Hi PMP aspirants, welcome to AKVTutorials. Ready to test your knowledge and skills with a diverse set of PMP Project Management Professional practice questions? Dive into PMP success with our Practice Questions—a strategic blend of challenge and insight for Project Management Professional aspirants. In this article, you will get Free PMP Exam Practice Test 61 Questions And Solutions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
On a project to launch a satellite that will explore and provide data about black holes, the team spends time documenting how scope will be defined and controlled. What is a tool or technique that may be needed to perform this process?
Option A : Voting
Option B : Benchmarking
Option C : Meetings
Option D : Decomposition
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Meetings
PMP Mock Test Question No 2
When considering adaptive projects, which of the following is not true?
Option A : If the project has high variability, a team with generalized specialists would be ideal
Option B : Project artifacts should not be broadly shared among stakeholders
Option C : Lightweight estimates are often used for a fast, high-level forecast
Option D : Detailed estimates are provided in a “just-in-time” fashion
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Project artifacts should not be broadly shared among stakeholders
PMP Practice Exam Question No 3
A project manager is working with a team to cleanup a hazardous waste site. During the project, she will need to work with several different parties that will be affected the project, including government officials and the local community, to ensure the project is successful. Which document outlines strategies for promoting the productive involvement of these parties?
Option A : Communication Styles Assessment
Option B : Stakeholder Register
Option C : Stakeholder Engagement Plan
Option D : Communications Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Stakeholder Engagement Plan
PMP Mock Exam Question No 4
A project manager is preparing a resource management plan for a project that includes building a new military training complex. Which of the following would not be included in that document?
Option A : An explanation of how the team will ensure adequate physical resources are available
Option B : A project organizational chart that shows reporting relationships for various team members
Option C : A description of how resources will be identified and acquired
Option D : An explanation of values, agreements, and operating guidelines for the team
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
An explanation of values, agreements, and operating guidelines for the team
Project Management Professional Question No 5
You are currently meeting with several qualified vendors, who may provide products or services needed to complete the project work, prior to their submission of proposals. It provides them an opportunity to ask questions about what is needed. This scenario reflects which of the following processes?
Option A : Conduct Procurements
Option B : Plan Procurement Management
Option C : Control Procurements
Option D : Plan Stakeholder Engagement
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Conduct Procurements
PMP Certification Prep Question No 6
Which of the following is not true about risk management on agile projects?
Option A : Risk and uncertainty is higher than on waterfall projects.
Option B : Risk is managed through frequent reviews of incremental work products.
Option C : Risk is identified, analyzed, and managed primarily at the beginning of the project.
Option D : Throughout the project, requirements may be reprioritized as risks are better understood.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Risk is identified, analyzed, and managed primarily at the beginning of the project.
PMP Exam Question No 7
On a construction project, you must get a permit from the local government before you start construction. This best describes which of the following dependencies?
Option A : Common
Option B : Discretionary
Option C : Internal
Option D : External
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
External
PMP Exam Sample Question No 8
A project to decommission a naval base that has been left in disrepair has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. At this time, the scope is clearly defined, and the project manager does not expect any significant changes. The project is expected to span 10 years. In this scenario, which type of contract should be utilized?
Option A : Firm Fixed Price (FFP)
Option B : Fixed Price Incentive Fee (FPIF)
Option C : Fixed Price with Economic Price Adjustment (FP-EPA)
Option D : Cost Plus Award Fee (CPAF)
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Fixed Price with Economic Price Adjustment (FP-EPA)
PMP Exam Practice Question No 9
Your project team has been tasked with developing an e-commerce website. At this time, the team is planning risk responses. In doing so, which of the following activities might they perform?
Option A : Conducting root cause analysis to pinpoint the source of a problem.
Option B : Taking action to increase the likelihood that opportunities on the project occur.
Option C : Determining if new risks have surfaced on the project — beyond those originally identified.
Option D : Determining which risks to transfer to a third party.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Determining which risks to transfer to a third party
PMP Certification Exam Question No 10
An aerospace company that sends small satellites into orbit has several projects that are funded by government customers. Prior to the start of those projects, the company had to show that they were compliant with several government standards. In this scenario, these marketplace conditions would be best classified as which of the following?
Option A : An organizational process asset
Option B : A procurement statement of work
Option C : An enterprise environmental factor
Option D : A marketplace condition
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
An organizational process asset