Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want access to realistic practice questions for a thorough self-assessment? Navigate the path to PMP mastery with our Practice Questions—a game-changing resource for Project Management Professional hopefuls.. In this article, you will get Free Exam Questions Paper 112 PMP. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
A playground fencing project was FPQ’d at $6 per foot. The play area has 4 equal side of 125 feet each and first requires the installation of 2 round cement posts for decorative purposes. 100 feet of fencing can be erected per day once the cement posts are installed. The 2 cement posts costs $250 to install and take one day for both to be installed. At the end of day three one side of the fence and 2/3 second side have been completed , What is the current status of the project?
Option A : the budget is on target with a 0 schedule variance.
Option B : It is behind schedule with a schedule variance of -$750.
Option C : It is under budget , with a cost variance of $500 with the completion of the cement posts.
Option D : It is over budget with a cost variance of $-500.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
the budget is on target with the 0 schedule variance
PMP Exam Preparation Test Question No 2
Which of the following is not aid in achieving consensus?
Option A : avoiding conflict.
Option B : maintaining a focus on the problem not each other.
Option C : avoiding self-oriented behavior.
Option D : Seeking facts.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
avoiding conflict
PMP Exam Sample Exam Question No 3
Project manager must carefully select the appropriate mode when managing conflict. Which of the following modes provide resolution when managing conflict?
Option A : withdrawal, smoothing.
Option B : compromising, forcing.
Option C : forcing, problem solving.
Option D : withdrawal, problem solving.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
forcing, problem solving
PMP Certification Exam Question No 4
During communications the sender is not responsible for:
Option A : Clarity.
Option B : Unambiguousness.
Option C : Completeness of message.
Option D : Correctness of understanding
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Correctness of understanding
Free PMP Practice Exam Question No 5
Which is not a tool or technique used in the quantitative risk analysis process?
Option A : interviewing.
Option B : SWOT analysis.
Option C : Sensitivity analysis
Option D : Simulation.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
SWOT Analysis
Best PMP Exam Practice Question No 6
Each project life cycle phase can act as a control point to measure progress and determine if the project should continue (go/no go decision ).These control points are called ______________.
Option A : Phase exit.
Option B : kill point.
Option C : Stage gate.
Option D : all of the above.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all of the above
Free PMP Exam Prep Question No 7
Given the following set of data: 40 20,20,50,70 and 75: what is the median?
Option A : 40
Option B : 50
Option C : 45
Option D : 20
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
45
Latest PMP Exam Question No 8
Which of the following are not example of barriers?
Option A : idea killers and negative positioning.
Option B : devil’s advocate and cultural differences.
Option C : amount of information, project jargon ,and terminology.
Option D : lack of subject knowledge and ” its never been done before”.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
amount of information, project jargon ,and terminology.
PMI PMP Exam Practice Question No 9
Internal rate of return is:
Option A : The present values of all cash flows.
Option B : The net present values of all cash flows.
Option C : The interest rate that equates the present value of expected future net cash inflows to the initial cost outlet.
Option D : the interest rate that equates all future cash inflows to zero
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The interest rate that equates the present value of expected future net cash inflows to the initial cost outlet.
PMP Certification Exam Agile Question No 10
Several months ago you completed an intranet design website project .This intranet site houses sensitive company data and high –security access is crucial. You are now working on another high security project and you notice what appears to be a flaw or hole ‘in ‘ the security code. However the access sequence is so obscure that you are certain no one has been able to break security yet. What should you do?
Option A : Keep the discovery to yourself but monitor the situation incase something does occur.
Option B : Alert your senior manager and ask that someone immediately confirm your findings.
Option C : Have someone immediately repair the perceived security flow.
Option D : Alter the security team.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Alert your senior manager and ask that someone immediately confirm your findings.