible

PMP Exam Question No 7

A project has been funded by a local government to study the causes of a series of car accidents that have occurred at the same intersection. During the project, the team spends time managing procurement relationships and monitoring contractor performance. Which of the following is not a tool or technique that may be needed to perform this particular process?

Option A : Variance Analysis 

Option B : Earned Value Analysis 

Option C : Performance Reviews

Option D : Proposal Evaluation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Proposal Evaluation

PMP Exam Sample Question No 8

At this point on your project, you are in the process of developing the project management plan, which will integrate several other plans, such as the cost management plan and schedule management plan, into one document. Which of the following are inputs of that process?

Option A : Outputs from Other Processes, Business Documents, Project Documents

Option B : Project Charter, Approved Changed Requests, Deliverables

Option C : Project Charter, Outputs from Other Processes, Organizational Process Assets 

Option D : Organizational Process Assets, Enterprise Environmental Factors, Agreements

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project Charter, Outputs from Other Processes, Organizational Process Assets 

PMP Exam Practice Question No 9

On a given project; earned value (EV) is $250,000; actual cost (AC) is $215,000; and planned value (PV) is $300,000. What is the cost performance index (CPI)?

Option A : 0.86

Option B : 1.16 

Option C : 0.83

Option D : 1.2

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

1.16 

PMP Certification Exam Question No 10

On a project to overhaul a city’s waste management system, the team spends time detecting threats and opportunities that may impact the project. In this case, what process is being performed?

Option A : Plan Risk Management 

Option B : Plan Risk Responses 

Option C : Implement Risk Responses 

Option D : Identify Risks

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Identify Risks

PMP Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply